Committee Reports::Report - Office of Public Works::09 January, 1985::Appendix

APPENDIX 3

OIFIG NA nOIBREACHA POIBLI


51 FAICHE STIABHNA, BAILE ÁTHA CLIATH, 2.


OFFICE OF PUBLIC WORKS, 51 ST. STEPHEN’S GREEN, DUBLIN, 2.

TEILEAFÓN 767541


TAG

TEILEAGRAIM OIBRE


DO THAG

Mr P M Judge


Committee on Public Expenditure


Kildare House


Kildare Street


Dublin 2.


Dear Mr Judge


Further to your letter of 30 January and subsequent ‘phone discussions I enclose -


(i)details of works at Kilmainham,


(ii)details of other projects before the committee,


(iii)a statement showing office rents per square foot in the years 1981/3,


(iv)comments on the Sunday Independent article,


(v)details of office space rented by Office of Public Works 1973/80 in Dublin.


Yours sincerely



28 February 1984.


Enc


Kilmainham Warehouse

Lease commencement date 1/8/81

Preparation and clearance of basic brief of requirements

July, 1981.

Preparation of layout drawings by architect and detailed development of scheme leading to the production of tender documents including full Bill of Quantities and invitation of tenders.

July ’81 - June ’83

Tenders received, examined and contract placed

November, 1983

Contract completion due

January, 1985

Estimated total cost

£1.2m.

On 16th September, 1981 O.P.W. sought D/Finance sanction to lease the premises.


D/Finance sanction was granted by minute dated 26th November, 1981.


The premises when leased was in a very poor condition having been closed for four years previously and badly vandalised in the interim, with the exception of a new roof and floor in part of the complex, most of leased area was old, with roofs that leaked or were structurally unsound in part, floors either non-existent or in a bad state of repair, corroded window frames, no glazing, doorless opes internally, damp plaster and generally in very poor decorative order. As far as underground services e.g. water, electricity and gas were concerned, these had been brought to a point just inside the area and there were consequently no plumbing, electrical or heating services in existence internally.


Irrespective of the user therefore, the condition of the premises dictated in the first instance the need for a major reconstruction and building job and coupled with the specialised facilities required by the user meant that the entire planning and execution of works could not be regarded as “fitting-out” in its usual interpretation.


The property at Kilmainham was the only one on the market at the time, either for leasing or purchase, which had the potential of meeting the needs of the Furniture Division from the point of view of open floor area, enclosed yards, several entrances for easy movement of transport and fairly central location. The Furniture Division had been experiencing very severe organisational difficulties, because of lack of centralised furniture workshop and store, in their endeavours to meet the demands of all Gov. Departments. Their position was serious and aggravated by industrial action. The Kilmainham warehouse was considered to be the best solution to their problems.


The rent payable reflects the condition of the premises.


The functions to be catered for in the building included furniture manufacture and upholstery workshop storage of timbers, furniture, various floor coverings, antiques and other valuable items. The construction of an office development of some 6,700 sq. ft. over part of the leased premises was also required to cater for the administrative functions of the Furniture Division as there was insufficient space within the leased area for same.


From the beginning it was envisaged that a considerable amount of time would be required to bring the building into use. A programme of 33 months from receipt of D/Finance sanction was envisaged. In the event this has had to be extended and by January ’85 when the contract works, which are in progress at present, are due to be completed, the period will be 38 months.


The development of the project proved to be more complex than had been originally envisaged.


The formulation of a detailed brief of requirements covering specialised facilities for the proper storage conditions for raw timbers, veneers, sheets of plywood, hardboard etc. office furniture, polling booths, examination desks, antiques, carpet linoleum, upholstery materials, curtaining, china, crystal, silverware and other valuable items was an essential pre-requisite to detailed planning.


Considerable research had to be conducted into the workings of modern furniture workshops viz. the sequence of operation from delivery of materials to dispatch of furniture and the individual requirements of Woodwork and Machine shops, Cabinet makers’ workshops, Veneering workshops, Upholstery workshops, French Polishing workshops, paint spray areas and areas for the storage of varnishes, paints, glues and other potentially explosive atmospheres.


Fire regulations governing a building housing a furniture factory and store are particularly stringent. They had to be thoroughly researched and design decisions made having regard to various aspects e.g. the height of stacking in stores, the layouts of lanes between stacks of storage, escape routes and fire classification of various materials. The gasses given off by the varnishes glues etc. used in French polishing and paint spraying are, especially in paint spraying, extremely hazardous and had to be researched fully.


The design of the “high Risk” preventative systems necessary to meet fire and safety regulations and provide a safe working environment required careful consideration by all members of the Design Team in consultation with the Local Authority.


