APPENDIX 10
STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1977 (VOTE 9: SUBHEAD E)
Work No. |
Service and Description |
Total Estimate |
Vote 1977 |
Expenditure |
Observations |
1977 |
To 31/12/76 |
To 31/12/77 |
|
|
£ |
£ |
£ |
£ |
£ |
|
|
President: |
|
|
|
|
|
|
1 |
Aras an Uachtaráin: Improvements |
.. |
.. |
.. |
10,000.00 |
1,000.00 |
22.30 |
587.65 |
609.95 |
In progress. |
|
|
|
|
22.30 |
|
|
|
|
Oireachtas: |
|
|
|
|
|
|
2 (1) |
Leinster House: Installation of Standby Generator (in |
|
|
|
|
|
|
|
combination with No. 4) |
.. |
.. |
.. |
.. |
.. |
50,000.00 |
25,000.00 |
62,056.57 |
21.25 |
62,077.82 |
In progress. |
2 (2) |
Leinster House: Additional Accommodation |
.. |
.. |
85,000.00 |
10,000.00 |
— |
96.63 |
96.63 |
Under consideration. |
2 (3) |
Leinster House: Re-allocation of space and refurbishing |
.. |
25,000.00 |
5,000.00 |
2,365.03 |
7,801.17 |
10,166.20 |
In progress. |
2 (4) |
Leinster House: Security work to windows |
.. |
.. |
.. |
15,000.00 |
— |
13,990.90 |
— |
13,990.90 |
do. |
|
|
|
|
78,412.50 |
|
|
|
|
Finance: |
|
|
|
|
|
|
3 |
Government Buildings: Adaptations to South Block |
.. |
400,000.00 |
90,000.00 |
165,939.57 |
250,863.42 |
416,802.99 |
do. |
3A |
Government Buildings: South Block: Rising step barrier |
.. |
|
|
6,201.22 |
— |
6,201.22 |
Completed |
4 |
Government Buildings: Installation of Standby Generator |
|
|
|
|
|
|
|
(in combination with No. 2 (1) |
.. |
50,000.00 |
25,000.00 |
60,630.28 |
— |
60,630.28 |
In progress. |
5 |
Government Buildings: Adaptations to North Block |
.. |
|
25,000.00 |
14,289.66 |
— |
14,289.66 |
do. |
6 |
Clare Island: Harbour Improvements |
.. |
.. |
.. |
160,000.00 |
5,000.00 |
— |
40,823.69 |
40,823.69 |
do. |
7 |
Inishbofin, Co. Galway: Harbour Improvements |
.. |
.. |
17,000.00 |
5,000.00 |
— |
— |
— |
Under consideration. |
8 |
Courtmacsherry, Co. Cork: Boring Survey |
.. |
.. |
.. |
8,000.00 |
2,000.00 |
3,295.88 |
— |
3,295.88 |
In progress. |
9 |
State Laboratory: Temporary Accommodation |
.. |
11,000.00 |
3,000.00 |
1,395.81 |
8,574.53 |
9,970.34 |
do. |
10 |
State Laboratory: Additional Accommodation |
.. |
.. |
|
25,000.00 |
— |
— |
— |
In planning. |
11 |
Stationery Office: Additional Accommodation |
.. |
.. |
|
25,000.00 |
— |
— |
— |
Under consideration. |
12 |
Valuation Office: Additional Accommodation |
.. |
.. |
16,000.00 |
15,000.00 |
14,127.00 |
— |
14,127.00 |
In progress. |
13 |
Ordnance Survey: New Printing Building |
.. |
.. |
.. |
340,000.00 |
20,000.00 |
3,708.14 |
320,916.35 |
324,624.49 |
Virtually completed. |
14 |
Ordnance Survey: Improvement of Residential Quarters |
.. |
14,000.00 |
9,500.00 |
14,697.00 |
283.47 |
14,980.47 |
In progress. |
15 |
Ordnance Survey: Provision of Canteen Facilities |
.. |
.. |
8,000.00 |
3,000.00 |
6,806.97 |
3,301.20 |
10,108.17 |
Virtually completed. |
|
|
|
|
291,091.53 |
|
|
|
|
Revenue commissioners: |
|
|
|
|
|
|
16 |
New Revenue Offices, Dublin Castle |
.. |
.. |
.. |
1,600,000.00 |
25,000.00 |
2,057.21 |
1,473,126.38 |
1,475,183.59 |
Completed. |
17 |
Refurbishing of premises at Lord Edward Street |
.. |
.. |
170,000.00 |
25,000.00 |
3,262.35 |
— |
3,262.35 |
In progress. |
18 |
Clones (Clondergole): New Frontier Customs Post |
.. |
18,000.00 |
17,000.00 |
11,582.63 |
— |
11,582.63 |
do. |
19 |
Monaghan: New Customs Road Station |
.. |
.. |
.. |
145,000.00 |
17,000.00 |
18,314.65 |
130,325.82 |
148,640.47 |
Virtually completed. |
20 |
Carrigans: New Frontier Customs Post |
.. |
.. |
.. |
18,000.00 |
1,000.00 |
— |
— |
— |
Tenders invited. |
21 |
Blacklion Frontier Customs Post: Stage 2 |
.. |
.. |
.. |
40,000.00 |
1,000.00 |
— |
— |
— |
In planning. |
21A |
Cloghore Frontier Post: Erection of New Building |
.. |
|
|
8,144.49 |
— |
8,144.49 |
Virtually completed. |
22 |
Dundalk Customs Road Station: Enlargement |
.. |
.. |
152,000.00 |
40,500.00 |
26,328.29 |
5,387.50 |
31,715.79 |
In progress. |
22A |
33-41 Lower Mount Street. Hume House Computer Centre: |
|
|
|
|
|
|
|
Movement of computer equipment |
.. |
.. |
.. |
6,000.00 |
|
2,679.18 |
— |
2,679.18 |
do. |
23 |
Ballyshannon New Offices |
.. |
.. |
.. |
.. |
.. |
12,000.00 |
5,000.00 |
3,707.01 |
7,200.00 |
10,907.01 |
Completed. |
|
|
|
|
76,075.81 |
|
|
|
|
Office of public works: |
|
|
|
|
|
|
24 |
Scoil Eanna, Rathfarnham: Restoration of Buildings (Stage II) |
100,000.00 |
60,000.00 |
77,924.00 |
27,733.20 |
105,657.20 |
In progress. |
25 |
Scoil Eanna, Rathfarnham: Natural History Exhibition |
|
|
|
|
|
|
|
Centre, Garages, Stores, etc. |
.. |
.. |
.. |
.. |
20,000.00 |
17,000.00 |
15,622.03 |
565.99 |
16,188.02 |
do. |
26 |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
Muckross House: Sanitary Services |
.. |
.. |
.. |
75,000.00 |
5,000.00 |
7,667.66 |
32,816.58 |
40,484.24 |
In progress. |
27 |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
Muckross House: Improvements |
.. |
.. |
.. |
— |
7,000.00 |
— |
346.18 |
346.18 |
In planning. |
28 |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
New Jaunting Road |
.. |
.. |
.. |
.. |
.. |
25,000.00 |
10,000.00 |
— |
— |
— |
Under consideration. |
28A |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
Jaunting Car Park and Jarvey Shelter |
.. |
.. |
2,000.00 |
|
264.00 |
— |
264.00 |
do. |
29 |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
Visitor Facilities, etc. at Gearhameen |
.. |
.. |
.. |
40,000.00 |
22,000.00 |
24,750.00 |
— |
24,750.00 |
In progress. |
30 |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
Knockreer House Adaptation |
.. |
.. |
.. |
.. |
— |
5,000.00 |
— |
— |
— |
In planning. |
31 |
Kilkenny Castle: Restoration of Picture Gallery Wing |
.. |
340,000.00 |
20,000.00 |
17,302.74 |
320,544.35 |
337,847.09 |
Virtually completed. |
32 |
Phoenix Park: Public Toilets and Car Parks at Knockmaroon |
15,000.00 |
8,000.00 |
— |
— |
— |
In planning. |
33 |
Phoenix Park: Extension (Islandbridge Park): General |
|
|
|
|
|
|
|
Development |
.. |
.. |
.. |
.. |
.. |
.. |
80,000.00 |
8,000.00 |
— |
42,309.78 |
42,309.78 |
Balance of work under review. |
34 |
Glenveagh National Park, Co. Donegal: Road Realignment |
50,000.00 |
35,000.00 |
5,651.00 |
— |
5,651.00 |
In progress. |
35 |
Connemara National Park: Development Stage I |
.. |
.. |
|
8,000.00 |
— |
— |
— |
Under consideration. |
36 |
Derrynane National Historic Park: Visitor Centre |
.. |
|
1,000.00 |
— |
— |
— |
do. |
37 |
Ilnacullin (Garnish Island), Co. Cork: Car Park, etc., at |
|
|
|
|
|
|
|
Shrone |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
15,000.00 |
1,000.00 |
— |
— |
— |
do. |
38 |
Shannon Navigation: General Improvements |
.. |
.. |
120,000.00 |
8,000.00 |
7,671.03 |
109,785.53 |
117,456.56 |
Completed. |
39 |
Shannon Navigation: New Jetty at Hodson’s Bay |
.. |
.. |
55,000.00 |
15,000.00 |
309.65 |
693.26 |
1,002.91 |
In progress. |
39A |
Shannon Navigation: Lough Key (Rockingham): New Quay |
|
|
331.80 |
— |
331.80 |
do. |
40 |
Shannon Navigation: Rossmore Quay Improvements |
.. |
24,000.00 |
1,000.00 |
5,389.77 |
20,866.53 |
26,256.30 |
Completed. |
41 |
Shannon Navigation: Portumna Castle: New Harbour |
.. |
50,000.00 |
15,000.00 |
17,531.88 |
846.89 |
18,378.77 |
In progress. |
42 |
Shannon Navigation: Lanesboro: New Wharf |
.. |
.. |
10,000.00 |
10,000.00 |
4,637.17 |
28.35 |
4,665.52 |
do. |
43 |
Shannon Navigation: Meelick Quay Improvements |
.. |
16,000.00 |
1,000.00 |
1,612.30 |
14,607.61 |
16,219.91 |
Completed. |
44 |
Shannon Navigation: Albert Lock: New Jetty |
.. |
.. |
8,000.00 |
5,000.00 |
1,427.79 |
— |
1,427.79 |
In progress. |
45 |
Shannon Navigation: Lough Allen Canal: Restoration |
.. |
30,000.00 |
20,000.00 |
30,739.52 |
10,140.66 |
40,880.18 |
Virtually completed. |
46 |
Shannon Navigation: New Store at Roosky |
.. |
.. |
6,000.00 |
6,000.00 |
8,098.08 |
— |
8,098.08 |
In progress. |
47 |
Shannon Navigation: Clonmacnoise: New Jetty |
.. |
.. |
18,000.00 |
9,000.00 |
— |
— |
— |
In planning. |
48 |
Ballinamore and Ballyconnell Canal: Survey |
.. |
.. |
11,000.00 |
1,000.00 |
1,106.51 |
9,611.00 |
10,717.51 |
In progress. |
48A |
National Monuments: Dunmore Cave Visitor Centre |
.. |
|
|
2,210.84 |
34,437.94 |
36,648.78 |
|
49 |
National Monuments: Clonmacnoise Visitor Centre |
.. |
72,000.00 |
9,000.00 |
72.00 |
6,783.13 |
6,855.13 |
do. |
50 |
National Monuments: Cahir Castle Visitor and Exhibition |
|
|
|
|
|
|
|
Centre |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
27,000.00 |
9,000.00 |
9,709.91 |
17,610.33 |
27,320.24 |
do. |
51 |
National Monuments: Rock of Cashel Visitor Centre |
.. |
40,000.00 |
4,000.00 |
14,640.19 |
35,793.60 |
50,433.79 |
do. |
|
|
|
|
254,669.87 |
|
|
|
|
Public service |
|
|
|
|
|
|
52 |
Provision of building for Computer (Stage 2) |
.. |
.. |
708,000.00 |
300,000.00 |
208,319.08 |
95,229.08 |
303,548.16 |
do. |
52A |
Provision of Standby Generator |
.. |
.. |
.. |
.. |
|
|
2,780.80 |
— |
2,780.80 |
do. |
53 |
New Premises for the Institute of Public Administration and |
|
|
|
|
|
|
|
the Department of the Public Service Training Centre |
.. |
1,500,000.00 |
5,000.00 |
— |
63,891.84 |
63,891.84 |
In planning. |
54 |
15 Merrion Square: Adaptations |
.. |
.. |
.. |
.. |
100,000.00 |
1,000.00 |
— |
15,103.32 |
15,103.32 |
In progress. |
|
|
|
|
211,099.88 |
|
|
|
|
Justice |
|
|
|
|
|
|
55 |
72/76 St. Stephen’s Green, Dublin: Improvements |
.. |
9,000.00 |
5,000.00 |
43.25 |
— |
43.25 |
do. |
56 |
Film Censor’s Office: Improvements |
.. |
.. |
.. |
|
1,000.00 |
— |
— |
— |
In planning. |
57 |
Garda Headquarters: Transport Garage and Stores: |
|
|
|
|
|
|
|
Extension and Improvements |
.. |
.. |
.. |
.. |
.. |
|
30,000.00 |
797.46 |
— |
797.46 |
do. |
58 |
Garda Headquarters: Provision of Standby Generator and |
|
|
|
|
|
|
|
Ancillary Works |
.. |
.. |
.. |
.. |
.. |
.. |
76,000.00 |
50,000.00 |
57,547.72 |
— |
57,547.72 |
In progress. |
58A |
Garda Headquarters: Accommodation for Garda Band |
.. |
|
|
8,129.51 |
29,951.24 |
38,080.75 |
Virtually completed. |
59 |
Garda Training Centre, Templemore: Swimming Pool |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
|
5,000.00 |
838.97 |
640.17 |
1,479.14 |
In planning. |
