Committee Reports::Report - Appropriation Accounts 1962 - 1963::12 November, 1964::Appendix

Qn. 277.


APPENDIX XXII.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1962-63 (VOTE 9, SUBHEAD B).

Work
No.

Service and Description

Total
Estimate

Vote
1962-63

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

£

£

s.

d.

£

s.

d.

£

s.

d.

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

 

 

1

Árus an Uachtaráin—Improvement of Planthouse Accommodation

8,250

5,000

2,924

3

7

262

5

11

3,186

9

6

In progress.

 

Total:

 

 

5,000

2,924

3

7

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

 

 

2

Leinster House—Extension

...

...

...

...

...

...

300,000

90,000

49,034

8

4

59 6,549

14 18

2 4

55,644

0

10

In progress.

 

Total:

 

 

90,000

49,034

8

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

 

3

State Apartments—Restoration of burnt-out Drawing Rooms

...

104,000

1,000

103

18

6

6,092

11

2

6,196

9

8

In planning.

 

Total:

 

 

1,000

103

18

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

 

4

Statue of Thomas Davis

...

...

...

...

...

...

...

6,500

1,000

214

1

8

150

0

0

364

1

8

Commissioned.

5

Central Heating Station—Renewal of Plant

...

...

...

...

50,000

25,000

88

10

0

88

10

0

In progress.

6

State Buildings (Upper Merrion Street and Kildare Street)—New

 

 

 

 

 

 

 

 

 

 

 

 

 

Electricity Distribution System

...

...

...

...

...

5,500

5,300

97

1

7

97

1

7

In planning.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

 

 

7

Dublin Castle—Rebuilding of Cross Block

...

...

...

115,000

60,000

21,246

4

11

16,886

7

9

38,132

12

8

In progress.

8

Stamping Branch—New Premises

...

...

...

...

525,000

2,000

2,270

16

11

2,270

16

11

In planning.

9

Carrickcarnan Customs Frontier Post—Office and Residence

15,000

10,000

10,376

0

0

1,599

0

2

11,975

0

2

Virtually completed.

10

Dundalk, New Customs Road Station

...

...

...

...

17,500

250

In planning.

11

Lifford Customs Post—Erection

...

...

...

...

...

9,500

5,000

Tenders under consideration.

12

Wexford, New Government Office and Telephone Exchange

...

33,000

12,000

4,100

0

1

3

3

0

4,103

3

1

In progress.

13

Government Publications Sale Office—Additional Accommodation

...

3,000

2,000

In planning.

14

Phoenix Park—Improvement of Water Supply

...

...

...

25,000

14,000

758

14

9

270

8

0

1,029

2

9

Planning completed.

 

Rotunda Gardens:

 

 

 

 

 

 

 

 

 

 

 

 

15

Garden of Remembrance—Architectural Works

...

...

144,000

75,000

57,332

0

0

40,708

15

0

98,040

15

0

In progress.

16

Memorial Sculpture

...

...

...

...

...

...

1,000

Under consideration.

 

Dún Laoghaire Harbour:

 

 

 

 

 

 

 

 

 

 

 

 

17

Mail Boat Pier Improvements

...

...

...

...

...

208,300

60,000

59,127

3

7

116,554

8

9

175,681

12

4

In progress.

18

Car Ferry Terminal

...

...

...

...

...

...

300,000

90,000

2,307

3

4

2,307

3

4

Trial-boring completed.

18A*

River Shannon—Bailey Bridge Offaly

...

...

...

...

...

2,144

0

0

2,144

0

0

Completed.

 

Total:

 

 

362,550

157,693

18

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

 

 

19

Garda Síochána Depot—Extension of Garage and Workshop

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

54,000

1,000

In planning.

20

New Garda Training Centre—Templemore—Adaptation, etc., works

435,000

200,000

207,708

5

9

93,506

5

3

301,214

11

0

In progress.

21

Erection of new Garda Síochána Stations and improvement of

 

 

 

 

 

 

 

 

 

 

 

 

 

existing specified Stations

...

...

...

...

...

...

375,000

140,000

93,313

7

9

 

 

 

 

 

 

 

 

 

 

 

 

(as under)

(detailed as follows)

 

 

 

 

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

 

 

 

 

 

 

Cabra—New Station

...

...

...

...

...

...

38,000

22,000

22,870

0

0

815

12

4

23,685

12

4

In progress.

 

Crumlin—New Divisional Headquarters

...

...

...

...

41,000

10,000

3,366

12

11

3,366

12

11

In progress.

 

Division of Dublin-Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

 

Clondalkin—New Station

...

...

...

...

...

...

12,000

2,000

In planning.

 

Divisional and District Headquarters Outside Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

 

Roscommon—New Divisional Headquarters

...

...

...

25,000

3,000

4,420

12

0

18,644

12

8

23,065

4

8

Completed.

 

Bantry—New District Headquarters

...

...

...

...

10,000

5,000

4,905

0

0

3,760

10

3

8,665

10

3

Virtually completed.

 

Ballyconnell—New District Headquarters

...

...

...

13,000

5,000

342

17

8

342

17

8

In progress.

 

Other New Stations as under:

200,000

80,000

47,458

8

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Co. Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

 

Cootehill

...

...

...

...

...

...

...

...

 

 

450

0

0

450

0

0

In progress.

 

Killeshandra

...

...

...

...

...

...

...

 

 

2,520

0

0

2,520

0

0

In progress.

 

Kingscourt

...

...

...

...

...

...

...

...

 

 

3,600

0

0

3,600

0

0

In progress.

 

Co. Clare:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ardnacrusha

...

...

...

...

...

...

...

 

 

In planning.

 

Labasheeda

...

...

...

...

...

...

...

...

 

 

273

17

6

273

17

6

In planning (work completed on well).

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

 

Castletownroche

...

...

...

...

...

...

...

 

 

Tenders invited.

 

Donoughmore

...

...

...

...

...

...

...

 

 

Contract placed.

 

Kinsale

...

...

...

...

...

...

...

...

 

 

Tenders invited.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

 

 

 

Burtonport

...

...

...

...

...

...

...

...

 

 

Tenders under consideration.

 

Carndonagh

...

...

...

...

...

...

...

...

 

 

Contract placed.

 

Castlefin

...

...

...

...

...

...

...

...

 

 

3,420

0

0

3,420

0

0

In progress.

 

Co. Galway:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ahascragh

...

...

...

...

...

...

...

...

 

 

2,250

0

0

2,250

0

0

In progress.

 

Portumna

...

...

...

...

...

...

...

...

 

 

5,478

0

0

5,478

0

0

In progress.

 

Co. Kerry:

 

 

 

 

 

 

 

 

 

 

 

 

 

Kilgarvan

...

...

...

...

...

...

...

...

 

 

153

0

0

153

0

0

Planning completed (work completed on well).

 

Co. Leitrim:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballinamore

...

...

...

...

...

...

...

 

 

Contract about to be placed.

 

Cloone

...

...

...

...

...

...

...

...

 

 

3,060

0

0

257

1

6

3,317

1

6

In progress.

 

Co. Louth:

 

 

 

 

 

 

 

 

 

 

 

 

 

Castlebellingham

...