Sophisticated fire alarm systems (activated by smoke) high risk sprinkler installations, automatic smoke ventilations, dust extraction, compressed air installation and intruder alarm systems had to be fully researched in detail as there are many variations and the most appropriate systems had to be decided upon.


s adverted to earlier, full lighting and heating installations had also to be designed.


part from the major adaptation of the existing premises, plans were prepared or the construction of an office block of some 6706 sq. ft. over part of he premises.


he extent and nature of the works required at Kilmainham which are vastly ifferent from a normal “fitting-out job” dictated the need for the design team o prepare full contract documents consisting of detailed drawing specifications nd Bills of Quantities. Such details require a considerable amount of time to repare and would not normally be required for fitting-out modern office locks.


enders were invited in June 1983 and a tender accepted in November, 1983 subject to receipt of a bond. This was produced in December, 1983 and the contractor moved on site in Jan. 1984. Acceptance of a tender was delayed somewhat because of objections raised by the Local Authority about transport movement via residential roads to and from the property. These were cleared in October, 1983.


 


Sarsfield House, Limerick

Lease commencement date, 1/2/81

 

Preparation of briefs of requirements by Department

 

 

(1)

Education

July 1980

 

(2)

Fisheries and Forestry

Sept. 1981

+

Layout plans prepared by Architect and with Departments for consideration and approval

 

 

(1)

Education

July 1980 - Oct. 1980

 

(2)

Fisheries and Forestry

Sept 1981 - April 1982

+*

Preparation of tender documents, tenders invited, received and contracts placed.

 

 

(1)

Education

Oct. 1980 - Feb. 1981

 

(2)

Fisheries and Forestry


(extra on contract for Education take)

May 1982

 

Contract completed

 

 

(1)

Education

April 1981

 

(2)

Fisheries and Forestry

August 1982

 

Occupied

 

 

(1)

Education

April, 1982

 

(2)

Fisheries and Forestry

Nov. 1982

+

Fitting out cost approximately

£60,000

 

This accommodation on the third floor of the building was leased to provide accommodation for the Departments of Education and Fisheries and Forestry.


The Department of Education was originally to have been accommodated on a lower floor of the building, leased prior to 1981, but the area allocated was subsequently required for expansion by the Revenue Commissioners.


The Department of Fisheries and Forestry staff were relocated here from St. Munchin’s House to afford expansion space there, for the expanded Department of Agriculture staff numbers viz. the Veterinary Offices of the Disease Eradication Programme.


-93 Lr. Mount Street (Blocks 5 & 6

Lease commencement date - 6/2/81

 

Preparation of brief of requirements by the Revenue Commissioners

March, 1980 - April, 1981

+

Preparation of layout plans by Architect

April, 1981 - May, 1981

 

Layout plans with Department for consideration and approval

May, 1981 - June, 1981

 

Tender documents prepared and tenders invited

June, 1981 - July 1981

 

Tenders received, examined and Contract placed

July, 1981 - Oct. 1981

 

Completion following the execution of extra works, required by the D/Posts & Telegraphs to facilitate the telephone installation

- Feb. 1982

 

Building ready for occupation following the installation of floor covering and furniture

June 1982

 

Occupation commenced

June 1982

*

 

(see note re part not occupied)

The total cost of fitting out the building is approximately £745,000.


Smithfield Chambers

Lease commencement date 25/2/81

 

Preparation of brief of requirement by Department of Justice

Feb. 1981 - April, 1981

 

Preparation of layout plans by Architect

April 1981 - July, 1981

 

Layout plans with Department for consideration and approval

July 1981 - Aug, 1981

 

Tender documents prepared and tenders invited

Aug. 1981 - Oct. 1981

 

Tenders received, examined and Contract placed

Oct. 1981 - March 1982

*

Contract works due for completion

June, 1982

 

Actual completion

Nov. 1982

+

Carpeting, furnishing and security works followed

 

 

Building occupied

July, 1983

x

The cost of fitting out the building was approximately £295,000.


Finglas Shopping Centre

Lease commencement date 1/3/81

 

Layout plans based on requirements submitted by the Department of Labour when requesting that the accommodation be leased was forwarded for consideration and approval

June, 1980

 

Layout plans approved

June, 1980 - Aug. 1980

 

Tender documents prepared and tenders received

Aug. 1980 - Dec. 1980

 

Agreement on terms of letting reached with lessor

May, 1981

 

Tenders examined and contract placed

Oct. 1981

+

Occupied

Sept. 1982

*

Delay in placing contract was due to constraints imposed on O.P.W. in relation to expenditure because of the then current financial situation.


The fitting out works cost £43,000 approximately.