60 |
Garda Stations: Erection of New Buildings and major |
|
|
|
|
|
|
|
improvement schemes |
.. |
.. |
.. |
.. |
.. |
|
650,000.00 |
935,309.72 |
|
|
|
|
|
|
|
detailed as follows: |
|
|
|
|
Dublin Metropolitan Division: |
|
|
|
|
|
|
|
Cabra |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,061.45 |
817.64 |
2,879.09 |
Completed. |
|
Kevin Street |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
750.00 |
— |
750.00 |
In planning. |
|
Store Street |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,200.43 |
194,052.70 |
201,253.13 |
Completed. |
|
Co. Dublin: |
|
|
|
|
|
|
|
Blanchardstown |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
757.52 |
11,710.00 |
12,467.52 |
do. |
|
Clondalkin |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,100.00 |
— |
1,100.00 |
In planning. |
|
Finglas |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
38,392.60 |
1,015.30 |
39,407.90 |
In progress. |
|
Irishtown |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,520.84 |
4,414.33 |
8,935.17 |
do. |
|
Swords |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
49,755.33 |
50,340.83 |
100,096.16 |
Completed |
|
Tallaght |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
17,900.00 |
— |
17,900.00 |
Virtually completed. |
|
Co. Cavan: |
|
|
|
|
|
|
|
Ballinagh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
23,511.00 |
— |
23,511.00 |
do. |
|
Mullagh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
19,285.00 |
— |
19,285.00 |
do. |
|
Virginia |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
14,040.00 |
— |
14,040.00 |
In progress. |
|
Co. Clare: |
|
|
|
|
|
|
|
Broadford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,500.00 |
16,200.00 |
24,700.00 |
Virtually completed. |
|
Corofin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,265.00 |
22,135.00 |
25,400.00 |
Completed. |
|
Tulla |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
10,350.00 |
12,600.00 |
22,950.00 |
Virtually completed. |
|
Co. Cork: |
|
|
|
|
|
|
|
Bantry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
28,120.00 |
— |
28,120.00 |
Virtually completed. |
|
Bridewell |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
19,620.00 |
— |
19,620.00 |
In progress. |
|
Carrignavar |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,196.36 |
18,817.74 |
27,014.10 |
Completed. |
|
Fermoy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,800.00 |
— |
1,800.00 |
In progress. |
|
Inchigeela |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,516.56 |
13,191.82 |
15,708.38 |
Completed. |
|
Kanturk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
39,728.37 |
7,064.74 |
46,793.11 |
In progress. |
|
Millstreet |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9,313.72 |
25,831.09 |
35,144.81 |
Completed. |
|
Passage West |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
13,698.00 |
— |
13,698.00 |
Virtually completed. |
|
Skibbereen |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,042.39 |
19,871.45 |
21,913.84 |
Completed. |
|
Co. Donegal: |
|
|
|
|
|
|
|
Ballyshannon |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,205.83 |
83,612.11 |
90,817.94 |
Virtually completed. |
|
Castlefin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,878.00 |
4,837.00 |
8,715.00 |
do. |
|
Creeslough |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
17,734.00 |
— |
17,734.00 |
do. |
|
Culdaff |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
108.49 |
16,200.00 |
16,308.49 |
Completed. |
|
Letterkenny |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,092.01 |
2,119.13 |
3,211.14 |
do. |
|
Newtowncunningham |
.. |
.. |
.. |
.. |
.. |
|
|
114.68 |
5,250.00 |
5,364.68 |
Virtually completed. |
|
Co. Galway: |
|
|
|
|
|
|
|
Kilchreest |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,862.79 |
— |
2,862.79 |
In progress. |
|
Kiltullagh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
308.80 |
15,352.00 |
15,660.80 |
Completed. |
|
Co. Kerry: |
|
|
|
|
|
|
|
Ardfert |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
14,607.70 |
13,599.12 |
28,206.82 |
do. |
|
Fenit |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
14,175.00 |
7,200.00 |
21,375.00 |
Virtually completed. |
|
Co. Kildare: |
|
|
|
|
|
|
|
Clane |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
199.55 |
13,260.12 |
13,459.67 |
Completed. |
|
Kill |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,375.00 |
4,500.00 |
11,875.00 |
Virtually completed. |
|
Naas |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
247.16 |
38,962.91 |
39,210.07 |
Completed. |
|
Co. Laols: |
|
|
|
|
|
|
|
Portlaoise |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
116,573.56 |
27,515.17 |
144,088.73 |
In progress. |
|
Co. Leitrim: |
|
|
|
|
|
|
|
Ballinamore |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,859.68 |
7,125.00 |
8,984.68 |
Completed. |
|
Co. Limerick: |
|
|
|
|
|
|
|
Limerick City: Divisional Headquarters |
.. |
.. |
|
|
33,042.82 |
454,553.53 |
487,596.35 |
Virtually completed. |
|
Croom |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
49.80 |
26,773.95 |
26,823.75 |
Completed. |
|
Newcastlewest |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
38,419.52 |
5,720.97 |
44,140.49 |
In progress. |
|
Co. Longford: |
|
|
|
|
|
|
|
Ballinalee |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,930.00 |
18,540.00 |
21,470.00 |
Virtually completed. |
|
Drumlish |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,050.00 |
— |
4,050.00 |
In progress. |
|
Granard |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,988.90 |
93,769.23 |
95,758.13 |
do. |
|
Co. Louth: |
|
|
|
|
|
|
|
Blackrock |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
528.54 |
10,619.96 |
11,148.50 |
Completed. |
|
Dundalk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
10,226.84 |
5,772.38 |
15,999.22 |
In planning. |
|
Omeath |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
21,150.00 |
4,500.00 |
25,650.00 |
Virtually completed. |
|
Co. Mayo: |
|
|
|
|
|
|
|
Charlestown |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,690.00 |
— |
3,690.00 |
In progress. |
|
Kilkelly |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,237.51 |
21,224.12 |
24,461.63 |
Completed. |
|
Co. Meath: |
|
|
|
|
|
|
|
Duleek |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,500.00 |
— |
4,500.00 |
In progress. |
|
Enfield |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,470.00 |
11,160.00 |
18,630.00 |
Virtually completed. |
|
Co. Monaghan: |
|
|
|
|
|
|
|
Castleblayney |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
22,727.12 |
16,745.28 |
39,472.40 |
In progress. |
|
Clones |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,186.05 |
16,178.95 |
24,365.00 |
Completed. |
|
Monaghan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,236.43 |
3,868.50 |
5,104.93 |
In planning. |
|
Co. Offaly: |
|
|
|
|
|
|
|
Shannonbridge |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
94.94 |
19,325.40 |
19,420.34 |
Completed. |
|
Co. Roscommon: |
|
|
|
|
|
|
|
Castlerea |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
30,686.23 |
43,343.51 |
74,029.74 |
In progress. |
|
Knockcroghery |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
249,74 |
18,492.00 |
18,741.74 |
Completed. |
|
Loughglynn |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
21,600.00 |
— |
21,600.00 |
In progress. |
|
Roscommon |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
19,355.00 |
8,100.00 |
27,455.00 |
Virtually completed. |
|
Co. Sligo: |
|
|
|
|
|
|
|
Cliffony |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
15,910.00 |
2,520.00 |
18,430.00 |
In progress. |
|
Grange |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
24,480.00 |
— |
24,480.00 |
do. |
|
Gurteen |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,940.00 |
— |
5,940.00 |
Virtually completed. |
|
Sligo |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9,920.99 |
8,563.97 |
18,484.96 |
Completed. |
|
Co. Tipperary: |
|
|
|
|
|
|
|
Ardfinnan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,303.41 |
425.00 |
3,728.41 |
In progress. |
|
Cloughjordan |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,084.00 |
20,602.63 |
21,686.63 |
Completed. |
|
Emly |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,107.64 |
21,090.00 |
25,197.64 |
do. |
|
Newport |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9,858.55 |
16,200.00 |
26,058.55 |
do. |
|
Templemore Garda Training Centre |
.. |
.. |
.. |
|
|
22,775.53 |
— |
22,775.53 |
In progress. |
|
Co. Waterford: |
|
|
|
|
|
|
|
Waterford City Divisional H.Q. |
.. |
.. |
.. |
.. |
|
|
12,331.95 |
— |
12,331.95 |
In progress. |
|
Portlaw |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
41.48 |
12,528.27 |
12,569.75 |
Completed. |
|
Co. Westmeath: |
|
|
|
|
|
|
|
Ballinahown |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
864.98 |
18,763.00 |
19,627.98 |
do. |
|
Kinnegad |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
152.60 |
12,393.92 |
12,546.52 |
do. |
|
Co. Wexford: |
|
|
|
|
|
|
|
Carrick-on-Bannow |
.. |
.. |
.. |
.. |
.. |
|
|
12,800.00 |
8,100.00 |
20,900.00 |
In progress. |
|
Clonroche |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,546.72 |
12,800.00 |
16,346.72 |
Completed. |
|
Duncannon |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,810.67 |
15,750.00 |
24,560.67 |
do. |
|
Kiltealy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
22,800.00 |
— |
22,800.00 |
In progress. |
|
Rosslare Pier |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,945.82 |
19,475.00 |
26,420.82 |
Completed. |
|
Rosslare Strand |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,634.12 |
13,191.11 |
16,825.23 |
do. |
|
Co. Wicklow: |
|
|
|
|
|
|
|
Blessington |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
15,815.00 |
8,233.17 |
24,048.17 |
Virtually completed. |
61 |
Garda Stations: Minor Improvement Schemes |
.. |
.. |
|
140,000.00 |
149,478.42 |
|
|
|
|
|
|
|
detailed as follows: |
|
|
|
Sub. No. |
Dublin Metropolitan Division: |
|
|
|
|
|
|
53 |
Ballyfermot |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
678.41 |
— |
678.41 |
Completed. |
37 |