...

...

...

...

...

...

 

 

1,890

0

0

1,890

0

0

In progress.

 

Co. Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Killala

...

...

...

...

...

...

...

...

 

 

2,880

0

0

2,880

0

0

In progress.

 

Co. Meath:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballivor

...

...

...

...

...

...

...

...

 

 

1,170

0

0

1,170

0

0

In progress.

 

Enfield

...

...

...

...

...

...

...

...

 

 

2,385

0

0

1,300

0

0

3,685

0

0

Completed.

 

Slane

...

...

...

...

...

...

...

...

...

 

 

450

0

0

450

0

0

In planning.

 

Co. Monaghan:

 

 

 

 

 

 

 

 

 

 

 

 

 

Clontibret

...

...

...

...

...

...

...

...

 

 

3,060

0

0

146

10

9

3,206

10

9

In progress.

 

Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

 

Banagher

...

...

...

...

...

...

...

...

 

 

2,250

0

0

2,250

0

0

In progress.

 

Co. Roscommon:

 

 

 

 

 

 

 

 

 

 

 

 

 

Kilmore

...

...

...

...

...

...

...

...

 

 

292

0

0

292

0

0

Well boring completed.

 

Strokestown

...

...

...

...

...

...

...

...

 

 

1,170

0

0

1,170

0

0

In progress.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballinafad

...

...

...

...

...

...

...

...

 

 

In planning.

 

Collooney

...

...

...

...

...

...

...

...

 

 

5,400

0

0

5,400

0

0

In progress.

 

Co. Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballingarry North

...

...

...

...

...

...

...

 

 

230

6

0

230

6

0

In progress.

 

Grangemockler

...

...

...

...

...

...

...

 

 

1,372

1

6

3,452

15

10

4,824

17

4

Completed.

 

Co. Westmeath:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballymore

...

...

...

...

...

...

...

...

 

 

10

0

0

10

0

0

In progress.

 

Rochfortbridge

...

...

...

...

...

...

...

 

 

810

0

0

810

0

0

In progress.

 

Co. Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Glynn

...

...

...

...

...

...

...

...

...

 

 

2,884

3

4

6,031

13

0

8,915

16

4

Completed.

 

Co. Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

 

Rathdrum

...

...

...

...

...

...

...

...

 

 

In planning.

 

Improvement Schemes as under:

36,000

13,000

9,949

16

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bridewell

...

...

...

...

...

...

...

...

 

 

2,891

0

9

18,842

13

8

21,733

14

5

Completed.

 

Parkgate Hall, Conyngham Road

...

...

...

...

...

 

 

443

8

11

945

13

2

1,389

2

1

Completed.

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

 

Inchigeela

...

...

...

...

...

...

...

...

 

 

924

10

7

454

2

6

1,378

13

1

Completed.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

 

 

 

Buncrana

...

...

...

...

...

...

...

...

 

 

1,508

15

10

1,508

15

10

Completed.

 

Co. Galway:

 

 

 

 

 

 

 

 

 

 

 

 

 

Leenane

...

...

...

...

...

...

...

...

 

 

1,604

2

3

131

17

4

1,735

19

7

Completed.

 

Oranmore

...

...

...

...

...

...

...

...

 

 

1,033

7

6

64

0

4

1,097

7

10

Completed.

 

Co. Limerick:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bruff

...

...

...

...

...

...

...

...

 

 

In planning.

 

Pallas

...

...

...

...

...

...

...

...

 

 

917

18

6

917

18

6

Completed.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bunninadden

...

...

...

...

...

...

...

 

 

324

0

0

461

18

2

785

18

2

Completed.

 

Sligo

...

...

...

...

...

...

...

...

...

 

 

860

11

0

630

0

0

1,490

11

0

Completed.

 

Co. Waterford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballymacarbery

...

...

...

...

...

...

...

 

 

1,302

15

0

1,302

15

0

Completed.

 

Co. Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Blackwater

...

...

...

...

...

...

...

...

 

 

360

0

0

360

0

0

In progress.

22

Improvement of other Garda Síochána Stations:

20,000

20,000

14,709

19

9

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Co. Carlow:

 

 

 

 

 

 

 

 

 

 

 

 

37/48 of 61/62

Muinebeag

...

...

...

...

...

...

...

...

 

 

788

0

0

1

5

0

789

5

0

In progress.

 

Co. Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

22/52

Stradone

...

...

...

...

...

...

...

...

 

 

200

0

0

200

0

0

In progress.

 

Co. Clare:

 

 

 

 

 

 

 

 

 

 

 

 

22/21

Lissyeasey

...

...

...

...

...

...

...

...

 

 

108

15

0

108

15

0

Completed.

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

22/35

Ballinspittle

...

...

...

...

...

...

...

...

 

 

327

11

2

327

11

2

Completed.

22/33

Coachford

...

...

...

...

...

...

...

...

 

 

616

10

4

616

10

4

Completed.

22/24

Fermoy

...

...

...

...

...

...

...

...

 

 

662

12

5

662

12

5

Completed.

22/61

Union Quay

...

...

...

...

...

...

...

...

 

 

135

13

0

135

13

0

Completed.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

 

 

27/21 of 61/62

Annagry

...

...

...

...

...

...

...

...

 

 

83

2

8

250

0

0

333

2

8

Completed.

22/40

Muff

...

...

...

...

...

...

...

...

...

 

 

900

0

0

900

0

0

In progress.

26 of 61/62

Rathmullen

...

...

...

...

...

...

...

...

 

 

218

17

2

650

0

0

868

17

2

In progress.

 

Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

 

Pearse Street (College):

 

 

 

 

 

 

 

 

 

 

 

 

22/60

New Mess Hall

...

...

...

...

...

...

...

 

 

293

15

6

293

15

6

In progress.

27/33 of 61/62

Canteen Improvements

...

...

...

...

...

...

 

 

27

8

9

156

11

7

184

0

4

Completed.

22/19

Accommodation for Ban Gárdaí

...

...

...

...

...

 

 

383

9

1

383

9

1

In progress.

22/25

Clontarf

...

...

...

...

...

...

...

...

 

 

343

3

5

343

3

5

Completed.

22/45

Cabinteely

...

...

...

...

...

...

...

...

 

 

112

7

3

112

7

3

In progress.

27/50 of 61/62

Kevin Street

...

...

...

...

...

...

...

 

 

21

1

9

427

8

4

448

10

1

Completed.

27/29 of 61/62

Kilmainham

...

...

...

...

...

...

...

...

 

 

24

0

6

140

1

11

164

2

5

Completed.

22/23

Store Street

...

...

...

...

...

...

...

...

 

 

528

17

10

528

17

10

In progress.

 

Co. Galway:

 

 

 

 

 

 

 

 

 

 

 

 

27/32 of 61/62

Clifden

...

...

...

...

...

...

...

...

 

 

254

7

0

 

16

0

255

3

0

Completed.

27/34 of 61/62

Headford

...

...

...

...

...

...

...

...

 

 

480

0

0

24

6

9

504

6

9

Completed.

22/3

Lettermore

...

...

...

...

...

...

...

...