Offices in Tralee

Lease commencement date 29/6/81

Preparation and clearance of brief of requirements by Department of Labour

Feb. ’81

Preparation of layouts and clearance with Department

Sept. ’81

Preparation of tender documents and tenders invited

Sept. ’81

Tenders received, examined and contract placed

Oct. ’81

Contract works complete

Feb. ’82

Occupied

Apr. ’82

Cost £13,000 approximately

 

 

Lombard House

Lease commencement date 16/9/81

1.

Department of Health

 

 

Preparation of brief by Department

in stages from March ’81 - June ’81

 

Preparation of layout plans by architect

in stages from May ’81 - August ’81

 

Plans with Department for consideration and approval

in stages from May ’81 - October ’81

 

Preparation of tender documents and tenders invited

October ’81 - November ’81

 

Tenders received examined and contract placed

February ’82

 

Contract works due for completion

May ’82

 

Contract works completed (extra works required)

July ’82

 

Carpeting and furnishing followed

 

 

Occupied

November-December ’83 *

 

Cost of fitting out works approximately

£237,000

+The building was leased primarily to meet the requirements of the General Record Office from the Custom House where industrial action had been threatened because of existing conditions and to relieve overcrowding generally in the Department.


As soon as the precise amount of space required by the General Record Office was established by reference to the layout of the new accommodation, the space available for other sections was clear and decisions as to the exact sections which could be accommodated were made.


Following the preparation of initial sketch plans, further exploratory discussions were held with the Department on detail requirements and some amendments to the scheme proved necessary.


Preparation of layout plans by architect

June ’81 - August ’81

Layout plans with Department-Eastern Health Board for consideration and approval

July ’81 - December ’81 +

Preparation of tender documents, and tenders invited

December ’81 - March ’82

Tenders received

April ’82

Contract not yet placed

*

Estimated cost of fitting out works

=

70,000

Some amendments were necessary to the initial sketch plans prepared by the architect because of a change from open plan storage layout to the provision of a strong room for storage of records.


The delay in placing a contract is attributable to the following:-


Eastern Health Board did not agree sub-lease terms and lodge money to meet fitting out costs until

June ’82

Lessors approval then sought to sub-leasing the accommodation to the Eastern Health Board

July ’82

Lessors approval obtained subject to certain conditions one of which required planning permission to change of use

October ’82

Following discussion The Eastern Health Board then sought the permission and advised the Office of Public Works that this had been obtained subject to bye-law approval and consultation with the Chief Fire Officer and Chief Health Officer

June ’83

The approval of the Chief Health Officer has been obtained but as bye-law approval and views of the Chief Fire Officer have not been obtained a contract for the works cannot be placed.

September ’83

Gondon House (portion)

Lease commencement date 1/10/81

Preparation of brief of requirements by Department of Social Welfare

April 81 - July 1981

Preparation of layout plans by Architect

July ’81 - Oct. ’81

Layout plans with Department for consideration and approval

October 81 - Oct. 81

Preparation of tender documents and tenders invited

October 81 - Nov. ’81

Tenders received, examined and contract placed

November 81 - Feb. ’82

Contract works due for completion. Work had subsequently to be phased as part of accommodation became occupied. This delayed final completion date somewhat.

April 1982

Occupied:

 

partially

-

fitting-out works to be carried out while some staff in occupation - staff being switched from floor to floor as areas completed

December ’81

fully

-

 

August ’82

Fitting-out costs approximately

£65,000

Hibernian House, Galway


(part of 1st floor)

Lease Commencement date 5/11/81

Preparation of brief of requirements by Revenue Commissioners

April 81

Preparation of layout plans by Architect

May ’81 - June ’81

Layout plans with Department for consideration and approval

June ’81 - July ’81

Tender documents prepared and tenders invited

August ’81 - November ’81

Lessors approval as required under the terms of the lease awaited to proposed plans

November ’81 - May ’82

New tenders sought in view of lapse of time and contract placed

July ’82

Occupied:

August ’82

Fitting out cost approximately £50,000

 

Sun Alliance Building, Dawson St.

Lease Commencement Date 25/12/’81


Rent free period to 10/1/82

Preparation of brief of requirements by the Stationery Office


Preparation of layout plans by Architect


Layout plans with the Stationery Office for consideration and approval

The brief of requirements was developed during inspections by the Architect of existing operations and at meetings with the Stationery Office following which layout plans were prepared and cleared by Nov. ’81.

Preparation of tender documents for main contract and mechanical and electrical sub-contracts, clearance of layout plans with Lessors, invitation of tenders, examination of tenders and placing of contracts.