Bridewell: Provide incinerator |
.. |
.. |
.. |
.. |
|
|
138.22 |
— |
138.22 |
In progress. |
64 |
Bridewell: Improvement to cooking facilities |
.. |
.. |
|
|
119.94 |
— |
119.94 |
Virtually completed. |
76/57 of 76 |
Clontarf |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,696.70 |
5,144.92 |
6,841.62 |
do. |
76/82 of 76 |
Crumlin: Improvements to Security. |
.. |
.. |
.. |
|
|
78.40 |
797.08 |
875.48 |
do. |
76/85 of 76 |
Crumlin: Alterations to accommodation |
.. |
.. |
.. |
|
|
227.11 |
1,134.73 |
1,361.84 |
do. |
50 |
Garda Headquarters, Dublin Castle: Communication |
|
|
|
|
|
|
|
Centre |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
648.79 |
— |
648.79 |
Completed. |
76/84 of 76 |
Garda Headquarters, Dublin Castle: Provision of glazed |
|
|
|
|
|
|
|
door in prefab. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
118.06 |
250.70 |
368.76 |
Completed. |
76/102 of 76 |
Garda Headquarters, Dublin Castle: Provision of canteen |
|
|
|
|
|
|
|
facilities in prefab. |
.. |
.. |
.. |
.. |
.. |
|
|
1,474.26 |
372.60 |
1,846.86 |
do. |
76/92 of 76 |
Garda Headquarters, Phoenix Park: Erection of new |
|
|
|
|
|
|
|
ceiling |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,604.98 |
18.45 |
2,623.43 |
do. |
76/50 of 76 |
Garda Headquarters, Phoenix Park: Provision of floor |
|
|
|
|
|
|
|
bases for precision instruments |
.. |
.. |
.. |
|
|
139.80 |
111.55 |
251.35 |
do. |
70/88 of 75 |
Garda Depot, Phoenix Park: Partitioning, etc. |
.. |
.. |
|
|
261.67 |
1,328.30 |
1,589.97 |
do. |
57 |
Garda Depot, Phoenix Park: Provision of concrete base |
|
|
|
|
|
|
|
and switchroom for aerial |
.. |
.. |
.. |
.. |
|
|
3,750.55 |
— |
3,750.55 |
In progress. |
59 |
Garda Depot, Phoenix Park: Improvements to Rooms 64, |
|
|
|
|
|
|
|
65, 87, Toilet and Passage |
.. |
.. |
.. |
.. |
|
|
851.61 |
— |
851.61 |
Completed. |
71 |
Garda Depot, Phoenix Park: Improvements to Room 27 |
|
|
4,192.05 |
— |
4,192.05 |
Virtually completed. |
94 |
Garda Depot, Phoenix Park: Alterations to Rooms 92 |
|
|
|
|
|
|
|
and 93 |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
268.82 |
— |
268.82 |
In progress. |
45 |
Garda Technical Bureau, St. John’s Road: Improvements |
|
|
|
|
|
|
|
to security |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,986.71 |
— |
2,986.71 |
Virtually completed. |
73 |
Garda Technical Bureau, St. John’s Road: Provision of |
|
|
|
|
|
|
|
oil tanks and flue pipe |
.. |
.. |
.. |
.. |
.. |
|
|
470.24 |
— |
470.24 |
In progress. |
70/94 of 75 |
Garda Technical Bureau, St. John’s Road: Installation of |
|
|
|
|
|
|
|
photographic equipment |
.. |
.. |
.. |
.. |
.. |
|
|
2.51 |
1,889.86 |
1,892.37 |
Completed. |
49/62 of 74 |
Irishtown |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6.92 |
1,140.00 |
1,146.92 |
do. |
52 |
Osmond House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,398.74 |
— |
2,398.74 |
Virtually completed. |
81 |
Rathmines |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
176.22 |
— |
176.22 |
In progress. |
33 |
Santry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,892.62 |
— |
3,892.62 |
Completed. |
76/81 of 76 |
Sundrive Road |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
25.60 |
1,967.91 |
1,993.51 |
do. |
67 |
Whitehall |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,383.08 |
— |
6,383.08 |
do. |
|
Co. Dublin: |
|
|
|
|
|
|
76/70 of 76 |
Balbriggan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
34.50 |
561.30 |
595.80 |
Completed. |
49/27 of 74 |
Cabinteely |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
50.00 |
9,561.61 |
9,611.61 |
do. |
19 |
Lusk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,486.76 |
— |
1,486.76 |
In progress. |
44 |
Rathcoole |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9,653.00 |
— |
9,653.00 |
do. |
90 |
Rush |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,141.00 |
— |
1,141.00 |
Completed. |
|
Co. Cavan: |
|
|
|
|
|
|
70/27 of 75 |
Ballyconnell |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,767.03 |
1,413.52 |
5,180.55 |
do. |
27/35 of 69/70 |
Cavan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
357.47 |
3,844.48 |
4,201.95 |
do. |
26 |
Swanlinbar |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,724.00 |
— |
3,724.00 |
In progress. |
|
Co. Clare: |
|
|
|
|
|
|
70/12 of 75 |
Carrigaholt |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,121.00 |
3,989.00 |
6,110.00 |
Virtually completed. |
76/7 of 76 |
Ennis |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,437.00 |
5,355.00 |
6,792.00 |
do. |
|
Co. Cork: |
|
|
|
|
|
|
76/64 of 76 |
Adrigole |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,530.00 |
1,440.00 |
2,970.00 |
do. |
54 |
Ballineen |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,600.00 |
— |
3,600.00 |
do. |
17 |
Bandon |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,160.00 |
— |
2,160.00 |
In progress. |
11 |
Blarney |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
547.10 |
— |
547.10 |
Completed. |
22 |
Clonakilty |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,543.00 |
— |
4,543.00 |
In progress. |
16 |
Cobh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
490.80 |
— |
490.80 |
Completed. |
76/55 of 76 |
Macroom |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
460.00 |
1,200.00 |
1,660.00 |
do. |
76/1 of 76 |
Union Quay |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,108.00 |
1,154.90 |
2,262.90 |
do. |
|
Co. Donegal: |
|
|
|
|
|
|
31 |
Bunbeg |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,759.42 |
— |
1,759.42 |
do. |
76/58 of 76 |
Bundoran |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
675.00 |
1,350.00 |
2,025.00 |
do. |
76/77 of 76 |
Killybegs |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
616.00 |
900.00 |
1,516.00 |
Completed. |
70/35 of 75 |
Letterkenny: Improvements to cells, etc. |
.. |
.. |
.. |
|
|
1,389.30 |
3,748.00 |
5,137.30 |
In progress. |
32 |
Letterkenny: Provision of stand-by generator |
.. |
.. |
|
|
709.42 |
— |
709.42 |
do. |
62 |
Pettigo |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,620.00 |
— |
1,620.00 |
do. |
49/45 of 74 |
Provision of huts at Donegal/Cavan border |
.. |
.. |
|
|
221.00 |
7,209.35 |
7,430.35 |
Completed. |
|
Co. Galway: |
|
|
|
|
|
|
55 |
Ardrahan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
422.06 |
— |
422.06 |
do. |
41 |
Currandulla |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,749.42 |
— |
1,749.42 |
do. |
74 |
Eglinton Street |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,670.00 |
— |
5,670.00 |
In progress. |
65 |
Eyrecourt |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
701.80 |
— |
701.80 |
Completed. |
72 |
Gort |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
247.20 |
— |
247.20 |
do. |
21 |
Headford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,515.75 |
— |
1,515.75 |
do. |
76/59 of 76 |
Loughrea |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
902.37 |
1,260.00 |
2,162.37 |
do. |
77 |
Monivea |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
457.70 |
— |
457.70 |
do. |
34 |
Salthill |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
669.06 |
— |
669.06 |
do. |
|
Co. Kerry: |
|
|
|
|
|
|
43/54 of 72/73 |
Beaufort |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
132.60 |
2,189.27 |
2,321.87 |
do. |
13 |
Brosna |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,665.00 |
— |
1,665.00 |
Virtually completed. |
32/39 of 71/72 |
Farranfore |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
334.85 |
4,797.90 |
5,132.75 |
Completed. |
70/81 of 75 |
Lauragh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,908.40 |
3,050.00 |
4,958.40 |
do. |
58 |
Moyvane |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
639.79 |
— |
639.79 |
do. |
76/29 of 76 |
Portmagee |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,418.50 |
3,960.00 |
6,378.50 |
Virtually completed. |
|
Co. Kilkenny: |
|
|
|
|
|
|
36 |
Ballyragget |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,225.00 |
— |
5,225.00 |
Completed. |
56 |
Callan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
213.62 |
— |
213.62 |
do. |
49/9 of 74 |
Mooncoin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
64.23 |
8,300.00 |
8,364.23 |
do. |
|
Co. Kildare: |
|
|
|
|
|
|
70/65 of 75 |
Droichead Nua |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
295.00 |
5,610.00 |
5,905.00 |
Completed. |
49/58 of 74 |
Maynooth |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
386.00 |
1,530.00 |
1,916.00 |
Virtually completed. |
|
Co. Laols: |
|
|
|
|
|
|
70/46 of 75 |
Arles |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
30.88 |
150.00 |
180.88 |
Completed. |
|
Co. Leitrim: |
|
|
|
|
|
|
70/70 of 75 |
Dromahair |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
72.00 |
1,377.22 |
1,449.22 |
do. |
76/65 of 76 |
Kinlough |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
225.00 |
450.00 |
675.00 |
do. |
|
Co. Limerick: |
|
|
|
|
|
|
76 |
Ballingarry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
813.15 |
— |
813.15 |
do. |
70/16 of 75 |
Bruff |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
492.06 |
5,130.00 |
5,622.06 |
do. |
70/18 of 75 |
Edward Street |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,616.00 |
829.96 |
6,445.96 |
In progress. |
43 |
Kilfinane |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,210.00 |
— |
6,210.00 |
do. |
46/16 of 73/74 |
Kilmeedy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
567.79 |
3,752.00 |
4,319.79 |
Completed. |
46/37 of 73/74 |
Tournafulla |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,074.55 |
3,150.00 |
4,224.55 |
do. |
|
Co. Longford: |
|
|
|
|
|
|
48 |
Newtown Cashel |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
642.80 |
— |
642.80 |
do. |
|
Co. Louth: |
|
|
|
|
|
|
51 |
Dundalk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
287.65 |
— |
287.65 |
do. |
|
Co. Mayo: |
|
|
|
|
|
|
76/54 of 76 |
Achill Sound |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,000.00 |
2,650.00 |
4,650.00 |
In progress. |
30 |
Ballinrobe |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,330.00 |
— |
3,330.00 |
do. |