 

 

140

10

3

140

10

3

Completed.

 

Co. Kildare:

 

 

 

 

 

 

 

 

 

 

 

 

22/20

Castledermot

...

...

...

...

...

...

...

...

 

 

636

11

0

636

11

0

Completed.

22/34

Kilcock

...

...

...

...

...

...

...

...

 

 

300

0

0

300

0

0

In progress.

 

Laois:

 

 

 

 

 

 

 

 

 

 

 

 

22/28

Ballylinan

...

...

...

...

...

...

...

 

 

600

0

0

600

0

0

Completed.

 

Co. Leitrim.

 

 

 

 

 

 

 

 

 

 

 

 

22/30

Carrick-on-Shannon

...

...

...

...

...

...

...

 

 

100

0

0

100

0

0

Completed.

 

Co. Limerick:

 

 

 

 

 

 

 

 

 

 

 

 

22/13

Askeaton

...

...

...

...

...

...

...

...

 

 

193

14

9

193

14

9

Completed.

27/57 of 61/62

Athea

...

...

...

...

...

...

...

...

 

 

517

12

6

1

5

0

518

17

6

Completed.

22/39

Limerick (Edward Street)

...

...

...

...

...

 

 

443

11

1

443

11

1

Completed.

27/37 of 61/62

Pallasgreen (New Pallas)

...

...

...

...

...

...

 

 

304

0

0

87

5

4

391

5

4

In progress.

 

Co. Louth:

 

 

 

 

 

 

 

 

 

 

 

 

22/26

Hackballscross

...

...

...

...

...

...

...

 

 

1,018

4

6

1,018

4

6

In progress.

 

Co. Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

22/15

Balla

...

...

...

...

...

...

...

...

 

 

381

10

9

381

10

9

Completed.

22/59

Bangor Erris

...

...

...

...

...

...

...

...

 

 

400

0

0

400

0

0

In progress.

27/8 of 61/62

Blacksod

...

...

...

...

...

...

...

...

 

 

64

5

0

338

6

7

402

11

7

Completed.

22/17

Cong

...

...

...

...

...

...

...

...

...

 

 

405

12

8

405

12

8

Completed.

22/7

Kiltimagh

...

...

...

...

...

...

...

...

 

 

214

14

6

214

14

6

In progress.

 

Co. Meath:

...

 

 

 

 

 

 

 

 

 

 

 

 

22/48

Oldcastle

...

...

...

...

...

...

...

...

 

 

180

0

0

180

0

0

In progress.

 

Co. Monaghan:

 

 

 

 

 

 

 

 

 

 

 

 

22/76

Corrinshigagh

...

...

...

...

...

...

...

...

 

 

350

0

0

350

0

0

In progress.

 

Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

22/27

Kilcormac

...

...

...

...

...

...

...

...

 

 

185

12

6

185

12

6

Completed.

 

Co. Roscommon:

 

 

 

 

 

 

 

 

 

 

 

 

27/30 of 61/62

Cootchall

...

...

...

...

...

...

...

...

 

 

198

12

6

600

0

0

798

12

6

Completed.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

22/10

Dromore West

...

...

...

...

...

...

...

 

 

270

15

0

270

15

0

Completed.

 

Co. Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

22/55

Thurles

...

...

...

...

...

...

...

...

 

 

233

13

0

233

13

0

In progress.

 

Co. Westmeath:

 

 

 

 

 

 

 

 

 

 

 

 

42/19 of 60/61

Kilbeggan

...

...

...

...

...

...

...

...

 

 

71

6

11

602

13

4

674

0

3

Completed.

 

Co. Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

22/31

Greystones

...

...

...

...

...

...

...

...

 

 

990

0

0

990

0

0

In progress.

23

Houses for married members of the Garda Síochána

...

...

25,000

25,000

101,254

0

0

101,254

0

0

In progress.

24

Courts of Justice—Renewal of Defective Stonework

...

...

...

50,000

10,000

1,460

13

7

3,485

0

10

4,945

14

5

Stage 1 completed.

 

Land Registry:

 

 

 

 

 

 

 

 

 

 

 

 

25

Improvements

...

...

...

...

...

...

...

7,500

450

370

5

4

7,002

7

8

7,372

13

0

Virtually completed.

26

Fire Precaution Works

...

...

...

...

...

...

5,200

2,600

3,460

17

11

330

14

7

3,791

12

6

In progress.

 

Total:

 

 

399,050

422,277

10

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

 

27

National Schools—Grants for Building, Enlarging, Enclosing, etc.

...

1,900,000

1,900,000

1,824,429

19

0

1,824,429

19

0

 

 

National Library:

 

 

 

 

 

 

 

 

 

 

 

 

28

Improvement of goods lift

...

...

...

...

...

...

1,375

500

525

0

0

900

15

10

1,425

15

10

Completed.

29

National Library and National Museum. Renewal of defective

 

 

 

 

 

 

 

 

 

 

 

 

 

stonework—Stage II

...

...

...

...

...

...

30,000

7,300

5,357

12

1

39,779

18

9

45,137

10

10

Nearing completion.

30

Dublin (Preventive Centre)—Erection

...

...

...

...

...

150,000

500

In planning.

31

National Gallery—Extension

...

...

...

...

...

...

277,000

250

2,411

5

4

2,411

5

4

In planning.

 

Total:

 

 

1,908,550

1,832,723

16

5

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

 

32

21-24 Upper Merrion Street Improvement of electrical installations

...

7,600

2,000

In planning.

 

Forestry Division:

 

 

 

 

 

 

 

 

 

 

 

 

33

Avondale House—Adaptation as Forestry Training and

 

 

 

 

 

 

 

 

 

 

 

 

 

Conference Centre

...

...

...

...

...

...

...

32,000

500

In planning.

34

Kinnitty Castle Forestry Training Centre—Additional

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation for Trainees and Fire Precaution Works

...

...

7,900

1,000

2,035

9

4

270 6,252

0 6

5 1

8,557

15

10

Completed.

 

Fisheries Division:

 

 

 

 

 

 

 

 

 

 

 

 

35

Galway, Fisheries Research Station—Erection

...

...

...

140,000

500

In planning.

36

Major Fishery Harbours (Stage 1)

...

...

...

...

1,260,000

140,000

57,058

7

0

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Castletownbere

...

...

...

...

...

...

...

 

 

7,181

3

4

1,038

14

7

8,219

17

11

Trial-borings completed.

 

Dunmore East

...

...

...

...

...

...

...

 

 

11,522

4

5

11,522

4

5

In planning.

 

Galway

...

...

...

...

...

...

...

...

 

 

21,316

17

7

2,420

2

7

23,737

0

2

Trial-borings completed.

 

Howth

...

...

...

...

...

...

...

...

...

 

 

2,406

9

11

1,512

6

6

3,918

16

5

Trial-borings in progress.

 

Killybegs

...

...

...

...

...

...

...

...

 

 

3,443

17

3

908 3,272

2 4

7 8

7,624

4

6

In planning.

 

Other expenditure

...

...

...

...

...

...

...

 

 

11,187

14

6

2,961

0

10

14,148

15

4

 

37

Works of Economic Development at other Fishery Harbours

...