Nov. ’81 - June ’82

Completion of contract works

Jan ’83

Furnishing followed

 

Occupied

Feb. ’83

Cost of fitting out approximately

£140,000

76-78 Harcourt Street

Lease Commencement date 15/1/82

Preparation of initial brief of requirements by Department of Foreign Affairs

Oct. ’81

-

Feb. ’82 +

Preparation of layout plans by Architect

Feb. ’82

-

May ’82 +

Revised brief received from Department

May ’82

 

Revised layout plans with Department for consideration and approval.

Aug. ’82

-

Nov. ’82 +

Tender documents prepared and tenders invited

Nov. ’82

-

Jan ’83

Tenders received, examined and contract placed

Jan ’83

-

July ’83 *

Completion of contract works

Jan ’84

 

Expected occupation following provision of floor covering and furnishing

March ’84

 

Cost of fitting out approximately

£350,000

 

Harcourt Square Garda Headquarters, Harcourt Street


 

Date

Blocks 2 and 3 lease commencement

1.6.’81

Department of Justice asked for brief

2.7.’81

Briefs for Blocks 1 and 3 (except top 1½ floors) received

1.12.’81

Block 4 lease commencement

1.1.’82

Layout plans for Block 3 sent to D/Justice for approval

16.3.’82

Layout plans for Block 1 sent to D/Justice for approval

16.4.’82

D/Justice approve plans for Blocks 1 and 3

22.4.’82

Block 1 lease commencement

1.5.’82

Brief for Block 2 (except top floor) received

23.5.’82

Tender received from G. & T. Crampton Ltd.

7.7.’82

*Layout plans for Block 2 sent to D/Justice for approval

21.9.’82

Cramptons tender accepted for entire complex

12.10.’82

Phase 1: Blocks 1 and 3 (except top 1½ floors) to be started at


once - completion due June ’83

 

Phase 2: Blocks 2 and 4

 

Partitioning sub-contractor nominated

29.10.’82

New partitioning sub-contractor appointed - 1st firm withdrew

1.12.’82

D/Justice alter briefs: staff from top floor of Block 1 to occupy all


Block 4 - brief supplied

28.3.’83

Staff from top floor of Block 2 to occupy top


floor of Block 1 but no brief supplied

 

*D/Justice alter layouts for Block 2 - now top 2 floors without brief

29.3.’83

Briefs for top 14 floors, Block 3 received

20.4.’83

Revised layout plans for Block 2 (except top 2 floors) sent to D/Justice

10.5.’83

Layout plans for Block 2 approved

12.5.’83

Brief for top 2 floors Block 2 received

16.5.’83

Layout plans for top 1½ floors Block 3 and Block 4 sent to D/Justice

27.5.’83

Top floors Block 2 - - proposal not feasible


for technical reasons - brief withdrawn

7 and 16.6.’83

Layout plans for top 1½ floors Block 3 and Block 4 approved - work to to be done in Phase 2.

17.6.’83

Phase 1: Blocks 1 and 3 (except top floor in each) completed

July ’83

Block 1 occupied

July ’83

Block 3 occupied

Aug. ’83

Phase 2 commences: Block 3 - top floor

17.8.’83

Block 2 (except top 2 floors)


 

Block 4


 

Block 3 - top floor completed

Nov. ’83

Block 3 - top floor occupied

Nov. ’83

Blocks 2 (except top 2 floors) and 4 will be finished

Mar. ’84

Block 2 and 4 to be occupied following carpeting and furnishings

mid ’84

Outstanding briefs:

top floor Block 1, 7,800 ft2

)to be used as

 

top 2 floors Block 2, 10,400 ft2

)Communications Centre

Nassau House

Lease Commencement date 15/2/82

Preparation of brief of requirements by Department of Energy

Nov. ’81


(outline brief received with request to lease premises)

Preparation of layout plans by Architect

Nov. ’81 - Dec ’81

Layout plans with Department for consideration and approval

Dec. ’81 - Dec ’81

Preparation of tender documents and tenders invited

Dec. ’81 - Dec. ’81

Tenders received examined and contract placed

Jan. ’82 +

Contract works due for completion

March ’82

Contract works actually completed

July ’82 *

Occupation: 1st Floor

Oct. ’82 x

2nd Floor

May. ’83 x

Cost of fitting out approximately £117,000

 

Dolphin House:

Lease Commencement date 1/4/82

Preparation of brief of requirements by Department of Justice

Sept. ’81 - Dec. ’81

Preparation of layout plans by Architect

in stages from Dec ’81 - April 82 +

Layout plans with Department for consideration and approval

in stages from Jan ’82 - April 82 +

Preparation of tender documents and tenders invited

April - 82 - May ’82

Tenders received, examined and contract placed

May ’82 - June ’82

Contract works actual completion (ahead of time)