70/22 of 75 |
Castlebar |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,114.70 |
1,800.00 |
2,914.70 |
In progress. |
70 |
Charlestown |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
227.00 |
— |
227.00 |
Completed. |
47 |
Hollymount |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
602.55 |
— |
602.55 |
do. |
|
Co. Meath: |
|
|
|
|
|
|
24 |
Athboy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,121.25 |
— |
2,121.25 |
do. |
46 |
Summerhill |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
729.20 |
— |
729.20 |
In progress. |
76/17 of 76 |
Trim |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
550.66 |
3,600.00 |
4,150.66 |
Completed. |
|
Co. Monaghan: |
|
|
|
|
|
|
35 |
Monaghan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
744.00 |
— |
744.00 |
do. |
|
Co. Offaly: |
|
|
|
|
|
|
1 |
Tullamore |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,143.15 |
— |
4,143.15 |
Virtually completed. |
|
Co. Sligo: |
|
|
|
|
|
|
28 |
Ballymote |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,530.00 |
— |
1,530.00 |
Completed. |
18 |
Tubbercurry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,246.82 |
— |
3,246.82 |
do. |
|
Co. Tipperary: |
|
|
|
|
|
|
79 |
Borrisokane |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
607.18 |
— |
607.18 |
do. |
76/3 of 76 |
Cappawhite |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
550.85 |
990.00 |
1,540.85 |
do. |
40 |
Dolla |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,067.10 |
— |
1,067.10 |
do. |
20 |
Thurles |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
941.00 |
— |
941.00 |
do. |
76/12 of 76 |
Tipperary |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
128.70 |
2,732.76 |
2,861.46 |
do. |
|
Co. Westmeath: |
|
|
|
|
|
|
76/49 of 76 |
Mullingar: Installation of central heating and |
|
|
|
|
|
|
|
improvements to lighting |
.. |
.. |
.. |
.. |
.. |
|
|
2,826.05 |
3,300.00 |
6,126.05 |
In progress. |
46/38 of 73/74 |
Mullingar |
.. |
.. |
.. |
.. |
.. |
|
|
74.01 |
1,313.00 |
1,387.01 |
Completed. |
|
Co. Wexford: |
|
|
|
|
|
|
23/34 of 70/71 |
Oulart |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
474.87 |
2,402.11 |
2,876.98 |
Completed. |
|
General: |
|
|
|
|
|
|
82 |
Provision of Garda Protection Huts |
.. |
.. |
.. |
|
|
2,026.29 |
— |
2,026.29 |
In progress. |
62 |
Courts of Justice: Provision of additional accommodation |
— |
45,000.00 |
5.63 |
— |
5.63 |
Under consideration. |
63 |
Courts of Justice: Fitting out of rented premises |
.. |
55,000.00 |
20,000.00 |
654.52 |
— |
654.52 |
In progress. |
64 |
New Permanent Courts |
.. |
.. |
.. |
.. |
.. |
— |
1,000.00 |
— |
— |
— |
Under consideration. |
|
|
|
|
1,152,805.20 |
|
|
|
|
Education: |
|
|
|
|
|
|
65 |
Athlone: New Offices |
.. |
.. |
.. |
.. |
.. |
950,000.00 |
250,000.00 |
386,553.52 |
679,953.50 |
1,066,507.02 |
Virtually completed. |
66 |
National Museum: Improvement of Lighting |
.. |
.. |
65,000.00 |
1,000.00 |
— |
— |
— |
In planning. |
67 |
National Museum: Additional Accommodation |
.. |
|
40,000.00 |
25,141.89 |
— |
25,141.89 |
In progress. |
68 |
National Library: Adaptation of premises at Kildare |
|
|
|
|
|
|
|
Street |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
25,000.00 |
15,338.33 |
1,576.32 |
16,914.65 |
do. |
69 |
National Library: Adaptation of premises at Leinster Lane |
30,000.00 |
10,000.00 |
115.50 |
— |
115.50 |
Under consideration. |
70 |
National Library: Improvement of Lighting |
.. |
.. |
|
15,000.00 |
— |
— |
— |
do. |
71 |
National Gallery: Alterations |
.. |
.. |
.. |
.. |
10,000.00 |
1,000.00 |
— |
— |
— |
do. |
72 |
Royal Irish Academy, Dublin: Improvements |
.. |
.. |
22,000.00 |
15,000.00 |
— |
— |
— |
In planning. |
|
|
|
|
427,149.24 |
|
|
|
|
Lands: |
|
|
|
|
|
|
73 |
Castlebar: New Offices |
.. |
.. |
.. |
.. |
.. |
1,320,000.00 |
100,000.00 |
91,916.30 |
1,211,318.67 |
1,303,234.97 |
Virtually completed. |
|
|
|
|
91,916.30 |
|
|
|
|
Gaeltacht |
|
|
|
|
|
|
74 |
Galway: New Offices |
.. |
.. |
.. |
.. |
.. |
225,000.00 |
25,000.00 |
17,158.25 |
— |
17,158.25 |
In planning. |
|
|
|
|
17,158.25 |
|
|
|
|
Agriculture |
|
|
|
|
|
|
75 |
Botanic Gardens: Developments (Herbarium, etc.) |
.. |
350,000.00 |
2,000.00 |
705.65 |
2,893.55 |
3,599.20 |
do. |
76 |
Botanic Gardens: Staff Canteen |
.. |
.. |
.. |
.. |
29,000.00 |
1,000.00 |
9,191.20 |
— |
9,191.20 |
In progress. |
77 |
Regional Veterinary and Dairy Produce Laboratories |
.. |
324,000.00 |
9,000.00 |
7,383.05 |
314,925.74 |
322,308.79 |
Completed. |
78 |
Abbotstown Farm: New Milking Parlour |
.. |
.. |
.. |
31,000.00 |
4,000.00 |
62.02 |
27,427.35 |
27,489.37 |
Virtually completed. |
79 |
Abbotstown Farm: Farm Manager’s Residence |
.. |
.. |
16,000.00 |
16,000.00 |
11,250.00 |
— |
11,250.00 |
In progress. |
80 |
Abbotstown Farm: Incinerator |
.. |
.. |
.. |
.. |
35,000.00 |
35,000.00 |
35,553.92 |
— |
35,553.92 |
Virtually completed. |
81 |
Abbotstown Farm: Loose Box Accommodation |
.. |
.. |
50,000.00 |
1,000.00 |
46,173.35 |
— |
46,173.35 |
In progress. |
82* |
* See under Fisheries. |
|
|
|
|
|
|
83 |
Abbotstown Farm: Improvements |
.. |
.. |
.. |
.. |
12,000.00 |
5,000.00 |
4,619.32 |
5,167.51 |
9,786.83 |
Completed. |
84 |
Abbotstown Farm: Extension of Gate Lodge |
.. |
.. |
6,000.00 |
5,000.00 |
— |
— |
— |
In planning. |
85 |
Tully West, Co. Kildare: Performance Testing Station for |
|
|
|
|
|
|
|
Beef Bulls |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
83,000.00 |
6,000.00 |
— |
76,866.63 |
76,866.63 |
Virtually completed. |
86 |
Tully West, Co. Kildare: New Office Accommodation |
.. |
31,000.00 |
25,000.00 |
23,280.30 |
— |
23,280.30 |
In progress. |
87 |
New Butter and Seed Testing Stations at Abbotstown |
.. |
— |
1,000.00 |
— |
— |
— |
In planning. |
88 |
Thorndale: Extension to Brucellosis Laboratory |
.. |
.. |
90,000.00 |
60,000.00 |
22,087.00 |
2,361.57 |
24,448.57 |
In progress. |
89 |
Kildalton College: Improvements |
.. |
.. |
.. |
.. |
8,000.00 |
1,000.00 |
2,575.60 |
21.70 |
2,597.30 |
do. |
90 |
Kildalton College: New Water Supply |
.. |
.. |
.. |
80,000.00 |
1,000.00 |
5,386.67 |
826.36 |
6,213.03 |
do. |
91 |
Kildalton College: Residences for Superintendent and two |
|
|
|
|
|
|
|
Inspectors |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
46,000.00 |
1,000.00 |
— |
2,007.61 |
2,007.61 |
In planning. |
92 |
Raphoe District Veterinary Office |
.. |
.. |
.. |
.. |
110,000.00 |
70,000.00 |
43,549.69 |
5,026.23 |
48,575.92 |
In progress. |
93 |
Veterinary College, Ballsbridge: Animal Unit Laboratory |
25,000.00 |
15,000.00 |
— |
— |
— |
In planning. |
94 |
Veterinary College, Ballsbridge: Cold room for Anatomy |
|
|
|
|
|
|
|
Department |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
16,000.00 |
13,000.00 |
7,854.00 |
2,700.00 |
10,554.00 |
Virtually completed. |
95 |
Ballyhaise Agricultural College: New Water Supply |
.. |
70,000.00 |
1,000.00 |
— |
1,221.34 |
1,221.34 |
In planning. |
96 |
Ballyhaise Agricultural College: New Accommodation |
.. |
183,000.00 |
1,000.00 |
— |
79.20 |
79.20 |
do. |
97 |
Clonakilty Agricultural College: Residence for |
|
|
|
|
|
|
|
Superintendent |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
15,000.00 |
1,000.00 |
— |
— |
— |
do. |
98 |
Mellowes Agricultural College, Athenry: New cottages and |
|
|
|
|
|
|
|
gate lodge |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
50,000.00 |
1,000.00 |
— |
— |
— |
do. |
99 |
New Office Block, Kildare Place: Fitting out, furnishing, etc. |
1,750,000.00 |
10,000.00 |
19,344.58 |
1,694,006.35 |
1,713,350.93 |
Virtually completed. |
100 |
Drogheda New Offices |
.. |
.. |
.. |
.. |
.. |
131,000.00 |
4,700.00 |
— |
126,420.83 |
126,420.83 |
Completed. |
101 |
Roscommon New Offices |
.. |
.. |
.. |
.. |
.. |
43,000.00 |
6,500.00 |
12,222.53 |
29,563.97 |
41,786.50 |
do. |
|
|
|
|
251,238.88 |
|
|
|
|
Fisheries |
|
|
|
|
|
|
82 |
Abbotstown Farm: Accommodation for Scientific and |
|
|
|
|
|
|
|
Research Staff (Fisheries) |
.. |
.. |
.. |
.. |
270,000.00 |
130,000.00 |
168,177.33 |
34,307.86 |
202,485.19 |
In progress. |
102 |
Dunmore East Fisheries Field Research Station: Extension |
12,000.00 |
2,000.00 |
— |
157.79 |
157.79 |
In planning. |
103 |
Castletownbere New Fisheries Field Research Station |
.. |
8,000.00 |
6,000.00 |
— |
— |
— |
do. |
|
|
|
|
168,177.33 |
|
|
|
|
Industry, Commerce and energy |
|
|
|
|
|
|
104 |
Geological Survey Office, Kildare Street: Improvements |
.. |
11,000.00 |
11,000.00 |
3,582.40 |
— |
3,582.40 |
In progress. |
|
|
|
|
3,582.40 |
|
|
|
|
Tourism and transport: |
£ |
£ |
£ |
£ |
£ |
|
105 |
Training School and Synoptic Reporting Station, |
|
|
|
|
|
|
|
Murrough, Co. Galway |
.. |
.. |
.. |
.. |
.. |
142,000.00 |
50,000.00 |
79,077.22 |
7,538.36 |
86,615.58 |
In progress. |
106 |
Claremorris: New Meteorological Station |
.. |
.. |
.. |
22,500.00 |
15,000.00 |
13,467.00 |
— |
13,467.00 |
do. |
107 |
Johnstown Castle: New Meteorological Station |
.. |
.. |
|
1,000.00 |
— |
— |
— |
In planning. |
|
|
|
|
92,544.22 |
|
|
|
|
Posts and telegraphs |
|
|
|
|
|
|
108 |
Central Sorting Office: Ventilation |
.. |
.. |
.. |
.. |
273,000.00 |
17,000.00 |
19,389.73 |
256,178.00 |
275,567.73 |
Completed. |
109 |
Central Sorting Office: Internal Alterations |
.. |
.. |
12,000.00 |
10,000.00 |
16,087.94 |
— |
16,087.94 |
In progress. |
110 |
Clondalkin Polefield: Resurfacing |
.. |
.. |
.. |
24,000.00 |
1,000.00 |
— |
— |
— |
Under consideration. |
111 |
Dundrum Engineering Training Centre |
.. |
.. |
.. |
185,000.00 |
1,000.00 |
582.63 |
8,243.14 |
8,825.77 |
do. |
112 |
Fairview: New Sorting Office |
.. |
.. |
.. |
.. |
|
1,000.00 |
— |
99.86 |
99.86 |
In planning. |
113 |
Finglas: Extension to Sorting Office |
.. |
.. |
.. |
.. |
40,000.00 |
10,000.00 |
62.76 |
— |
62.76 |
do. |
114 |
Phibsboro Post Office: Extension |
.. |
.. |
.. |
.. |
90,000.00 |
8,000.00 |
5,088.23 |
88,198.04 |
93,286.27 |
Completed. |
115 |
Athy Post Office: Improvements |
.. |
.. |
.. |
.. |
17,500.00 |
12,500.00 |
— |
— |
— |
In planning. |
116 |
Ballinlough Sorting Office, Cork: Adaptations |
.. |
.. |
25,000.00 |
22,400.00 |
15,750.00 |