70,210

50,000

24,157

17

5

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Aileen Reef

...

...

...

...

...

...

...

...

 

 

164

4

2

131

8

3

295

12

5

Completed.

 

Burtonport

...

...

...

...

...

...

...

...

 

 

1,493

12

1

3,074

15

4

4,568

7

5

Virtually completed.

 

Cahore

...

...

...

...

...

...

...

...

...

 

 

492

14

4

492

14

4

Completed.

 

Clogherhead

...

...

...

...

...

...

...

...

 

 

2,162

0

7

2,162

0

7

Nearing completion.

 

Dingle

...

...

...

...

...

...

...

...

 

 

3

11

4

4,650

0

0

4,653

11

4

Completed.

 

Greencastle

...

...

...

...

...

...

...

...

 

 

19,354

18

2

12,240

12

6

31,595

10

8

In progress.

 

Giles Quay

...

...

...

...

...

...

...

...

 

 

452

12

0

452

12

0

Completed.

 

Kilmore Quay

...

...

...

...

...

...

...

 

 

34

4

9

34

4

9

In planning.

 

Total:

 

 

194,000

83,251

13

9

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

 

 

 

Veterinary College, Ballsbridge:

 

 

 

 

 

 

 

 

 

 

 

 

38 (1)

Improvements

...

...

...

...

...

...

...

20,000

5,000

5,703

2

5

9,578

0

3

15,281

2

8

Virtually completed.

38 (2)

Pathological Anatomy Unit

...

...

...

...

...

11,900

6,000

1,839

12

0

150

0

0

1,989

12

0

In progress.

39

Botanic Gardens—New Fern House

...

...

...

...

...

10,000

1,000

179

8

0

179

8

0

Contract about to be placed.

 

Abbotstown Farm:

 

 

 

 

 

 

 

 

 

 

 

 

40 (1)

Artifical Insemination Experimental Station

...

...

...

23,500

1,000

139

7

6

20,555

15

0

20,695

2

6

Completed.

40 (2)

Experimental Animals Farmyard

...

...

...

66,000

20,000

24,398

6

0

11,060

6

11

35,458

12

11

In progress.

40 (3)

Foundation Stock Farmyard

...

...

...

...

...

65,000

20,000

6,534

0

6

17,484

7

1

24,018

7

7

Stages II and III in progress.

40 (4)

Residence for Director

...

...

...

...

...

...

5,800

3,800

2,520

0

0

678

3

6

3,198

3

6

In progress.

40 (5)

Residence for Farm Manager

...

...

...

...

...

4,400

2,500

3,164

0

0

147

7

2

3,311

7

2

Virtually completed.

40 (6)

Veterinary Field Station

...

...

...

...

...

...

90,000

500

Contract placed.

 

Athenry Agricultural School:

 

 

 

 

 

 

 

 

 

 

 

 

41 (1)

Precaution Works

...

...

...

...

...

...

...

1,500

500

3

11

8

3

11

8

In planning.

41 (2)

Improvement of Water Supply

...

...

...

...

...

12,000

2,000

320

19

3

912

13

4

1,233

12

7

Pump installed.

41 (3)

New Building

...

...

...

...

...

...

...

...

110,000

45,000

34,271

5

0

19,287

11

9

53,558

16

9

In progress.

41 (4)

Provision of additional facilities at Turkey Hatchery

...

...

 

9,171

3

10

9,171

3

10

In progress.

 

Ballyhaise Agricultural School:

 

 

 

 

 

 

 

 

 

 

 

 

42 (1)

Employees’ Cottages

...

...

...

...

...

...

13,000

1,500

2,859

0

0

11,064

8

10

13,923

8

10

Completed.

42 (2)

Re-arrangement of Grinding Plant

...

...

...

...

2,100

500

433

12

6

433

12

6

Plant delivered.

 

Clonakilty Agricultural School:

 

 

 

 

 

 

 

 

 

 

 

 

43 (1)

Fire Precaution Works

...

...

...

...

...

...

2,250

500

633

9

11

633

9

11

In progress.

43 (2)

Improvement of Water Supply

...

...

...

...

...

12,250

8,000

753

12

11

552

8

0

1,306

0

11

In progress.

43 (3)

New Building

...

...

...

...

...

...

...

...

110,000

45,000

33,300

0

0

6,699

16

2

39,999

16

2

In progress.

 

Johnstown Castle:

 

 

 

 

 

 

 

 

 

 

 

 

44

Improvement of Water Supply

...

...

...

...

...

21,000

1,000

2,459

17

0

18,033

8

5

20,493

5

5

Completed.

 

Munster Institute:

 

 

 

 

 

 

 

 

 

 

 

 

45 (1)

Fire Precaution Works

...

...

...

...

...

...

2,500

1,500

27

10

11

209

0

3

236

11

2

Minor architectural works in progress.

45 (2)

Improved accommodation

...

...

...

...

...

...

20,000

3,000

1,960

0

0

15,291

3

2

17,251

3

2

Completed.

45 (3)

New Poultry Plant

...

...

...

...

...

...

...

98,500

200

17,093

2

7

17,093

2

7

Adaptations completed, further works in planning.

45 (4)

Reconstruction of Cattle Court and Calf Sheds

...

...

...

5,000

2,000

In planning.

46

Thorndale—Detention Station for Imported Livestock

...

...

12,000

3,000

280

0

0

280

0

0

Planning completed.

 

Total:

 

 

173,500

129,881

5

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

 

 

47

Valentia Observatory—Accommodation for Seismological Instruments

1,500

1,200

2,603

5

3

7

16

0

2,611

1

3

Completed.

 

Total:

 

 

1,200

2,603

5

3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

 

 

 

Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

48

New Central Sorting Office

...

...

...

...

...

...

600,000

175,000

84,954

12

8

1,490

2

4

86,444

15

0

In progress.

49

New District Sorting Office and Telephone Exchange Coolock,

 

 

 

 

 

 

 

 

 

 

 

 

 

Raheny

...

...

...

...

...

...

...

...

13,500

250

13

10

0

13

10

0

In planning.

50

New District Sorting Office and Telephone Exchange, Finglas

...

18,200

6,000

3,974

11

0

31

8

10

4,005

19

10

In progress.

51

G.P.O. Arcade—Conversion of Shop to Office Accommodation

6,000

3,500

5,449

3

0

5,449

3

0

Completed.

52

New Warehousing, etc., accommodation

...

...

...

190,000

2,000

In planning.

53

Arklow Post Office—Improvements and New Telephone Exchange

12,850

3,000

847

12

1

847

12

1

Tenders under consideration.

54

Ballinasloe—New Post Office and Telephone Exchange

...

...

24,500

7,500

512

13

3

512

13

3

In progress.

55

Carrick-on-Shannon Post Office—Improvements

...

...

...

19,000

8,000

7,479

13

8

10,176

6

1

17,655

19

9

Virtually completed.

56

Ennis Post Office—Improvements and New Telephone Exchange

...

9,600

6,400

3,638

11

2

2,050

3

9

5,688

14

11

In progress.

57

Killarney Post Office—Improvements

...

...

...

...

...