Nov. ’82

Floor covering and furnishing followed

 

Occupation commenced

Feb. ’83 *

completed

Sept ’83 *

Cost of fitting out approximately £500,000

 

Island House, Galway

Lease commencement date 1/10/82

 

Rent free period to 31/12/82

Preparation of brief of requirements by Department of Labour (Manpower Service)

August ’81 - Nov. ’81

Preparation of layout plans by Architect

+

Manpower Service

July 82 - Oct. 82 *

Social Welfare

Sept 82 - Oct. 82

Environment

Sept 82 - Oct. 82

Layout plans with Department for

 

consideration and approval

 

Manpower Service

Aug. 82 - Oct. 82 *

Social Welfare

Oct. 82 - Oct. 82

Environment

Oct. 82 - Feb. 83

Preparation of tender documents and tenders invited

Nov. 82 - Dec 82

Tenders received, examined and contract placed

Dec. 82 - Jan 83

Contract works completed

April 1983

Floor covering and furnishing followed

 

Occupied

 

Manpower Service

 

Social Welfare)


Environment   )

April ’83


June ’83 x

Fitting out cost approximately £33,000

Poplar Sq. Naas

Lease commencement date 1/12/82

 

Rent free period to 31/3/83

Agreement to lease the premises reached with lessor

Nov. ’82

Brief of requirements received from Departments of Agriculture and Social Welfare

Nov. ’82 - Dec. ’82

It was not possible to meet all requirements within the available space and both Departments were asked to review their requirements in the light of this (Dec. 82). In the event the space was allocated to the Department of Agriculture.


Layout plans prepared by Architect

Jan ’83 - Feb ’83

Layout plans with Department for consideration and approval

Feb ’83

Preparation of tender documents and tenders invited

Feb ’83 - April 83 +

Tenders received, examined and contract placed

April 83 - May 83

Contract completion due

July ’83

Flooring and furnishing followed

 

Occupied

Sept. ’83

Coolock Shopping Centre


Unit A2

Lease commencement date 1/4/83

The accommodation was leased as an adjunct to a previously leased and occupied adjoining Unit.

Layout plans prepared by Architect in respect of overall requirements for both units having regard to combined requirements.

June ’82

Layout plans with Department for consideration and approval

June ’82 - June ’82

Preparation of tender documents and tenders invited

June ’82 - Sept. ’82

Tenders received, examined and contract placed

Oct ’82 - Feb. ’83 +

Completion of contract works.

June ’83

Occupied

April ’83 *

Fitting out cost approximately £65,000

 

Office Rents


1981

1981

Private Sector transactions of which O.P.W. is aware.

O.P.W. transactions:-

10 transactions involving 139,000 sq. ft. 5 in Dublin 2, 4 in Dublin 4, 1 in the outer suberbs gave an average rent of £8.26 sq. ft.

4 transactions involving 98,000 sq. ft. in Dublin, 3 in Dublin 2, 1 in Dublin 7 gave an average rent of £6.540 sq. ft.

1982

1982

4 private sector transactions involving 59,000 sq. ft., 2 in Dublin 2, 1 in the outer suberbs in Dun Laoghaire gave an average rent of £8.33 per sq. ft.

5 O.P.W. transactions involving 95,600 sq. ft. in Dublin 2 gave an average of £7.66 per sq. ft.

 

1983

 

O.P.W. new letting were not significant, rent reviews in 10 cases involving 187,837 sq. ft. 6 in Dublin 2, 3 in Dublin 1, 1 Dublin 8 gave an average of £7.91 per sq. ft.

Exchange Buildings

Lease Commencement date 1/1/84


Rent free period to 31/3/84

Preparation of brief by Department

September ’83

Preparation of layout plans by Architect

Oct. ’83 - Dec ’83

Layout plans with Department for consideration and approval

Nov. ’83 - Dec. ’83

Preparation of tender documents and tenders invited

Dec. ’83

Tenders received, examined and contract placed

5 January ’84

Occupation expected

February 1984

Fitting out cost approximately £23,000

 

“Sunday Independent” article - 13 March 1983


“Sunday Independent” Statement

O.P.W. Comment

1.The Irish Civil Service is renting 289,400 square feet of office space it has never used.

1 and 2.


In March 1983 some 170,000 square feet of office space leased by O.P.W. in Dublin was unoccupied, approximately 95% of which cost less than £8 per square foot in rent

2.Every square foot of the unused space costs the taxpayers £8 at present commercial rates

3.Even since 1973 the Irish Civil Service has rented office space at exactly twice the rate staff were recruited to fill it.