111.00 |
15,861.00 |
In progress. |
117 |
Ballyhaunis Post Office: Modernisation |
.. |
.. |
.. |
28,000.00 |
18,000.00 |
6,795.00 |
6,297.48 |
13,092.48 |
do. |
118 |
Bray Post Office: Extension |
.. |
.. |
.. |
.. |
.. |
15,000.00 |
1,000.00 |
— |
— |
— |
Under consideration. |
119 |
Castleblayney Post Office: Improvements |
.. |
.. |
.. |
12,000.00 |
3,000.00 |
— |
— |
— |
do. |
120 |
Castlerea Post Office: Improvements |
.. |
.. |
.. |
15,000.00 |
6,000.00 |
9,535.69 |
4,500.00 |
14,035.69 |
Virtually completed. |
121 |
Clonmel New Post Office |
.. |
.. |
.. |
.. |
.. |
245,000.00 |
133,000.00 |
146,771.25 |
15,666.31 |
162,437.56 |
In progress. |
122 |
Cobh Post Office: Modernisation |
.. |
.. |
.. |
.. |
38,000.00 |
5,000.00 |
833.25 |
31,610.33 |
32,443.58 |
Virtually completed. |
123 |
Cork (Brian Boru Street) Sorting Office: Extension |
.. |
— |
1,000.00 |
— |
— |
— |
In planning. |
124 |
Donegal New Post Office |
.. |
.. |
.. |
.. |
.. |
265,000.00 |
34,000.00 |
45,229.32 |
228,390.90 |
273,620.22 |
Completed. |
125 |
Dungarvan New Post Office |
.. |
.. |
.. |
.. |
68,000.00 |
5,000.00 |
— |
64,355.14 |
64,355.14 |
do. |
126 |
Enniscorthy Post Office: Improvements |
.. |
.. |
.. |
58,500.00 |
30,000.00 |
1,174.20 |
2,645.14 |
3,819.34 |
In progress. |
127 |
Fermoy New Post Office |
.. |
.. |
.. |
.. |
.. |
|
3,000.00 |
— |
— |
— |
Under consideration. |
128 |
Letterkenny Post Office: Extension |
.. |
.. |
.. |
62,000.00 |
6,000.00 |
4,462.96 |
53,291.15 |
57,754.11 |
Virtually completed. |
129 |
Limerick Post Office: Improvements |
.. |
.. |
.. |
|
1,000.00 |
— |
1,180.33 |
1,180.33 |
In planning. |
130 |
Listowel New Post Office |
.. |
.. |
.. |
.. |
.. |
74,500.00 |
3,000.00 |
3,218.85 |
71,205.27 |
74,424.12 |
Completed. |
131 |
Longford New Post Office |
.. |
.. |
.. |
.. |
.. |
125,000.00 |
15,000.00 |
3,660.81 |
— |
3,660.81 |
In planning. |
132 |
Mullingar New Post Office |
.. |
.. |
.. |
.. |
.. |
450,000.00 |
40,000.00 |
3,656.46 |
6,270.99 |
9,927.45 |
do. |
133 |
Navan New Post Office |
.. |
.. |
.. |
.. |
.. |
|
1,000.00 |
— |
— |
— |
Under consideration. |
134 |
Roscommon Post Office: Modernisation |
.. |
.. |
.. |
20,000.00 |
5,000.00 |
— |
— |
— |
In planning. |
135 |
Shannon New Post Office |
.. |
.. |
.. |
.. |
.. |
320,000.00 |
1,000.00 |
— |
15,286.91 |
15,286.91 |
do. |
136 |
Thurles Post Office: |
|
|
|
|
|
|
|
(1) Improvements Stage I |
.. |
.. |
.. |
.. |
8,000.00 |
4,000.00 |
8,207.92 |
3,600.00 |
11,807.92 |
Completed. |
|
(2) Improvements Stage II |
.. |
.. |
.. |
.. |
|
1,000.00 |
— |
— |
— |
Under consideration. |
137 |
Tipperary New Post Office |
.. |
.. |
.. |
.. |
.. |
202,000.00 |
10,000.00 |
5,390.00 |
5,614.34 |
11,004.34 |
In planning. |
138 |
Togher Sorting Office, Cork: Fitting out |
.. |
.. |
.. |
10,000.00 |
1,000.00 |
302.40 |
8,877.00 |
9,179.40 |
Completed. |
139 |
Tralee Post Office: Improvements |
.. |
.. |
.. |
.. |
|
6,000.00 |
— |
— |
— |
Under consideration. |
140 |
Waterford Post Office: Improvements |
.. |
.. |
.. |
60,000.00 |
1,000.00 |
— |
— |
— |
In planning. |
141 |
Enniscorthy: Improvement of accommodation for postal |
|
|
|
|
|
|
|
vans |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
19,000.00 |
11,000.00 |
— |
— |
— |
do. |
142 |
Carrick-on-Shannon Area Engineering Headquarters |
.. |
3,800.00 |
1,500.00 |
2,048.12 |
— |
2,048.12 |
In progress. |
143 |
Clonmel Area Engineering Headquarters |
.. |
.. |
.. |
4,000.00 |
1,000.00 |
— |
— |
— |
In planning. |
144 |
Ennis Area Stock Depot |
.. |
.. |
.. |
.. |
.. |
5,000.00 |
2,500.00 |
— |
— |
— |
do. |
145 |
Monaghan Area Engineering Headquarters |
.. |
.. |
1,200.00 |
1,000.00 |
— |
— |
— |
Under consideration. |
146 |
Tipperary Area Stock Depot |
.. |
.. |
.. |
.. |
4,000.00 |
1,500.00 |
79.80 |
— |
79.80 |
In planning. |
147 |
Walkinstown Engineering Headquarters |
.. |
.. |
.. |
1,500.00 |
1,400.00 |
2,956.63 |
— |
2,956.63 |
In progress. |
|
|
|
|
301,283.95 |
|
|
|
|
Defence |
|
|
|
|
|
|
148 |
General Headquarters: Provision of printing building |
.. |
6,000.00 |
6,000.00 |
5,257.57 |
— |
5,257.57 |
Completed. |
149 |
General Headquarters: Improvement works |
.. |
.. |
20,000.00 |
13,000.00 |
5,076.36 |
6,476.80 |
11,553.16 |
In progress. |
150 |
Military Billets at Government Buildings: Adaptations |
.. |
100,000.00 |
25,000.00 |
16,543.00 |
— |
16,543.00 |
do. |
|
|
|
|
26,876.93 |
|
|
|
|
Foreign affairs |
|
|
|
|
|
|
151 |
Embassy at Beirut: Fitting out |
.. |
.. |
.. |
.. |
|
1,000.00 |
— |
20,142.18 |
20,142.18 |
Suspended due to civil war. |
152 |
Embassy at Berne: Fitting out of new Chancery |
.. |
.. |
25,000.00 |
25,000.00 |
20,246.68 |
— |
20,246.68 |
In progress. |
153 |
Embassy at Bonn: Improvements to Residence |
.. |
.. |
34,000.00 |
20,000.00 |
17,907.58 |
— |
17,907.58 |
do. |
154 |
Embassy at Bonn: Fitting out of new Chancery |
.. |
.. |
|
10,000.00 |
9,688.09 |
— |
9,688.09 |
do. |
155 |
E.E.C. Mission, Brussels: Fitting out of new Residence |
.. |
17,000.00 |
15,000.00 |
12,407.44 |
811.71 |
13,219.15 |
Completed. |
156 |
Embassy at Cairo. Fitting out |
.. |
.. |
.. |
.. |
|
1,000.00 |
1,761.43 |
— |
1,761.43 |
In planning. |
157 |
Embassy at Canberra: Erection of new Residence and |
|
|
|
|
|
|
|
Chancery |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
1,000.00 |
155.84 |
3,406.90 |
3,562.74 |
do. |
158 |
Embassy at Jeddah (including Residence for First Secretary): |
|
|
|
|
|
|
|
Fitting out |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
93,000.00 |
39,000.00 |
41,510.24 |
— |
41,510.24 |
In progress. |
159 |
Embassy at Lagos: Erection of new Residence |
.. |
.. |
|
1,000.00 |
— |
— |
— |
In planning. |
160 |
Embassy at Lisbon: Fitting out of new Residence |
.. |
.. |
20,000.00 |
10,000.00 |
597.73 |
741.04 |
1,338.77 |
In progress. |
161 |
Embassy at London: Adaptations |
.. |
.. |
.. |
10,000.00 |
9,000.00 |
12,165.01 |
32.79 |
12,197.80 |
Completed. |
162 |
Embassy at Moscow (including Staff Residence): Fitting out |
|
|
|
|
|
|
|
for occupation |
.. |
.. |
.. |
.. |
.. |
.. |
139,000.00 |
3,000.00 |
4,027.22 |
135,648.25 |
139,675.47 |
Virtually completed. |
163 |
Consulate General at New York: Improvements |
.. |
.. |
32,000.00 |
30,000.00 |
25,837.73 |
1,978.29 |
27,816.02 |
do. |
164 |
Embassy at Ottawa: Extension of Residence |
.. |
.. |
57,000.00 |
1,000.00 |
— |
1,384.42 |
1,384.42 |
In planning. |
164A |
Embassy at Ottawa: Extension of Chancery |
.. |
.. |
|
|
4,472.92 |
33,609.29 |
38,082.21 |
Completed. |
165 |
Embassy at Paris: Improvements |
.. |
.. |
.. |
.. |
75,000.00 |
2,500.00 |
2,746.42 |
72,000.32 |
74,746.74 |
do. |
166 |
Embassy at Paris: Replacement of lifts etc. |
.. |
.. |
|
1,000.00 |
— |
— |
— |
Under consideration. |
167 |
Embassy at Rome: Fitting out of new Chancery |
.. |
.. |
|
5,000.00 |
388.33 |
— |
388.33 |
In planning. |
168 |
Embassy at Teheran: Fitting out |
.. |
.. |
.. |
.. |
54,000.00 |
10,000.00 |
7,666.41 |
— |
7,666.41 |
In progress. |
169 |
Embassy at Vienna: Fitting out |
.. |
.. |
.. |
.. |
65,000.00 |
5,000.00 |
2,170.98 |
30,052.29 |
32,223.27 |
do. |
|
|
|
|
163,750.05 |
|
|
|
|
Social welfare |
|
|
|
|
|
|
170 |
Arklow Employment Exchange: Adaptations |
.. |
.. |
5,500.00 |
1,500.00 |
950.00 |
4,035.12 |
4,985.12 |
Completed. |
171 |
Dún Laoghaire Employment Exchange: Erection of new |
|
|
|
|
|
|
|
building |
.. |
.. |
.. |
.. |
.. |
.. |
250,000.00 |
1,000.00 |
— |
— |
— |
In planning. |
172 |
Limerick Employment Exchange |
.. |
.. |
.. |
.. |
|
1,000.00 |
— |
— |
— |
Under consideration. |
173 |
Manorhamilton Employment Exchange: Erection of new |
|
|
|
|
|
|
|
building |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
52,000.00 |
5,000.00 |
— |
— |
— |
In planning. |
|
|
|
|
950.00 |
|
|
|
|
Sundry departments |
|
|
|
|
|
|
174 |
New Buildings |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
— |
1,500,000.00 |
1,880,542.60 detailed as follows: |
|
|
|
|
93-99 Lower Leeson Street, Dublin |
.. |
.. |
.. |
|
|
79,629.28 |
294,822.69 |
374,451.97 |
In progress. |
|
Ship Street Barracks, Dublin Castle |
.. |
.. |
.. |
|
|
— |
11,780.39 |
11,780.39 |
In planning. |
|
Department of Defence New Headquarters, Infirmary |
|
|
|
|
|
|
|
Road, Dublin |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
13,575.21 |
56,783.16 |
70,358.37 |
do. |
|
Blocks 8, 9 and 10 Dublin Castle |
.. |
.. |
.. |
.. |
|
|
21,013.55 |
35,718.62 |
56,732.17 |
do. |
|
14-17 Upper Merrion Street, Dublin |
.. |
.. |
.. |
|
|
8,284.18 |
7,045.46 |
15,329.64 |
do. |
|
Beggars Bush, Haddington Road, Dublin |
.. |
.. |
|
|
36,792.58 |
134,098.31 |
170,890.89 |
do. |
|
Shelbourne Road, Ballsbridge |
.. |
.. |
.. |
.. |
|
|
434,690.79 |
231,816.85 |
666,507.64 |
In progress. |
|
Sligo Temporary Revenue Offices (The Mall) |
.. |
.. |
|
|
21,169.69 |
88,592.80 |
109,762.49 |
Completed. |
|
Waterford Temporary Revenue Offices |
.. |
.. |
.. |
|
|
3,019.41 |
55,089.08 |
58,108.49 |
do. |
|
New Garda Headquarters, Phoenix Park (Stage I) |
.. |
|
|
638,304.85 |
486,899.70 |
1,125,204.55 |
In progress. |
|
Thurles Temporary Revenue Offices |
.. |
.. |
.. |
|
|
— |
41,858.47 |
41,858.47 |
Completed. |
|
Kilkenny Temporary Revenue Offices |
.. |
.. |
.. |
|
|
1,945.00 |
37,261.93 |
39,206.93 |
do. |
|
13-14 Earlsfort Terrace, Dublin |
.. |
.. |
.. |
.. |
|
|
313,965.00 |
92,662.77 |
406,627.77 |
In progress. |
|
Marlborough House, Glasnevin (New Meteorological |
|
|
|
|
|
|
|
Service Headquarters) |
.. |
.. |
.. |
.. |
.. |
|
|
256,186.78 |
53,244.15 |
309,430.93 |
do. |
|
Waterford Government Offices |
.. |
.. |
.. |
.. |
|
|
31,480.65 |
18,936.43 |
50,417.08 |
do. |
|
Cork Government Offices |
.. |
.. |
.. |
.. |
.. |
|
|
10,485.63 |
— |
10,485.63 |
In planning. |
|
Mullingar Government Offices |
.. |
.. |
.. |
.. |
|
|
10,000.00 |
— |
10,000.00 |
do. |
175 |
Fitting out of premises for occupation |
.. |
.. |
.. |
|
500,000.00 |
935,433.08 detailed as follows: |
|
|
|
|
Furniture for fitting out premises |
.. |
.. |
.. |
.. |
|
|
77,966.20 |
— |
77,966.20 |
In progress. |
|
Ossian House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
22,499.11 |
144,572.71 |
