ESTIMATED COST OF THE DEPARTMENT OF DEFENCE PROPOSED NEW HEADQUARTERS BUILDING.

Secretary,


Public Accounts Committee


The estimated cost of the project at March 1980 prices is £7.318m. exclusive of fees and fitting out costs. Fees for the project are estimated at £.964m. The order of cost for fitting out work is £1.44m plus £.18m for fees.


S. MacCÁRTHAIGH


Accounting Officer