3 and 4.


Space was rented not only for newly recruited staff but to relieve overcrowding in existing buildings and to accommodate staff moved from unsuitable accommodation. Also space provided by O.P.W. includes such facilities as Garda Headquarter accommodation, facilities for the State Laboratory, Meteorological Office, National Museum etc.


4.In 1973 there was 2.7 million square feet for 41,000 “non-industrial” staff. Today, there is 5.3 million square feet for just 21,000 more.

5.For the past decade the Civil Service has been the largest renter of office space on the property market, consistently leasing between 6 and 9 acres each (i.e. between 261,360 and 392,040 square feet).

5.O.P.W. Takes in Dublin over the period 1972 to 1982 averaged 165,590 square feet per annum. In the entire country during that period the annual average leased by O.P.W. was 196,502 square feet.

6.This year’s bill in Dublin alone will be almost £18,000,000 including unoccupied offices.

6.Actual O.P.W. outlay on rent and rates in 1983 in entire country totalled £14.6 million.

7.Buildings are rented by the Department that wants them after consultation with the Board of Works.

7.Buildings are rented by the Office of Public Works and not by the individual Departments.

8.In practice, however, the Board has little authority to do anything more than offer advice, and there is no obligation on any Department to heed its recommendations.

8.The Office of Public Works will not rent space unless it is satisfied that the Department needs it, and that the rent is reasonable.

9.The Board of Works has a statutory obligation to provide ofice space for Departments who claim to need it - once they can prove to the Department of Finance that there is money to meet the bill for the first year.

9.Provision of accommodation is the function of the O.P.W. - see 8 above.

10.10.Since 1979 there were over 1000 extra Gardai recruited to the force but less than £2 million allocated towards accommodating them.

10.It is not clear to what the £2 million allocation mentioned refers.


It is not reasonable to equate the amount of funds allocated for Garda Building and the numbers recruited to the Force. For instance, the drive to increase recruitment substantially commenced in 1982. In that year approximately £316,000 was expended providing new classrooms and sleeping accommodation at Templemore Training Centre. Sleeping accommodation within bussing distance of the Centre was also leased.


With regard to the Garda Building programme £8 million has been expended since 1979 and the allocation for 1984 is £4.27 m. While it could be argued that this amount was not expended on additional accommodation - in the majority of cases we are replacing buildings which have outlived their usefulness - the modern Garda Station caters for the increased manpower and services provided by the Gardai.

11.At present over 15% of the (Garda) force are working ....... “unfit for human habitation.”

11.Have no information to substantiate this point.

12.Yet their new Harcourt Street Headquarters is lying idle since March 1981 at a total cost of almost £1.5 m because the Board of Works awarded the original tender to “fit out” the building to a builder who was not able to complete the contract.

12.Blocks II and III were leased from June 1981 and Blocks I and IV from May 1982 and January 1982 respectively.


Blocks I and III were substantially occupied in July/August and November 1993. Blocks II and IV will be occupied mid 1984. The rent etc. paid to 1 March 1983 was £1.2m.


The main contractors Messrs G & T Crampton Ltd have been satisfactory. The sub-contractor referred to withdrew at the time of acceptance of the main tender and an alternative sub-contractor was appointed within 5 weeks.


The premises at Harcourt Street are to house the Dublin Metropolitan area Headquarters and are not relevant in the context of recruits.

13.Tender system blamed for expensive hold-ups.

13.O.P.W., like other Departments, must work within the prescribed framework of procedures laid down for the allocation of Government contracts. The tender system is an integral part of these procedures. It is designed to ensure fair competition exists and is seen to exist in the allocation of contracts. It can on occasion take time to process.

 


Year:

Office Area Leased (in Square Feet)

 

A

B

C

D

 

Dublin

Area in A

Provincial

A + C

 

 

still under

 

 

 

 

OPW control

 

 

1972

280,265

280,265

N.A.

N.A.

1973

153,723

153,723

21,789

177,512

1974

81,496

74,296

18,501

99,997

1975

173,584

131,504

48,320

221,904

1976

190,465

189,365

18,935

209,400

1977

58,943

41,320

26,209

85,152

1978

219,581

189,232

34,193

253,774

1979

35,175

35,175

60,531

95,706

1980

139,023

139,023

27,084

166,107

1981

171,345

171,345

36,685

208,030

1982

101,417

101,417

16,868

118,285

1983

4,678

4,678

11,000

15,678

 


 

Premises

Area

1973

Earlsfort House

63,400

 

1 Lr. Grand Canal St.

38,000

 

Hawkins House (10th, 11th flrs)

9,600

 

Oisin House

42,000

 

O’Connell Br. House (part)

723

 


1974

1, Ardee Road

32,600

 

290 Ballyfermot Rd.

800

 

Lyon House

18,281

 

Osmond House, Ship St.