167,071.82 |
Virtually completed. |
|
Earlsfort House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,849.82 |
278,350.37 |
282,200.19 |
do. |
|
52 St. Stephen’s Green |
.. |
.. |
.. |
.. |
.. |
|
|
8,305.06 |
133,311.17 |
141,616.23 |
do. |
|
Osmond House, Little Ship St. |
.. |
.. |
.. |
.. |
|
|
1,252.34 |
91,512.02 |
92,764.36 |
Completed. |
|
44-45 St. Stephen’s Green |
.. |
.. |
.. |
.. |
|
|
7,393.08 |
26,880.33 |
34,273.41 |
do. |
|
Ardee Road, Rathmines |
.. |
.. |
.. |
.. |
.. |
|
|
5,607.08 |
128,361.14 |
133,968.22 |
In progress. |
|
Sackville Place (two floors) |
.. |
.. |
.. |
.. |
|
|
32,676.28 |
46,665.34 |
79,341.62 |
Virtually completed. |
|
Lyon House (Revenue) O’Connell Street, Dublin |
.. |
|
|
3,600.77 |
118,398.06 |
121,998.83 |
Completed. |
|
Townsend Street (Social Welfare) |
.. |
.. |
.. |
|
|
37,225.61 |
117,609.43 |
154,835.04 |
In progress. |
|
Kildare Building (Setanta) |
.. |
.. |
.. |
.. |
.. |
|
|
143,860.38 |
241,540.31 |
385,400.69 |
do. |
|
Clanwilliam Court (Block 1) |
.. |
.. |
.. |
.. |
|
|
3,378.30 |
64,670.01 |
68,048.31 |
Completed. |
|
Earl House, Dundalk |
.. |
.. |
.. |
.. |
.. |
|
|
12,041.55 |
51,415.88 |
63,457.43 |
Virtually completed. |
|
Hibernian House, Eyre Square, Galway |
.. |
.. |
.. |
|
|
1,970.40 |
18,954.37 |
20,924.77 |
Completed. |
|
Sarsfield House, Limerick |
.. |
.. |
.. |
.. |
|
|
5,578.38 |
73,888.51 |
79,466.89 |
do. |
|
Wicklow House, George’s Street |
.. |
.. |
.. |
.. |
|
|
60,742.23 |
48,999.70 |
109,741.93 |
In progress. |
|
Hawkins House, Dublin (1st floor) |
.. |
.. |
.. |
|
|
1,911.31 |
2,748.97 |
4,660.28 |
Completed. |
|
Todds Building, Limerick: 12-16 Upper O’Connell Street |
|
|
23,019.42 |
— |
23,019.42 |
Virtually completed. |
|
Credit Union Building, Mallow |
.. |
.. |
.. |
.. |
|
|
2,266.41 |
3,007.71 |
5,274.12 |
Completed. |
|
51 St. Stephen’s Green (Ground and 2nd floors) |
.. |
|
|
38,904.19 |
6,000.16 |
44,904.35 |
Virtually completed. |
|
Holbrook House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,797.13 |
— |
6,797.13 |
Completed. |
|
7-9 Merrion Row |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
160.50 |
— |
160.50 |
In progress. |
|
Molesworth Building (Setanta) |
.. |
.. |
.. |
.. |
|
|
365,227.67 |
— |
365,227.67 |
do. |
|
Nassau Building (Setanta) |
.. |
.. |
.. |
.. |
.. |
|
|
62,329.08 |
56,597.27 |
118,926.35 |
do. |
|
72-76 St. Stephen’s Green |
.. |
.. |
.. |
.. |
|
|
1,610.34 |
— |
1,610.34 |
do. |
|
Civil Service Commission, 1 Grand Canal Street |
.. |
|
|
1,223.40 |
— |
1,223.40 |
Completed. |
|
Grattan House, Lower Mount Street |
.. |
.. |
.. |
|
|
934.17 |
35,316.92 |
36,251.09 |
do. |
|
St. Martin’s House, Fitting out for Stationery Office |
.. |
|
|
3,102.87 |
— |
3,102.87 |
In progress. |
|
|
|
|
2,815,975.68 |
|
|
|
|
Other buildings |
|
|
|
|
|
|
176 |
Premises at Earlsfort Terrace: Adaptations for Concert Hall |
|
|
|
|
|
|
|
purposes |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
75,000.00 |
37,084.21 |
4,383.13 |
41,467.34 |
In planning. |
177 |
Restoration of Royal Hospital Kilmainham (Stage II) |
.. |
|
45,000.00 |
17,811.60 |
94,146.16 |
111,957.76 |
do. |
|
|
|
|
54,895.81 |
|
|
|
|
General |
|
|
|
|
|
|
178 |
Minor New Works not exceeding £5,000 each |
.. |
.. |
|
180,000.00 |
184,527.11 |
|
|
Details appended. |
179 |
Urgent and Unforeseen Works |
.. |
.. |
.. |
.. |
|
5,000.00 |
|
— |
|
— |
180 |
Minor Balances of Expenditure (not provided for above) on works of prior years which may not be completed on 1st |
|
|
|
|
|
|
|
January, 1977 |
.. |
.. |
.. |
.. |
.. |
.. |
|
25,000.00 |
33,870.28 |
|
|
Details appended |
|
Total |
.. |
.. |
.. |
|
6,600,000.00 |
6,698,073.52 |
|
|
|
DETAILS OF NO. 178—MINOR NEW WORKS
Work No. |
Service and Description |
Total Estimate |
Vote 1997 |
Expenditure |
Observations |
1977 |
To 31/12/76 |
To 31/12/77 |
|
|
£ |
£ |
£ |
£ |
£ |
|
Sub. No. |
President |
|
|
|
|
|
|
172 |
Áras an Uachtaráin: Conversion of octagonal and adjoining |
|
|
|
|
|
|
|
rooms to Private Study |
.. |
.. |
.. |
.. |
.. |
|
|
2,522.73 |
— |
2,522.73 |
In progress. |
183 |
Áras an Uachtaráin: Provision of piped television service |
|
|
2,551.34 |
— |
2,551.34 |
Completed. |
|
Oireachtas |
|
|
|
|
|
|
78 |
Leinster House: Security Works (Windows) |
.. |
.. |
|
|
3,863.20 |
— |
3,863.20 |
do. |
|
Taoiseach |
|
|
|
|
|
|
50 |
State Apartments, Dublin Castle: China/Cutlery Stores |
.. |
|
|
1,405.96 |
— |
1,405.96 |
do. |
171/174 of 76 |
State Apartments, Dublin Castle: Presidential Inauguration |
|
|
1,678.62 |
3,344.50 |
5,023.12 |
do. |
119 |
Central Statistics, Earlsfort Terrace: Provision of Waiting |
|
|
|
|
|
|
|
Room on 1st Floor |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
553.11 |
— |
553.11 |
do. |
61 |
Central Statistics, Ardee Road, Rathmines: Extension of |
|
|
|
|
|
|
|
fire alarm system |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
611.82 |
— |
611.82 |
do. |
|
Finance |
|
|
|
|
|
|
171/78 of 76 |
Valuation Office, 5/6 Ely Place: Adaptations for P.A.B.X. |
|
|
|
|
|
|
|
equipment |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
47.79 |
798.04 |
845.83 |
do. |
151/126 of 75 |
Valuation Office, 5/6 Ely Place: Provision of Tea-room |
.. |
|
|
73.24 |
1,876.75 |
1,949.99 |
do. |
171/109 of 76 |
State Laboratory, Upper Merrion Street: Provision of bench |
|
|
|
|
|
|
|
in laboratory |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
195.08 |
766.67 |
961.75 |
do. |
83 |
State Laboratory, Merrion Row: Provision of fan and hood |
|
|
229.17 |
— |
229.17 |
do. |
87 |
Stationery Office: Provision of 500 timber pallets |
.. |
.. |
|
|
970.71 |
— |
970.71 |
do. |
135 |
Ordnance Survey Office, Phoenix Park: Provision of map |
|
|
|
|
|
|
|
sales office and demolition of photography studio |
.. |
|
|
1,236.85 |
— |
1,236.85 |
In progress. |
153 |
Ordnance Survey Office, Phoenix Park: Improvements to |
|
|
|
|
|
|
|
heating and lighting |
.. |
.. |
.. |
.. |
.. |
|
|
443.22 |
— |
443.22 |
do. |
Sub. No. |
|
|
|
|
|
|
|
|
Revenue commissioners |
|
|
|
|
|
|
171/147 of 76 |
Hume House: Provision of canteen facilities |
.. |
.. |
|
|
1,653.62 |
4.86 |
1,658.48 |
Virtually completed. |
121 |
Hume House: Partitioning |
.. |
.. |
.. |
.. |
.. |
|
|
408.16 |
— |
408.16 |
Completed. |
21 |
9/10, Upper O’Connell Street: Adaptations to |
|
|
|
|
|
|
|
accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,353.59 |
— |
2,353.59 |
do. |
151/127 of 75 |
Inishannon Customs Post, Monaghan: Supply and erection |
|
|
|
|
|
|
|
of timber structure |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
750.00 |
3,626.18 |
4,376.18 |
do. |
96 |
Muff Customs and Excise Station, Co. Donegal: |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,187.54 |
— |
3,187.54 |
Virtually completed. |
102 |
Earlsfort House: Installation of thermostats |
.. |
.. |
|
|
586.08 |
— |
586.08 |
Completed. |
133 |
Lansdowne House: Partitioning |
.. |
.. |
.. |
.. |
|
|
863.34 |
— |
863.34 |
do. |
171/116 of 76 |
Dundalk Customs Road Station: Erection of prefab, office |
|
|
2,404.79 |
3,000.00 |
5,404.79 |
do. |
146 |
Computer Centre, St. John’s Road: Provision of security |
|
|
|
|
|
|
|
hut and barrier |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
933.04 |
— |
933.04 |
In progress. |
180 |
10, Upper O’Connell Street: Partitioning of 1st Floor |
.. |
|
|
56.06 |
— |
56.06 |
do. |
103/26 of |
Cobh Custom and Excise, Co. Cork: Heating and lighting |
|
|
|
|
|
|
73/74 |
improvements |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
199.79 |
532.74 |
732.53 |
Completed. |
121/141 of 74 |
Roden House, Dundalk: Renovations |
.. |
.. |
.. |
|
|
131.37 |
1,519.82 |
1,651.19 |
do. |
|
Office of public works |
|
|
|
|
|
|
65 |
52, St. Stephen’s Green (3rd and 4th Floors): Provision of |
|
|
|
|
|
|
|
hand-dryers in ladies’ cloak-rooms |
.. |
.. |
.. |
|
|
245.95 |
— |
245.95 |
do. |
171/130 |
52, St. Stephen’s Green (3rd and 4th Floors): Accounts |
|
|
|
|
|
|
of 76 |
Branch Improvements |
.. |
.. |
.. |
.. |
.. |
|
|
108.10 |
1,392.22 |
1,500.32 |
do. |
77 |
51, St. Stephen’s Green: Improvements to file storage rooms |
|
|
259.58 |
— |
259.58 |
In progress. |
171/89 of 76 |
St. Stephen’s Green Park: Provision of prefab. office |
.. |
|
|
138.20 |
1,236.31 |
1,374.51 |
Completed. |
76 |
Cork City Hall: Stand for Science Exhibition |
.. |
.. |
|
|
2,731.83 |
— |
2,731.83 |
Virtually completed. |
171/114 of 76 |
Bonham Street Furniture Store: Electrical Works |
.. |
|
|
520.88 |
494.91 |
1,015.79 |
Completed. |
171/139 |
B.V.M. Park, Killarney, Superintendent’s Residence: |
|
|
|
|
|
|
of 76 |
Heating installation |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
486.00 |
864.00 |
1,350.00 |
Virtually completed. |
151/142 |
Furniture Division, Rathmines: Provision of canteen |
|
|
|
|
|
|
of 75 |
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
48.84 |
3,002.34 |
3,051.18 |
Completed. |
171/98 of 76 |
Phoenix Park: Provision of hut at Cabra gate |
.. |
.. |
|
|
339.89 |
1,869.37 |
2,209.26 |
do. |
27 |
Phoenix Park: Provision of new glasshouses |
.. |
.. |
|
|
4,394.50 |
— |
4,394.50 |
do. |
192 |
Phoenix Park: Furry Glen Tree planting scheme |
.. |
.. |
|
|
155.27 |
— |
155.27 |
In progress. |
49 |
Harbour Master’s House, Dún Laoghaire: Installation of |
|
|
|
|
|
|
|
oil-fired heating |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,607.12 |
— |
1,607.12 |
Completed. |
171/137 of 76 |
R.D.S. Ballsbridge: Erection of horticultural display stand |
|
|
64.05 |
307.84 |
371.89 |
do. |
151 |
R.D.S. Ballsbridge: Erection of horticultural display stand |
|
|
357.52 |
— |
357.52 |
do. |
|
Public service |
|
|
|
|
|
|
106 |
Computer Centre, Inchicore: Extension of Burglar Alarm |
|
|
|
|
|
|
|
System |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
779.71 |
— |
779.71 |
do. |
126 |
Computer Centre, Inchicore: Partitioning |
.. |
.. |
.. |
|
|
1,010.49 |
— |
1,010.49 |
do. |
139 |
Computer Centre, Inchicore: Security Works |
.. |
.. |
|
|
188.40 |
— |
188.40 |
In progress. |
125 |
Civil Service Commission, 1 Grand Canal Street: Provision |
|
|
|
|
|
|
|
of heating in reception area |
.. |