2,880

500

421

12

11

1,709

3

2

2,130

16

1

Completed.

 

Limerick:

 

 

 

 

 

 

 

 

 

 

 

 

58

New Engineering Stores and Garages

...

...

...

...

1,700

1,600

Planning completed.

59

Post Office Improvements

...

...

...

...

...

...

13,000

7,500

6,840

0

0

53

5

0

6,893

5

0

In progress.

60

Sligo Post Office—Improvements

...

...

...

...

...

6,000

4,000

1,620

0

0

3,611

5

4

5,231

5

4

Completed.

61

Waterford Post Office—Improvements

...

...

...

...

1,700

200

1,150

1

2

662

8

0

1,812

9

2

Completed.

 

Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

62

New Area Engineering Headquarters

...

...

...

...

1,500

1,500

1,710

0

0

375

0

0

2,085

0

0

Nearing completion.

63

Post Office—Improvements

...

...

...

...

...

...

6,000

1,200

1,709

4

4

3,500

19

3

5,210

3

7

Completed.

64

Wicklow—New Post Office and Telephone Exchange

...

...

29,800

13,700

15,778

0

0

3,252

15

6

19,030

15

6

In progress.

65

Youghal—New Post Office and Telephone Exchange

...

...

...

13,000

8,000

3,096

11

9

3,096

11

9

In progress.

 

Total:

 

 

249,850

139,195

17

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

 

66

School of Civil Defence—Improved Accommodation

...

...

23,500

14,000

3,803

1

3

414

18

6

4,217

19

9

In progress.

67

Dublin, Cathal Brugha Barracks—Dining Hall and Cookhouse

...

62,000

25,000

560

4

4

500

0

0

1,060

4

4

Planning completed.

68

Curragh Camp—New Catholic Church

...

...

...

...

...

124,000

5,000

118,529

17

7

118,529

17

7

Completed.

69

Arbour Hill Detention Prison—Memorial to 1916 Leaders

...

...

29,000

1,000

816

0

0

25,011

0

3

25,827

0

3

In progress.

 

Total:

 

 

45,000

5,179

5

7

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

 

 

70

Irish Embassy to the Federation of Nigeria—Residences for

 

 

 

 

 

 

 

 

 

 

 

 

 

Ambassador and Secretary

...

...

...

...

...

...

...

64,000

500

80

0

0

80

0

0

In planning.

 

Total:

 

 

500

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

 

 

71

Dublin—New Headquarters, Haddington Road

...

...

...

1,100,000

15,000

3,151

6

8

3

14

0

3,155

0

8

In planning.

72

Achill—New Employment Exchange

...

...

...

...

...

7,800

1,000

536

11

0

7,425

11

1

7,962

2

1

Completed.

73

Carrick-on-Shannon—New Employment Exchange

...

...

...

14,000

11,500

9,967

16

11

226

17

6

10,194

14

5

Virtually completed.

74

Mullingar—New Employment Exchange

...

...

...

...

20,500

14,000

12,099

14

6

313

7

11

12,413

2

5

In progress.

75

Tralee—New Employment Exchange

...

...

...

...

42,500

1,000

3,148

18

3

37,707

19

9

40,856

18

0

Completed.

 

Total:

 

 

42,500

28,904

7

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

 

 

 

Central Mental Hospital, Dundrum:

 

 

 

 

 

 

 

 

 

 

 

 

76 (1)

Fire Prevention and Control

...

...

...

...

...

5,500

1,400

837

6

2

4,131

7

6

4,968

13

8

Nearing completion.

76 (2)

New Residence for Governor

...

...

...

...

...

5,600

4,500

6,120

0

0

111

7

0

6,231

7

0

Completed.

 

Total:

 

 

5,900

6,957

6

2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

General:

 

 

 

 

 

 

 

 

 

 

 

 

77

Minor New Works not exceeding £2,000 each

...

...

...

...

20,000

20,000

31,989

7

1

Details appended.

78

Urgent and Unforeseen Works

...

...

...

...

...

...

5,000

5,000

38,040

14

0

Details appended.

79

Minor Balances of Expenditure (not provided for above) on works of

 

 

 

 

 

 

 

 

 

 

 

 

 

prior years which may not be completed on 1st April, 1962

...

15,000

15,000

16,394

0

1

Details appended.

 

Total:

 

 

3,518,600

2,947,154

16

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Deduct:

 

 

 

 

 

 

 

 

 

 

 

 

 

(1) for works which might not have been carried out during the year (£173,600) and (2) for adjustment for expenditure previously

 

 

 

 

 

 

 

 

 

 

 

 

 

borne on Vote 9 (£25,000)

...

...

...

...

...

...

 

198,600

 

 

 

 

 

 

 

 

 

 

 

Net Totals:

 

 

3,320,000

2,947,154

16

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF 77—MINOR NEW WORKS NOT EXCEEDING £2,000

Minor Work No.

Service and Description

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

Central Statistics Office:

 

 

 

 

 

 

 

 

 

 

82/1/ of 1961/62

Partitioning

...

...

...

...

...

...

...

...

...

...

...

...

29

17

4

180

12

2

210

9

6

Completed.

82/57 of 1961/62

Ladies’ Rest Room

...

...

...

...

...

...

...

...

...

...

...

 

5

2

194

9

1

194

14

3

Completed.

46

Heating Improvement

...

...

...

...

...

...

...

...

...

...

...

622

19

1

622

19

1

Completed.

78

Improvements

...

...

...

...

...

...

...

...

...

...

...

...

263

8

1

263

8

1

Completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

37

Headquarters—Improvements

...

...

...

...

...

...

...

...

...

...

181

2

2

181

2

2

Completed.

49

O.   M. Section—Adaptations, etc.

...

...

...

...

...

...

...

...

...

...

1,304

5

4

1,304

5

4

Completed.

90/52 of 1960/61

Finance Section—Electrical Installation

...

...

...

...

...

...

...

...

...

 

1

11

236

11

5

236

13

4

Completed.

 

Office of Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

100

Custom House, Dublin—Partitioning

...

...

...

...

...

...

...

...

...

139

19

8

139

19

8

Completed.

82/70 of 1961/62

Dublin Castle—Improved Ventilation

...

...

...

...

...

...

...

...

...

41

13

3

11

18

11

53

12

2

Completed.

82/98 of 1961/62

9-10 Upper O’ConnellStreet, Dublin—Adaptations

...

...

...

...

...

...

...

878

15

1

271

3

7

1,149

18

8

Completed.

52

51 Lr. Baggot Street, Dublin—Elecrrical Installation

...

...

...

...

...

...

...

621

9

4

621

9

4

Completed.

30

Clondergole Customs Huts—Electrical Installation

...

...

...

...

...

...

...

160

11

8

160

11

8

Completed.

82/19 of 1961/62

Donegal St. Johnstown Customs Hut—Sanitary Facilities, etc.

...

...

...

...

...

15

10

0

196

1

6

211

11

6

Completed.

70

Limerick Government Offices—Improvements etc.

...

...

...

...

...

...

...

242

8

3

242

8

3

In progress.

27

Moybridge Customs Station—Electrical Installation

...

...

...

...

...

...

...