22,615

 

(a)28 Bishop St.

5,900

 

(b)15 Molesworth St.

1,300

 


 

Rented Premises

Area

1975

(a)28 Bishop St.

16,729

 

Leinster Market

838

 

Castle House

35,050

 

Clonwilliam St. I

12,622

 

Norwich Union Building

12,300

 

1, Main St. Tallaght

200

 

44/45 St. Stephen’s Green

4,277

 

(b)49 St. Stephen’s Green

2,600

 

Sackville Place

17,092

 

(c)A.C.C. House

7,388

 

(d)Kildare Building

49,325

 

(e)Clonwilliam St. III

13,688

 

(f)14 St. Stephen’s Green

1,475

Notes:


(a)since surrendered


(b)since surrendered


(c)since surrendered


(d)the freehold of this building was purchased by the Commissioners of Public Works in 1976


(e)since surrendered


(f)since surrendered


 

Premises

Area

1976

Grattan House (gr. fl.)

2,950

 

Grattan House (1st fl.)

4,160

 

Grattan House (2nd fl.)

4,160

 

Hawkins House (part 1st flr.)

8,810

 

Holbrook House (1st fl.)

5,220

 

Hume House (2nd fl.)

11,140

 

13 Hume St.

3,850

 

7/9 Merrion Row

17,930

 

Molesworth Building

55,500

 

Nassau Building (2nd fl.)

17,312

 

(a)3 Lr. Ormond Q.

1,100

 

146 Sundrive Rd.

400

 

157/164 Townsend St.

35,563

 

Wicklow House

21,684

 

85 Ballymun Avenue

686

Note:


(a)since surrendered


 

Premises

Area

1977

Holbrook House (2nd fl.)

5,220

 

(a)15 Molesworth St.

2,000

 

Nassau Building (3rd fl.)

17,312

 

Nassau Building (4th fl.)

6,652

 

Ormond House

7,195

 

(b)102 Patrick St.

800

 

(c)21 Shelbourne Rd.

19,764

Notes:


(a)since surrendered


(b)since surrendered


(c)14823 sq. ft. of this space is sub-let to the National Board for Science & Technology.


 

 

Premises

Area

1978

 

Baggot Br. House

27,947

 

 

4 Burlington Rd.,

3,875

 

 

Ely Court

19,224

 

(a)

27 Upr. Fitzwilliam St.

1,537

 

 

Gandon House (grnd, 1st & 2nd flrs)

20,773

 

 

13-15 Lr. Hatch St.

11,237

 

 

Irish Life Centre

(B1. I)

29,924

 

(b)

(Bls V-Vii)

35,734

 

(c)

Nassau Bldg (5th, 6th fls.)

18,766

 

 

(1st fl.)

5,300

 

(d)

(1st fl.)

18,678

 

 

Park House (part 2nd & 4th flrs)

14,050

 

 

126-128 Thomas St.

10,668

 

 

O’Connell Br. House (1st fl.)

1,868

Notes:


(a)since surrendered


(b)17,542 sq. ft. of this building has been sub-let to An Bord Pleanala from June 1978.


(c)1,770 sq. ft. of this space is sub-let to Kilkenny Design Workshops Ltd.


(d)5500 sq. ft. of this space is sub-let to Kilkenny Design Workshops Ltd.


 

Premises

Area

1979

Apollo House (2nd-4th fls.)

16,650

 

Airways Ind. Estate

2,327

 

Coolock Shopping C. (Unit Al)

1,377

 

Four Courts (1.L.S.)

1,961

 

Irish Life Centre (Bl. I)

5,700

 

(a)5 Kildare St.

7,250

Note:


(a)This space has since been surrendered.


1980

22/25 Clare Street

20,385

 

4/5 Harcourt Rd.

32,800

 

Landsdowne Ho. (1st fl.)

7,990

 

Claremont Rd.

20,669

 

Earl Court

44,103

 

Bow Street

8,026

 

14/19 Crow St. (part)

3,900

 

54 Merrion Sq. (ground floor)

1,150

+The Department of Fisheries and Forestry staff strongly resisted the move, hence the delay in agreeing layout plans and subsequently in moving into the accommodation.


*Layout plans were forwarded November 1981. Alterations were sought Dec. 1981 and fresh plans prepared and finally agreed April, 1982.


+The delay in furnishing a brief of requirements was, it is understood, due to the fact that the Revenue Commissioners were at that time considering a re-organisation and expansion of the Dublin Tax Districts and intended to use this building as a Taxes headquarters.