.. |
.. |
.. |
|
|
507.44 |
— |
507.44 |
do. |
141 |
Civil Service Commission, 1 Grand Canal Street: Improve- |
|
|
|
|
|
|
|
provement to lighting in reception area |
.. |
.. |
.. |
|
|
542.81 |
— |
542.81 |
do. |
Sub. No. |
Justice |
|
|
|
|
|
|
171/151 of 76 |
128, Lower Baggot Street: Improvements to rest-room and |
|
|
|
|
|
|
|
dining-room |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
78.17 |
184.16 |
262.33 |
Completed. |
171/131 of 76 |
Registry of Deeds: Provision of storage accommodation and |
|
|
|
|
|
|
|
improvements to kitchen |
.. |
.. |
.. |
.. |
.. |
|
|
178.69 |
1,137.93 |
1,316.62 |
In progress. |
151/12 of 75 |
Registry of Deeds: Adaptations |
.. |
.. |
.. |
.. |
|
|
46.51 |
2,596.54 |
2,643.05 |
Completed. |
45 |
Registry of Deeds: Transfer of Indexing Section and |
|
|
|
|
|
|
|
installation of Lift |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,868.54 |
— |
3,868.54 |
In progress. |
171/145 of 76 |
Public Records Office: Partitioning Room 20 |
.. |
.. |
|
|
377.84 |
147.58 |
525.42 |
Completed. |
171/149 of 76 |
Four Courts: Probate Office: Partitioning |
.. |
.. |
|
|
224.99 |
351.97 |
576.96 |
do. |
92 |
Four Courts: Improvements |
.. |
.. |
.. |
.. |
.. |
|
|
2,121.40 |
— |
2,121.40 |
do. |
138 |
Four Courts: Improvements to accommodation for Justice |
|
|
|
|
|
|
|
Costello |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
342.28 |
— |
342.28 |
do. |
140 |
Four Courts: Adaptations of Dean Swift Room in former |
|
|
|
|
|
|
|
Four Courts Hotel for use as Temporary Court Room |
.. |
|
|
1,290.53 |
— |
1,290.53 |
In progress. |
157 |
Four Courts: Improvements to Judge D’Arcy’s Room |
.. |
|
|
922.54 |
— |
922.54 |
Virtually completed. |
31 |
Land Registry: Public Records: Improvements to Fire |
|
|
|
|
|
|
|
Alarm System |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
526.64 |
— |
526.64 |
Completed. |
123 |
Land Registry: Improvements to ventilation in basement |
.. |
|
|
945.23 |
— |
945.23 |
Virtually completed. |
130 |
Land Registry: Improvements to rooms 22/23 |
.. |
.. |
|
|
428.10 |
— |
428.10 |
do. |
113 |
72/76 St. Stephen’s Green: Provision of security huts and |
|
|
|
|
|
|
|
alteration to barrier |
.. |
.. |
.. |
.. |
.. |
|
|
741.87 |
— |
741.87 |
Completed. |
54 |
39 St. Anne’s Lane: Installation of burglar alarm system |
.. |
|
|
1,405.95 |
— |
1,405.95 |
do. |
162 |
Welfare Office, Sligo: Provision of heating |
.. |
.. |
.. |
|
|
1,331.87 |
— |
1,331.87 |
Virtually completed. |
166 |
Courts of Justice: Improvements to Central Office |
.. |
|
|
209.43 |
— |
209.43 |
In progress. |
Sub. No. |
|
|
|
|
|
|
|
|
Environment |
|
|
|
|
|
|
171/94 of 76 |
O’Connell Bridge House: Partitioning (2nd, 10th and 11th |
|
|
|
|
|
|
|
Floors) |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
341.06 |
1,032.80 |
1,373.86 |
Completed. |
47 |
O’Connell Bridge House: Partitioning (3rd Floor) |
.. |
.. |
|
|
1,184.50 |
— |
1,184.50 |
do. |
39 |
Skibbereen Driving Test Centre: Toilet facilities |
.. |
.. |
|
|
576.22 |
— |
576.22 |
In progress. |
171/27 of 76 |
Driving Test Centre, Parkgate Hall, Conyngham Road: |
|
|
|
|
|
|
|
Double glazing of windows of Interview Room |
.. |
|
|
5.54 |
520.71 |
526.25 |
Completed. |
171/97 of 76 |
Driving Test Centre, 85, Ballymun Avenue: Fitting Out |
.. |
|
|
87.35 |
1,849.15 |
1,936.50 |
do. |
|
Education |
|
|
|
|
|
|
84/15 of |
Marlboro Street: Information Centre |
.. |
.. |
.. |
|
|
4,555.81 |
2,595.49 |
7,151.30 |
do. |
72/73 |
|
|
|
|
|
|
|
103 |
Marlboro Street: Security Works |
.. |
.. |
.. |
.. |
|
|
107.10 |
— |
107.10 |
In progress. |
144 |
Marlboro Street: Adaptations to accommodation |
.. |
|
|
667.44 |
— |
667.44 |
do. |
131 |
Marlboro Street: Provisions of Waiting Room |
.. |
.. |
|
|
150.68 |
— |
150.68 |
do. |
109 |
Marlboro Street: Fire precautionary works |
.. |
.. |
|
|
265.82 |
— |
265.82 |
do. |
151/76 of 75 |
Higher Education Authority: Fire precautionary works |
.. |
|
|
2,730.74 |
5,108.22 |
7,838.96 |
do. |
103/107 of 73/74 |
Limerick Model School: Accommodation for Inspectorate |
|
|
987.36 |
6,538.51 |
7,525.87 |
do. |
171/28 of |
Limerick Model School (Girls): Electrical and heating |
|
|
|
|
|
|
76 |
installations |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,879.40 |
1,710.00 |
4,589.40 |
do. |
171/132 of |
Training College Building, Marlboro Street: Improvements |
|
|
712.08 |
433.97 |
1,146.05 |
In progress. |
76 |
|
|
|
|
|
|
|
95 |
National Gallery: Provision of heaters |
.. |
.. |
.. |
|
|
799.62 |
— |
799.62 |
Completed. |
171/135 of |
National Gallery: Provision of Dark Room |
.. |
.. |
|
|
1,465.99 |
232.06 |
1,698.05 |
do. |
76 |
|
|
|
|
|
|
|
171/134 of |
National Gallery: Installation of frescoes in Room 1A |
.. |
|
|
314.37 |
134.24 |
448.61 |
Completed. |
76 |
|
|
|
|
|
|
|
128 |
National Museum: Provision of conference room |
.. |
|
|
350.00 |
— |
350.00 |
In progress. |
171/31 of |
Talbot House, Marlboro Street: Provision of double glazing |
|
|
15.69 |
1,515.18 |
1,530.87 |
Completed. |
76 |
|
|
|
|
|
|
|
|
Lands |
|
|
|
|
|
|
171/153 of |
21, Merrion Street: Alterations and Improvements to |
|
|
|
|
|
|
76 |
Luncheon Club |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
275.39 |
946.95 |
1,222.34 |
do. |
171/133 of |
83, Merrion Square: Provision of storage heating |
.. |
.. |
|
|
1,038.25 |
2,632.50 |
3,670.75 |
do. |
76 |
|
|
|
|
|
|
|
28 |
93 Merrion Square: Provision of toilet facilities |
.. |
.. |
|
|
62.92 |
— |
62.92 |
In progress. |
82 |
24, Upper Merrion Street: Provision of grilles on windows |
|
|
307.64 |
— |
307.64 |
Completed. |
81 |
Custom House, Galway: Installation of fluorescent lighting |
|
|
510.78 |
— |
510.78 |
do. |
171/107 of |
Mullingar: Erection of partitions, etc. |
.. |
.. |
.. |
|
|
62.62 |
1,200.00 |
1,262.62 |
do. |
76 |
|
|
|
|
|
|
|
|
Agriculture |
|
|
|
|
|
|
171/140 of |
Abbotstown Farm: Supply and erection of diesel storage |
|
|
|
|
|
|
76 |
tank |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
159.84 |
400.46 |
560.30 |
do. |
120 |
Abbotstown Farm: Research Laboratory: Pre-fab. building |
|
|
|
|
|
|
|
—provision of shower facilities |
.. |
.. |
.. |
.. |
|
|
1,614.97 |
— |
1,614.97 |
do. |
132 |
Abbotstown Farm: Research Laboratory: Improvements to |
|
|
|
|
|
|
|
piggeries |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
857.87 |
— |
857.87 |
In progress. |
101 |
Abbotstown Farm: Fencing |
.. |
.. |
.. |
.. |
.. |
|
|
2,975.30 |
— |
2,975.30 |
Completed. |
171/92 of |
Abbotstown Farm: Provision of window in office of Animal |
|
|
|
|
|
|
76 |
House |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9.28 |
719.80 |
729.03 |
do. |
171/36 of 76 |
Abbotstown Farm: Provision of cycle shed and weighbridge |
|
|
145.20 |
1,598.38 |
1,743.58 |
Completed. |
171/58 of 76 |
Backweston Farm: Extension to cottage |
.. |
.. |
.. |
|
|
94.81 |
1,729.26 |
1,824.07 |
do. |
67 |
Backweston Farm: Adaptations to granary |
.. |
.. |
|
|
239.99 |
— |
239.99 |
do. |
55 |
Backweston Farm: Improvements to silage plant |
.. |
.. |
|
|
2,068.24 |
— |
2,068.24 |
do. |
171/160 of |
Ballsbridge Veterinary College: Provision of cold room for |
|
|
|
|
|
|
76 |
Microbiology Unit |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
19.75 |
113.76 |
133.51 |
In progress. |
171/120 of |
Ballsbridge Veterinary College: Partitioning Immunology |
|
|
|
|
|
|
76 |
Laboratory |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
926.44 |
3,323.59 |
4,250.03 |
Completed. |
171/144 of |
Ballsbridge Veterinary College: Alterations and |
|
|
|
|
|
|
76 |
improvements in Rooms 12,13 |
.. |
.. |
.. |
.. |
.. |
|
|
273.67 |
666.77 |
940.44 |
do. |
171/88 of 76 |
Ballsbridge Veterinary College: Partitioning consulting room |
|
|
204.85 |
2,017.86 |
2,222.71 |
do. |
103/81 of |
Ballsbridge Veterinary College: Improved toilet and canteen |
|
|
|
|
|
|
73/74 |
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
15.86 |
3,578.99 |
3,594.85 |
do. |
171/85 of 76 |
Tipperary Veterinary Office: Electrical rewiring |
.. |
.. |
|
|
69.30 |
1,033.02 |
1,102.32 |
do. |
38 |
Ballyhaise Agricultural College: Superintendent’s House: |
|
|
|
|
|
|
|
Improvement to scullery |
.. |
.. |
.. |
.. |
.. |
|
|
1,290.00 |
— |
1,290.00 |
do. |
56 |
Ballyhaise Agricultural College: Improvements to heating |
|
|
|
|
|
|
|
in recreation area |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
418.49 |
— |
418.49 |
do. |
171/143 of 76 |
Ballyhaise Agricultural College: Improvements to kitchen |
|
|
1,541.52 |
692.16 |
2,233.68 |
Virtually completed. |
2 |
Ballyhaise Agricultural College: Erection of oil storage shed |
|
|
1,724.85 |
— |
1,724.85 |
Completed. |
156 |
Waterford Bovine T.B. Unit: Installation of fluorescent |
|
|
|
|
|
|
|
lighting |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
842.54 |
— |
842.54 |
do. |
42 |
Munster Institute: Electrical Installation in breeding house |
|
|
2,322.00 |
— |
2,322.00 |
do. |
93 |
Thorndale Veterinary Laboratory: Provision of nissen hut |
|
|
3,438.16 |
— |
3,438.16 |
In progress. |
41 |
Thorndale Veterinary Laboratory: Improvements to |
|
|
|
|
|
|
|
water supply |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
644.46 |
— |
644.46 |
Completed. |
43 |
Government Buildings: Provision of gateman’s hut |
.. |
|
|
1,617.04 |
— |
1,617.04 |
do. |
84 |
Kildalton College: Conversion of recreation hall |
|
|
|
|
|
|
|
to classrooms |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,687.34 |
— |
2,687.34 |
Completed. |
110 |
Claremoris Farm Development Office: Alterations to |
|
|
|
|
|
|
|
heating and lighting |
.. |
.. |
.. |
.. |
.. |
|
|
823.29 |
— |
823.29 |
Virtually completed. |
86 |
Loughrea Farm Development Office: Electrical and Heating |
|
|
|
|
|
|
|
works |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,081.50 |
— |
1,081.50 |
Completed. |
|
Labour |
|
|
|
|
|
|
58 |
Castlebar Manpower Service: Adaptations, etc. (Cavalry |
|
|
|
|
|
|
|
Barracks) |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,287.09 |
— |
1,287.09 |
do. |
62 |
Davitt House: Partitioning Room 13 |
.. |
.. |
.. |
|
|
817.80 |
— |
817.80 |
do. |
75 |