116

9

11

116

9

11

Completed.

87

Tralee Customs House—Electrical Installation

...

...

...

...

...

...

...

...

280

8

6

280

8

6

Completed.

 

Valuation Office:

 

 

 

 

 

 

 

 

 

 

4

5-6 Ely Place—Improved Heating, etc.

...

...

...

...

...

...

...

...

...

561

6

2

561

6

2

Completed.

82/39 of 1961/62

5-6 Ely Place—Adaptations

...

...

...

...

...

...

...

...

...

...

501

9

7

31

17

0

533

6

7

Completed.

90/90 of 1960/61

Ordance Survey Office—Alterations

...

...

...

...

...

...

...

...

...

18

0

0

655

7

6

673

7

6

Completed.

82/58 of 1961/62

Ordance Survey Office—Sanitary Facilities

...

...

...

...

...

...

...

...

138

3

11

34

19

8

173

3

7

Completed.

96

Ordnance Survey Office—Electrical Installation

...

...

...

...

...

...

...

244

12

2

244

12

2

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

82/44 of 1961/62

51 St. Stephen’s Green, Dublin—Adaptations

...

...

...

...

...

...

...

...

21

0

10

685

4

7

706

5

5

Completed.

8

51 St. Stephen’s Green—Lunch Club Equipment

...

...

...

...

...

...

...

305

16

5

305

16

5

Completed.

80

Engineer’s Branch—Heating and Equipment

...

...

...

...

...

...

...

...

 

15

2

 

15

2

Deferred to 1963 64

77

District Office, Castlebar—Improved Heating

...

...

...

...

...

...

...

...

110

17

2

110

17

2

Completed.

113

District Office, Waterford—Adaptations

...

...

...

...

...

...

...

...

145

11

0

145

11

0

Completed.

95

Central Engineering Workshop—Partitioning

...

...

...

...

...

...

...

...

175

3

0

175

3

0

In progress.

 

Phoenix Park:

 

 

 

 

 

 

 

 

 

 

6

Extension at Chapelizod Gate-Lodge

...

...

...

...

...

...

...

...

...

931

16

11

931

16

11

Completed.

73

Improvement of Spa Lodge, East

...

...

...

...

...

...

...

...

...

...

552

7

9

552

7

9

Completed.

82/79 of 1961/62

Improvements at Ashview House

...

...

...

...

...

...

...

...

...

340

0

0

360

0

0

700

0

0

Completed.

105

Heating for Glasshouses

...

...

...

...

...

...

...

...

...

...

...

160

0

0

160

0

0

Completed.

18

Improvement of Knockmary Lodge

...

...

...

...

...

...

...

...

...

389

17

4

389

17

4

In progress.

68

Garinish Island—Improved Heating of House

...

...

...

...

...

...

...

...

269

14

6

269

14

6

Completed.

82/3/ of 1961/62

Garinish Island—Office, etc.

...

...

...

...

...

...

...

...

...

...

...

11

3

0

631

18

6

643

1

6

Completed.

75

Dunmore East Harbour—New Structure

...

...

...

...

...

...

...

...

...

771

4

7

771

4

7

Completed.

57

Royal Hospital, Kilmainham—Improvement of West Avenue Cottage

...

...

...

...

...

396

1

6

396

1

6

Completed.

67

Dun Laoghaire, Former Coast Guard Station—Improvement of Cottages

...

...

...

...

597

9

4

597

9

4

Completed.

 

Chief State Solicitor’s Office:

 

 

 

 

 

 

 

 

 

 

82/40 of 1961/62

Renovation of Rooms over Children’s Court

...

...

...

...

...

...

...

...

197

1

9

865

8

0

1,062

9

9

Completed.

103

Basement Storage Improvements

...

...

...

...

...

...

...

...

...

98

3

9

98

3

9

In progress.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

106

Public Record Office—Provision of Book Lift

...

...

...

...

...

...

...

...

31

12

3

31

12

3

In progress.

39

Garda Depot—Storage

...

...

...

...

...

...

...

...

...

...

...

285

19

6

285

19

6

Completed.

82/60 of 1961/62

Police Huts

...

...

...

...

...

...

...

...

...

...

...

...

...

17

11

0

249

10

0

267

1

0

Completed.

82/103 of 1961/62

Land Registry—Adaptations

...

...

...

...

...

...

...

...

...

...

...

755

14

7

56

12

7

812

7

2

Completed.

72

Registry of Deeds—Improved Heating

...

...

...

...

...

...

...

...

...

441

16

4

441

16

4

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

76

Headquarters—Alterations

...

...

...

...

...

...

...

...

...

...

...

137

15

7

137

15

7

Completed.

122

Headquarters—Improvements (Room 18)

...

...

...

...

...

...

...

...

...

45

9

4

45

9

4

In progress.

 

Technical Instruction Branch:

 

 

 

 

 

 

 

 

 

 

32/34 of 1961/62

Adaptations

...

...

...

...

...

...

...

...

...

...

...

...

...

60

3

2

156

7

2

216

10

4

Completed.

43

Improvements

...

...

...

...

...

...

...

...

...

...

...

...

406

9

9

406

9

9

Completed.

58

Improved Storage

...

...

...

...

...

...

...

...

...

...

...

...

172

19

0

172

19

0

In progress.

82/74 of 1961/62

National Museum—Improved Lighting

...

...

...

...

...

...

...

...

...

17

11

0

107

10

4

125

1

4

Completed.

115

National Museum—Improved Lighting (Central Court)

...

...

...

...

...

...

...

11

4

3

11

4

3

In progress.

82/87 of 1961/62

National Gallery—Fire Precaution Work, etc.

...

...

...

...

...

...

...

...

336

14

2

54

9

4

391

3

6

Completed.

90

National College of Art—Adaptation, etc. (Room 9)

...

...

...

...

...

...

...

479

15

0

479

15

0

In progress.

104

Model School, St. Joseph’s—Partitioning, etc.

...

...

...

...

...

...

...

...

452

8

4

452

8

4

In progress.

69

Model School, Sligo—Electrical Installation

...

...

...

...

...

...

...

...

242

8

4

242

8

4

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

56

Land Commission—Sanitary Facilities

...

...

...

...

...

...

...

...

...

262

14

3

262

14

3

Completed.

3

Land Commission—Incinerators

...

...

...

...

...

...

...

...

...

...

148

10

0

148

10

0

Completed.

94

Forestry Branch, Headquarters—Shelving

...

...

...

...

...

...

...

...

...

73

15

6

73

15

6

In progress.

82/26 of 1961/62

Forestry Branch, Kilkenny—Partitioning, etc.

...

...

...

...

...

...

...

...

299

12

0

21

9

6

321

1

6

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

85

Government Buildings (South Block)—Shelving

...

...

...

...

...

...

...

...

105

6

4

105

6

4

Completed.

 

Botanic Gardens:

 

 

 

 

 

 

 

 

 

 

82/83 of 1961/62

Garage

...

...

...

...

...

...

...

...

...

...

...

...

...

3

6

7

170

6

11

173

13

6

Completed.

53

Oil Storage

...

...

...

...

...

...

...

...

...

...

...

...

...