*Occupation commenced on a phased basis in June 1982. The transfer of two of the nine District Tax Sections scheduled to occupy the premises, was postponed by the Revenue Commissioners because of problems with Unions arising initially from the Government embargo on the filling of posts and latterly from difficulties concerning disturbance money. Approximately 6,000 sq. ft. practically all on the rear of the 3rd floor remains unoccupied at present.


*The apparent delay in placing a contract was due to an unusual situation which arose with the lowest tenderer which called into question the validity of his tender.


+The contract works were to have been completed June, 1982 but did not complete until November, 1982 because of delays by the Contractor and also because extra works were required.


xThe building could not become operational until telephones were installed and although floor covering, furnishing and completion of a special security system followed on completion of the contract works the building was not occupied until July 1983 when the telephone installation was completed.


*The delay in occupying the premises was due to performance difficulties experienced with two of the four contractors involved in the various aspects and to requests for extra works by the Department.


*The delay in occupying the premises was due initially to a reluctance by the Department to occupy the premises until fitting-out works on the ground floor for the Eastern Health Board had been undertaken and completed as they maintained that these works when ongoing would involve hazards for their public callers and undesirable working conditions for their staff. The Office of Public Works did not accept this view and were not, in any event, in a position to execute the works concerned because of difficulties associated with the sub-lease to the Eastern Health Board. In an effort to allay the fears then expressed by the Department that security in the building would be inadequate pending completion of the security works included in the fitting-out proposals for the Eastern Health Board take, it was arranged to have some of these works undertaken as a separate matter viz. the provision of roller shutter grills to windows and doors on the ground floor. When these works were completed, the transfer of staff was further delayed because of a dispute about disturbance money.


+The apparent delay in furnishing a brief of requirements and the consequential preparation layout plans was due to receipt of a revised brief by the Department in May ’82 - the original brief had been furnished Feb. ’82.


It was not possible to meet all of the space requirements of the new brief and several meetings had to be held with the Department and new plans prepared before it was possible to settle the precise groupings which could be accommodated to meet the working arrangements of the Department.


* The delay in placing a contract was due to constraints imposed on O.P.W. in relation to expenditure because of the them current financial situation.


+Although the lease commencement date is 15/2/82, it was agreed with the lessor that works could commence Jan ’82. D/Finance sanctioned the leasing of the premises 15/1/82.


*The contractor was generally slow but obviously was experiencing problems as the firm was wound up shortly after completion of the contract.


xThe apparent delay in occupying the premises was due to the absence of telephones which were installed on the first floor in Oct. ’82 and on the 2nd floor 10 May ’83 and to a change of mind by the Department as to the proposed occupiers of the 2nd floor.


+ Layout plans for the ground to 2nd floors were prepared and sent to Department for approval Jan ’82 and for the 3rd and 4th floors, Feb. ’82. In March ’82 the Department sought the inclusion of additional services viz. two High Court Offices in the accommodation. This necessitated the preparation of revised layout plans which were approved by the Department in April 1982.


*The premises were ready for occupation but absence of telephones delayed occupation until Feb ’83 when two direct lines only were installed. This enabled part only of the accommodation including the Rent Tribunal Court rooms to be brought into use at that time.


The phone installation was completed in March 1983 but the Department did not take up occupation until September 1983.


+This building was inspected during its construction stage but was considered unacceptable for Government staff because of poor natural lighting and insufficient toilet accommodation. It was again inspected in June 1982. As additional toilets had been provided and the natural lighting problem overcome, the premises was considered acceptable. This being so, fitting out planning arrangements were put in hand.


*Layout plans for the National Manpower Service were prepared and sent for approval in August 1982. However in September 1982 it proved necessary to provide accommodation in the building for the Departments of Social Welfare and Environment. New plans had to be prepared and were sent to all concerned on 1st October 1982.


xSocial Welfare (Medical Referee) was awaiting the appointment of Staff’ (Nurse). Environment (Driver Tester) had already arranged tests from his existing accommodation and could not rearrange schedule until May 1983.


+Although tenders were received October ’82 the placing of a contract had to await receipt of Department of Finance sanction to leasing the premises. This sanction was granted January 1983. The contract was placed 3rd Feb. 1983.


*Staff of the National Manpower Office were already in occupation of the adjoining unit. The fitting-out contract encompassed both units and it was therefore necessary to fit out the premises in 2 phases - Unit A2 and part of Unit A1 being the first phase. As soon as these works were completed staff took up occupation viz. in April ’83. Works then commenced in Unit A1 and completed in June 1983. Staff then took up permanent positions in both units and additional staff transferred from City Centre Offices to Coolock.