Committee Reports::Report - Control of Capital Projects::15 July, 1985::Appendix

APPENDICES

Table 1


Summary of Capital Budget* Requirements and Resources: 1984 Provisional Outturn and 1985 Estimate


 

1984


Provisional Outturn £m

1985


Estimate


£m

Capital Expenditure

 

 

Public Capital Programme (PCP) of which

1,796

1,800

(a) Exchequer

...

...

...

...

931

1,040

(b) Non-Exchequer

...

...

...

865

760

Exchequer Non-Programme Outlays (NPO)

140

45

Total Capital Expenditure

...

...

...

1,936

1,845

Capital Resources

 

 

Exchequer Resources of which

280

306

(a) Loan Repayments

...

...

...

58

63

(b) Sinking Funds

...

...

...

129

145

(c) Appropriations in Aid

...

...

19

19

(d) ERDF

...

...

...

...

74

79

Non-Exchequer Resources

...

...

...

865

760

Total Capital Resources

...

...

...

1,145

1,066

EBR (capital)

...

...

...

...

791

779

Source: “Public Capital Programme” 1985


(Pl. 2684)


Table 2


Public Capital Programme 1980 to 1987


£ million, current prices


 

1980

1981

1982

1983

1984 Provisional Outturn

1985 Provision

% change 1985 Provision over 1984 Provisional Outturn

“Building on Reality” Planned Provisions

1986

1987

Sectoral Economic Investment

 

 

 

 

 

 

 

 

 

Agriculture

...

...

...

119

109

109

82

72

75

+ 4

79

73

Industry

...

...

...

324

380

392

318

322

346

+ 7

361

362

Tourism

...

...

...

4

5

8

5

8

12

+45

10

9

Fisheries

...

...

...

12

13

13

8

7

9

+17

9

9

Forestry

...

...

...

10

16

16

18

18

20

+ 8

22

23

Miscellaneous

...

...

...

4

4

3

2

2

1

-33

1

1

Sub-total

...

...

473

527

541

433

429

463

+8

482

477

Productive Infrastructure

 

 

 

 

 

 

 

 

 

Energy

...

...

...

...

155

227

299

257

285

257

-10

180

137

Transport

...

...

...

69

99

114

84

127

68

-46

86

95

Roads, Sanitary Services, etc.

90

137

182

198

208

236

+13

245

259

Telecommunications, RTE, Postal Service

144

247

225

205

186

178

-4

136

116

Sub-total

...

...

458

710

820

744

806

739

- 8

647

607

Social Infrastructure

 

 

 

 

 

 

 

 

 

Housing

...

...

...

202

276

334

365

377

385

+ 2

397

411

Education

...

...

...

61

82

93

89

82

96

+17

107

115

Hospitals

...

...

...

35

45

49

53

56

58

+ 4

58

61

Government Construction etc.

30

53

61

55

46

59

+28

59

61

Sub-total

...

...

328

456

537

562

561

598

+ 7

621

648

Contingency Provision

...

...

50

Total

...

...

...

1,259

1,693

1,898

1,739

1,796

1,800

1,750

1,782

Notes:

(1) There are minor differences between some of the programme figures for 1985 in this table and table 7.2 in “Building on Reality” due to reclassification and rounding.

 

(2) Because of rounding of expenditure data, some of the figures and percentage changes shown here may differ from the details figures shown in the chapters dealing with the individual sectors. However, because rounding would give rise to significant distortions in the cases of Tourism, Forestry, Fisheries and Miscellaneous the percentage changes quoted are based on actual expenditure data.

* excluding current budget deficit.