178

0

5

178

0

5

Completed.

63

Improved Water Supply

...

...

...

...

...

...

...

...

...

...

...

10

0

3

10

0

3

In progress.

82/59 of 1961/62

Abbotstown Farm—Fire Precautions

...

...

...

...

...

...

...

...

...

341

4

5

191

3

5

532

7

10

Completed.

84

Thorndale Veterinary Laboratory—Fencing, etc.

...

...

...

...

...

...

...

...

540

13

9

540

13

9

Completed.

82/47 of 1961/62

Munster Institute, Pig Progeny Testing Station—Partitioning

...

...

...

...

...

...

12

17

11

312

18

5

325

16

4

Completed.

 

Bovine Tuberculosis Eradication Scheme Offices:

 

 

 

 

 

 

 

 

 

 

55

Cork—Improvements

...

...

...

...

...

...

...

...

...

...

...

573

1

7

573

1

7

Completed.

19

Ennis—Improvements

...

...

...

...

...

...

...

...

...

...

...

252

2

4

252

2

4

Completed.

82/56 of 1961/62

Galway—Improved Heating, etc.

...

...

...

...

...

...

...

...

...

146

7

2

405

0

0

551

7

2

Completed.

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

101

Kildare Street—Partitioning

...

...

...

...

...

...

...

...

...

...

...

107

16

10

107

16

10

In progress.

 

Meteorological Office:

 

 

 

 

 

 

 

 

 

 

90/55 of 1960/61

Adaptations

...

...

...

...

...

...

...

...

...

...

...

...

...

30

18

6

1,607

4

6

1,638

3

0

Completed.

1

Formation of Laboratory

...

...

...

...

...

...

...

...

...

...

...

938

3

9

938

3

9

Completed.

33

Fire Precautions

...

...

...

...

...

...

...

...

...

...

...

...

671

14

6

671

14

6

Completed.

24

Mullingar—Electrical Installation

...

...

...

...

...

...

...

...

...

...

223

0

0

223

0

0

Completed.

7

Mercantile Marine Office—Improvement of Heating

...

...

...

...

...

...

...

373

1

4

373

1

4

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

82/80 of 1961/62

Headquarters (Kildare Street)—Partitioning

...

...

...

...

...

...

...

...

62

7

0

155

2

5

217

9

5

Completed.

60

Patents Office—Improvements

...

...

...

...

...

...

...

...

...

...

14

2

0

14

2

0

In progress.

82/97 of 1961/62

Industrial Development Authority—Renovations

...

...

...

...

...

...

...

545

2

7

17

5

0

562

7

7

Completed.

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

35

Central Telegraph Office—Conversion of Telex

...

...

...

...

...

...

...

...

982

10

0

982

10

0

Completed.

71

Central Telegraph Office—Adaptations

...

...

...

...

...

...

...

...

...

230

6

10

230

6

10

Completed.

83

Telephone Exchange, Crown Alley—Improvements

...

...

...

...

...

...

...

287

11

5

287

11

5

Completed.

50

Dublin Post Office Factory—Installation of Petrol Pump

...

...

...

...

...

...

...

142

0

0

142

0

0

Completed.

32

Athy Post Office—Partitioning

...

...

...

...

...

...

...

...

...

...

139

15

4

139

15

4

Completed.

82/92 of 1961/62

Cork Sorting Office—Partitioning, etc.

...

...

...

...

...

...

...

...

...

382

9

7

182

16

1

565

5

8

Completed.

40

Cork Sorting Office—Improvements

...

...

...

...

...

...

...

...

...

...

152

9

9

152

9

9

Completed.

45

Kinsale Post Office—Adaptations

...

...

...

...

...

...

...

...

...

...

157

10

0

157

10

0

Completed.

9

Longford Post Office—Improvements

...

...

...

...

...

...

...

...

...

822

7

3

822

7

3

Completed.

17

Tipperary Post Office—Fire Precautions

...

...

...

...

...

...

...

...

...

50

0

0

50

0

0

In progress.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

General Headquarters:

 

 

 

 

 

 

 

 

 

 

82/9 of 1961/62

Ladies’ Cloakroom

...

...

...

...

...

...

...

...

...

...

28

16

0

218

19

2

247

15

2

Completed.

82/68 of 1961/62

Arrangement of accommodation

...

...

...

...

...

...

...

...

...

...

145

14

9

280

13

7

426

8

4

Completed.

21

Improvement of Heating

...

...

...

...

...

...

...

...

...

...

...

528

10

0

528

10

0

Completed.

28

Adaptations (Strongroom)

...

...

...

...

...

...

...

...

...

...

...

224

7

8

224

7

8

Completed.

59

Government Buildings (Main Guard Room)—Erection of Partitions

...

...

...

...

...

258

16

11

258

16

11

Completed.

82/66 of 1961/62

Civil Defence Store, Newbridge—Surfacing Approaches

...

...

...

...

...

...

...

147

4

2

59

0

0

206

4

2

In progress.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

 

Headquarters:

 

 

 

 

 

 

 

 

 

 

82/95 of 1961/62

Shelving

...

...

...

...

...

...

...

...

...

...

...

...

...

48

3

7

53

8

7

101

12

2

Completed.

91

Improvement of Lighting

...

...

...

...

...

...

...

...

...

...

...

8

11

8

8

11

8

In progress.

 

Embassies Abroad:

 

 

 

 

 

 

 

 

 

 

62

Bonn—Improvement of Heating

...

...

...

...

...

...

...

...

...

489

17

5

489

17

5

Completed.

82/102 of 1961/62

Brussels—Partitioning

...

...

...

...

...

...

...

...

...

...

...

581

6

9

387

16

0

969

2

9

Completed.

51

Canberra—Partitioning

...

...

...

...

...

...

...

...

...

...

...

798

15

1

798

15

1

Completed.

2

Lagos—Partitioning

...

...

...

...

...

...

...

...

...

...

...

1,952

7

1

1,952

7

1

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

29

Áras Mhic Dhiarmada—Equipment for Lunch Club

...

...

...

...

...

...

...

158

13

6

158

13

6

Completed.

 

Employment Exchanges:

 

 

 

 

 

 

 

 

 

 

90/70 of 1960/61

Beresford Place (Northumberland House)—Improved electric lighting

...

...

...

...

98

13

7

170

7

5

269

1

0

Completed.

81

Gardiner Street—Partitioning, etc.

...

...

...

...

...

...

...

...

...

122

13

10

122

13

10

Completed.

36

Gardiner Street—Shelving, etc.

...

...

...

...

...

...

...

...

...

...

959

15

0

959

15

0

Completed.

114

Dundalk—Improved lighting

...

...

...

...

...

...

...

...

...

...

245

19

10

245

19

10

Completed.

41

Limerick—Improved lighting

...

...

...

...

...

...

...

...

...

...

80

9

5

80

9

5

Part Completed.

20

Mallow Social Welfare Office—Improved Heating

...

...

...

...

...

...

...

116

19

6

116

19

6

Completed.

 

Total:

 

...

£31,989

7

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF No. 78—URGENT AND UNFORESEEN WORKS.

Work No.

Service and Description

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Oireachtas:

 

 

 

 

 

 

 

 

 

 

7

Dáil Chamber—Improved acoustics

...

...

...

...

...

...

...

...

...

1,555

9

2

1,555

9

2

Stage I completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Office of the Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

6

21 Parliament Street, Dublin—Adaptation for Claims Branch

...

...

...

...

...

2,889

17

10

2,889

17

10

In progress.

13

9-10 Upper O’ConnellStreet, Dublin—Installation of computer

...

...

...

...

...

5,293

12

7

5,293

12

7

In progress.

10

55-56 Upper O’ConnellStreet, Dublin—Adaptations, etc.

...

...

...

...

...

...

3,139

0

11

3,139

0

11

In progress.

12

19-22 Dame Street, Dublin—Adaptations, etc.

...

...

...

...

...

...

...

...

1,163

10

0

1,163

10

0

Virtually completed.

 

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

1

121 Lower Baggot Street, Dublin—Adaptations, etc., for Road Traffic Section

...

...

...

4,709

14

6

4,709

14

6

In progress.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

8

9-10 Burlington Road, Dublin—Adaptations, etc. for Institute for Advanced Studies

...

...

...

5,601

16

1

5,601

16

1

In progress.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

9

69 Fitzwilliam Square, Dublin—Adaptations, etc.

...

...

...

...

...

...

...

...

800

10

0

800

10

0

In progress.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

3

1, 7   8 Mount Street Crescent—Adaptations etc. for An Foras Tionscail and the Industrial

 

 

 

 

 

 

 

 

 

 

 

Development Authority

...

...

...

...

...

...

...

...

...

...

...

...

6,033

6

2

6,033

6

2

In progress.

4

21 Fitzwilliam Square, Dublin—Adaptations etc. for An Cheard Chomhairle

...

...

...

5,301

6

8

5,301

6

8

In progress.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

11

Stockholm Legation—Adaptations, etc.

...

...

...

...

...

...

...

...

...

1,552

10

1

1,552

10

1

In progress.

 

Total:

...

38,040

14

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF B.79—MINOR BALANCES OF EXPENDITURE.

Work No.

Service and Description

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Oireachtas:

 

 

 

 

 

 

 

 

 

 

3 of 1960/61

Leinster House—Reconstruction of loggias

...

...

...

...

...

...

...

...

...

1,772

2

1

14,112

17

11

15,885

0

0

Completed.

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

Central Statistics Office:

 

 

 

 

 

 

 

 

 

 

4 of 1961/62

Accommodation for Census of Population Staff

...

...

...

...

...

...

...

2,166

5

9

23,953

17

9

26,120

3

6

In progress.

91/3 of 1960/61

Transfer of dining club, etc.

...

...

...

...

...

...

...

...

...

...

29

6

6

3,721

17

6

3,751

4

0

In progress.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

9 of 1961/62

Economic Research Institute (73 Lr. Baggot Street, Dublin)—Adaptations

...

...

...

...

1,827

9

2

6,226

5

7

8,053

14

9

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

9a of 1961/62

Adaptations at 8-9 Merrion Row, Dublin

...

...

...

...

...

...

...

...

2

0

1

2,023

5

6

2,025

5

7

In progress.

9b of 1961/62

Adaptations at 50-51 St. Stephen’s Green, Dublin

...

...

...

...

...

...

...

68

19

2

2,271

10

7

2,340

9

9

In progress.

11a of 1961/62

Cork Government Offices—Adaptations

...

...

...

...

...

...

...

...

185

0

0

969

18

0

1,154

18

0

In progress.

12a of 1961/62

Cloghore Customs Frontier Post—Improvements

...

...

...

...

...

...

...

205

8

5

1,092

8

4

1,297

116

9

In progress.

 

Ordnance Survey Office:

 

 

 

 

 

 

 

 

 

 

11 of 1960/61

Fundamental Bench Marks

...

...

...

...

...

...

...

...

...

208

11

4

3,251

17

2

3,460

8

6

In progress.

17 of 1961/62

Improvement of storage equipment

...

...

...

...

...

...

...

...

...

525

0

0

634

12

11

1,159

12

11

In progress.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

96/3 of 1957/58

Kilkenny Forestry Office—Adaptations

...

...

...

...

...

...

...

...

...

135

4

6

490

11

7

625

16

1

Completed.

34 of 1961/62

Shelton Abbey Forestry School—Accommodation for additional trainees

...

...

...

...

192

4

6

3,693

19

1

3,886

3

7

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

48 of 1961/62

Cork: Egg and Poultry Inspection—Accommodation

...

...

...

...

...

...

...

623

2

11

2,074

2

6

2,697

5

5

In progress.

49 of 1961/62

Waterford Bovine Tuberculosis and Portal Inspection Offices—Adaptations

...

...

...

...

558

5

9

4,637

4

0

5,195

9

9

Completed.

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

50 of 1961/62

Valentia Observatory—Alterations and additions

...

...

...

...

...

...

...

...

2,531

16

7

63,210

15

5

65,742

12

0

Completed.

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

57a of 1960/61

General Post Office, Dublin—Partitions in Post Office Savings Bank

...

...

...

...

...

198

0

0

1,786

19

0

1,984

19

0

Completed.

35 of 1961/62

Bandon—New Telephone Exchange, Engineers Stores and Garages

...

...

...

...

...

395

12

10

1,030

4

10

1,425

17

8

In progress.

58 of 1960/61

Churchtown, Dublin—New District Sorting Office

...

...

...

...

...

...

...

54

13

6

17,309

6

9

17,364

0

3

Completed.

57 of 1961/62

Droichead Nua—New Post Office and Telephone Exchange

...

...

...

...

...

...

167

0

4

15,682

6

3

15,849

6

7

In progress.

59 of 1961/62

Galway—New Post Office and Telephone Exchange

...

...

...

...

...

...

...

358

17

8

55,542

14

0

55,901

11

8

In progress.

60 of 1961/62

Gorey Post Office—Improvements

...

...

...

...

...

...

...

...

...

...

217

11

10

2,573

0

2

2,790

12

0

In progress.

70 of 1961/62

Letterkenny—New Post Office and Telephone Exchange

...

...

...

...

...

...

...

30

1

4

31,310

8

10

31,340

10

2

Completed.

64 of 1961/62

Mallow Post Office—Improvements

...

...

...

...

...

...

...

...

...

...

810

11

5

1,654

4

7

2,464

16

0

In progress.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

73 of 1961/62

Curragh Camp, Plunkett Barracks—Dining Hall and Cookhouse

...

...

...

...

...

1,891

5

4

69,449

2

2

71,340

7

6

Completed.

74 of 1961/62

Haulbowline—New water main

...

...

...

...

...

...

...

...

...

...

1,210

15

6

9,383

4

5

10,593

19

11

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

88 of 1960/61

Central Mental Hospital—New water main

...

...

...

...

...

...

...

...

12

16

1

5,125

11

1

5,138

7

2

Completed.

88a of 1960/61

Customs House, Dublin—Demolition of annexe

...

...

...

...

...

...

...

...

15

17

6

3,409

3

3

3,425

0

9

Completed.

 

Total:

...

16,394

0

1