Davitt House: Security works |
.. |
.. |
.. |
.. |
|
|
1,043.92 |
— |
1,043.92 |
do. |
90 |
Placement Office, O’Connell Bridge House: Partitioning |
|
|
|
|
|
|
|
Works |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,501.21 |
— |
2,501.21 |
do. |
25 |
Placement Office, Cork: Partitioning |
.. |
.. |
.. |
|
|
684.95 |
— |
684.95 |
Virtually completed. |
23 |
Sligo Industrial Inspectorate: Electrical installations |
|
|
|
|
|
|
|
—19 Chapel Street |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,001.38 |
— |
1,001.38 |
Completed. |
|
Industry, Commerce and energy |
|
|
|
|
|
|
121/75 of 74 |
Kildare Street: Adaptations |
.. |
.. |
.. |
.. |
.. |
|
|
1,547.65 |
6,095.41 |
7,643.06 |
do. |
88 |
Price Line Office, Sligo: Electrical installations |
.. |
.. |
|
|
519.27 |
— |
519.27 |
do. |
104 |
14, Hume Street: Provision of sink unit |
.. |
.. |
.. |
|
|
302.03 |
— |
302.03 |
do. |
|
Tourism and transport |
|
|
|
|
|
|
171/67 of 76 |
26/27 Eden Quay: Mercantile Marine: Conversion of |
|
|
|
|
|
|
|
caretaker’s quarters to offices |
.. |
.. |
.. |
.. |
.. |
|
|
880.47 |
3,754.63 |
4,635.10 |
Virtually completed. |
|
Posts and telegraphs |
|
|
|
|
|
|
35 |
G.P.O., Dublin: Adaptations to former R.T.E. |
|
|
|
|
|
|
|
accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,170.80 |
— |
7,170.80 |
In progress. |
171/119 of 76 |
G.P.O., Dublin: Adaptations to 2nd floor |
.. |
.. |
.. |
|
|
658.99 |
2,040.87 |
2,699.86 |
Completed. |
98 |
G.P.O., Dublin: Partitioning on 2nd floor for storage |
.. |
|
|
1,193.78 |
— |
1,193.78 |
do. |
118 |
G.P.O., Dublin: Central Telegraph Office: Supply and |
|
|
|
|
|
|
|
erection of partitions |
.. |
.. |
.. |
.. |
.. |
|
|
2,000.00 |
— |
2,000.00 |
Virtually completed. |
124 |
G.P.O., Dublin: Improvements to basement storage area |
|
|
1,386.83 |
— |
1,386.83 |
In progress. |
71 |
St. John’s Road: Improvements to accommodation |
.. |
|
|
1,225.76 |
— |
1,225.76 |
Completed. |
89 |
Birr Post Office: Alterations |
.. |
.. |
.. |
.. |
.. |
|
|
5,805.00 |
— |
5,805.00 |
do. |
171/74 of 76 |
Athlone Post Office: Alterations |
.. |
.. |
.. |
.. |
|
|
4,696.80 |
766.60 |
5,463.40 |
do. |
151/68 of 75 |
Brian Boru Street Sorting Office, Cork: Improvements |
.. |
|
|
14.11 |
4,188.38 |
4,202.49 |
do. |
171/125 of 76 |
Clonakilty Post Office: Improvements |
.. |
.. |
.. |
|
|
1,530.00 |
1,800.00 |
3,330.00 |
Virtually completed. |
32 |
Ballymote Postmaster’s Residence: Provision of oil fired |
|
|
|
|
|
|
|
central heating |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,575.00 |
— |
1,575.00 |
do. |
33 |
Ballymote Postmaster’s Residence: Extension |
.. |
.. |
|
|
3,447.43 |
— |
3,447.43 |
Completed. |
108 |
Amiens Street, Parcels Office: Improvement to toilets |
.. |
|
|
3,607.27 |
— |
3,607.27 |
do. |
48 |
Central Sorting Office: Provision of security presses and |
|
|
|
|
|
|
|
wire mesh to conveyor |
.. |
.. |
.. |
.. |
.. |
|
|
467.08 |
— |
467.08 |
Virtually completed. |
84/72 of 72/73 |
Central Sorting Office: Dining Club improvements |
.. |
|
|
455.75 |
740.55 |
1,196.30 |
Completed. |
136 |
Ballsbridge Post Office: Partitioning |
.. |
.. |
.. |
|
|
699.31 |
— |
699.31 |
Virtually completed. |
103/115 of 73/74 |
Ballina Post Office: New floor in sorting office, etc. |
.. |
|
|
202.07 |
1,476.10 |
1,678.17 |
Completed. |
171/141 of 76 |
Crumlin Sorting Office: Removal of internal walls |
.. |
|
|
6.94 |
746.69 |
753.63 |
do. |
148 |
Kilkenny Area Stock Depot |
.. |
.. |
.. |
.. |
|
|
603.90 |
— |
603.90 |
In progress. |
37 |
Tuam Post Office: Alterations |
.. |
.. |
.. |
|
|
1,271.64 |
— |
1,271.64 |
Completed. |
161 |
Aldboro House: Improvements to staff canteen |
.. |
.. |
|
|
1,337.67 |
— |
1,337.67 |
In progress. |
190 |
Westport Post Office: Fire precautionary works |
.. |
.. |
|
|
896.24 |
— |
896.24 |
Completed. |
|
Defence |
|
|
|
|
|
|
151/33 of 75 |
General Headquarters, Parkgate Street: Adaptations to |
|
|
|
|
|
|
|
Communications Centre |
.. |
.. |
.. |
.. |
.. |
|
|
674.11 |
2,973.83 |
3,647.94 |
Virtually completed. |
171/148 of |
General Headquarters, Parkgate Street: Improvements to |
|
|
|
|
|
|
76 |
ladies’ toilets |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
357.30 |
483.08 |
840.38 |
Completed. |
105 |
General Headquarters, Parkgate Street: Provision of |
|
|
|
|
|
|
|
additional car parking facilities |
.. |
.. |
.. |
.. |
.. |
|
|
39.44 |
— |
39.44 |
In progress. |
168 |
General Headquarters, Parkgate Street: Installation of hand |
|
|
|
|
|
|
|
dryers |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,166.96 |
— |
1,166.96 |
do. |
69 |
Coláiste Caoimhin: Provision of ladies’ toilets on ground |
|
|
|
|
|
|
|
floor |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,639.85 |
— |
5,639.85 |
do. |
80 |
Coláiste Caoimhin: Accommodation for messenger staff |
.. |
|
|
318.59 |
— |
318.59 |
Completed. |
30 |
Civil Defence School, Phoenix Park: Supply and installation |
|
|
|
|
|
|
|
of intruder alarm system |
.. |
.. |
.. |
.. |
.. |
|
|
1,170.08 |
— |
1,170.08 |
do. |
|
Foreign affairs |
|
|
|
|
|
|
64 |
Iveagh House: Sound proofing partitions |
.. |
.. |
.. |
|
|
481.32 |
— |
481.32 |
do. |
112 |
Iveagh House: Provision of dishwasher |
.. |
.. |
.. |
|
|
1,838.40 |
— |
1,838.40 |
do. |
|
Social welfare |
|
|
|
|
|
|
171/95 of 76 |
D’Olier House: Improvements to lighting |
.. |
.. |
.. |
|
|
362.27 |
1,221.72 |
1,583.99 |
do. |
171/129 of 76 |
Thurles Employment Exchange: Adaptations and |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
649.91 |
1,277.06 |
1,926.97 |
do. |
66 |
Townsend Street: Provision of fluorescent fittings in toilets |
|
|
472.33 |
— |
472.33 |
do. |
91 |
Victoria Street Employment Exchange: Improvements |
.. |
|
|
1,297.98 |
— |
1,297.98 |
In progress. |
107 |
Cobh New Employment Exchange: Improvement works |
.. |
|
|
1,287.50 |
— |
1,287.50 |
do. |
169 |
North Cumberland Street Employment Exchange: |
|
|
|
|
|
|
|
Installation of hand dryers |
.. |
.. |
.. |
.. |
.. |
|
|
224.04 |
— |
224.04 |
do. |
151/113 of 75 |
Áras Mhic Dhiarmada: Improvement of storage |
|
|
|
|
|
|
|
accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,754.91 |
350.00 |
2,104.91 |
Completed. |
117 |
Áras Mhic Dhiarmada: Installation of fire alarm system |
.. |
|
|
3,443.72 |
— |
3,443.72 |
do. |
51 |
Bridge House, Bandon: Adaptations |
.. |
.. |
.. |
|
|
1,052.67 |
— |
1,052.67 |
do. |
115 |
Claremorris Social Welfare Office: Adaptations |
.. |
.. |
|
|
854.16 |
— |
854.16 |
do. |
155 |
Mullingar Social Welfare Office: Partitioning, etc. |
.. |
|
|
179.17 |
— |
179.17 |
do. |
99 |
Muine Bheag: Electrical Work |
.. |
.. |
.. |
.. |
|
|
278.10 |
— |
278.10 |
do. |
68 |
Athy (Meeting Lane): Electrical and heating works |
.. |
|
|
259.04 |
— |
259.04 |
do. |
|
Health |
|
|
|
|
|
|
151/88 of 75 |
Custom House, Dublin: Improvements to ladies’ cloakroom |
|
|
420.22 |
1,215.50 |
1,635.72 |
do. |
122 |
Custom House, Dublin: Improvements to Room No. 174 |
.. |
|
|
1,292.58 |
— |
1,292.58 |
Virtually completed. |
152 |
Custom House, Dublin: Alterations |
.. |
.. |
.. |
.. |
|
|
176.01 |
— |
176.01 |
In progress. |
DETAILS OF NO. 180—MINOR BALANCES OF EXPENDITURE
Work No. |
Service and Description |
Total Estimate |
Vote 1977 |
Expenditure |
Observations |
1977 |
To 31/12/76 |
To 31/12/77 |
|
|
£ |
£ |
£ |
£ |
£ |
|
Sub. No. |
|
|
|
|
|
|
|
|
Finance |
|
|
|
|
|
|
24 of 74 |
Tralee: New Government Offices |
.. |
.. |
.. |
.. |
|
|
433.44 |
26,299.03 |
26,732.47 |
Completed. |
17 of 76 |
Law Reform Commission: Accommodation |
.. |
.. |
|
|
213.69 |
22,198.74 |
22,412.43 |
do. |
18A of 76 |
Stationery Office, Beggars Bush: Improvements |
.. |
.. |
|
|
3,372.88 |
3,696.82 |
7,069.70 |
do. |
23 of 76 |
Letterkenny New Government Offices |
.. |
.. |
.. |
|
|
125.20 |
179,749.32 |
179,874.52 |
do. |
|
Revenue commissioners |
|
|
|
|
|
|
6 of 76 |
Provision of additional computer accommodation |
.. |
|
|
530.30 |
257,319.22 |
257,849.52 |
Completed. |
8 of 75 |
11-13 Upper O’Connell Street: Adaptations |
.. |
.. |
|
|
115.96 |
64,813.84 |
64,929.80 |
do. |
7 of 76 |
Áras Brugha: Adaptations |
.. |
.. |
.. |
.. |
|
|
2,494.64 |
100,620.62 |
103,115.26 |
do. |
|
Office of public works |
|
|
|
|
|
|
66 of 76 |
Dún Laoghaire Harbour: Multi-purpose Ship Facilities |
.. |
|
|
1,743.31 |
392,944.87 |
394,688.18 |
do. |
52 of 76 |
Shannon Navigation: Athlone New Office |
.. |
.. |
.. |
|
|
756.95 |
4,776.00 |
5,532.95 |
do. |
45 of 76 |
Shannon Navigation: Extension of Pier at Mountshannon |
|
|
504.20 |
46,148.45 |
46,652.65 |
do. |
58 of 76 |
National Monuments: Kilkenny District Depot: |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
229.48 |
1,127.46 |
1,356.94 |
do. |
|
Public service |
|
|
|
|
|
|
67 of 76 |
Provision of building for Computer—Stage 1 |
.. |
.. |
|
|
1,501.27 |
364,923.10 |
366,424.37 |
do. |
|
Justice |
|
|
|
|
|
|
77 of 76 |
Provision of alternative accommodation for Garda personnel |
|
|
|
|
|
|
|
at Dublin Castle |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,249.78 |
84,821.88 |
93,071.66 |
do. |
70 of 76 |
Garda Headquarters: Technical Bureau: Improvements |
.. |
|
|
22.92 |
41,005.21 |
41,028.13 |
do. |
47 of 74 |
Garda Training Centre Templemore: Adaptations etc. |
.. |
|
|
739.39 |
646,829.14 |
647,568.53 |
do. |
|
Education |
|
|
|
|
|
|
87 of 76 |
Dublin Preventive Centre, Finglas |
.. |
.. |
.. |
.. |
|
|
3,840.50 |
449,267.38 |
453,107.88 |
do. |
79A of 75 |
Central Model Schools: General improvements |
.. |
.. |
|
|
1,153.27 |
104,578.38 |
105,731.65 |
do. |
|
Lands |
|
|
|
|
|
|
89 of 76 |
Bray Forestry Offices: Adaptations |
.. |
.. |
.. |
.. |
|
|
79.92 |
30,526.76 |
30,606.68 |
do. |
Sub. No. |
Agriculture |
|
|
|
|
|
|
84A of 75 |
Botanic Gardens: Office and Toilet Accommodation |
.. |
|
|
1,022.47 |
15,200.00 |
16,222.47 |
Completed |
60 (1) of 73/74 |
Abbotstown Farm: New Laboratory Block |
.. |
.. |
|
|
1,903.28 |
165,064.67 |
166,967.95 |
do. |
|
Posts and telegraphs |
|
|
|
|
|
|
127 of 76 |
Lyon House, Dublin: Partitioning, etc. |
.. |
.. |
.. |
|
|
125.27 |
50,398.26 |
50,523.53 |
do. |
129A of 76 |
16/17 Princes Street (Holroyd and Jones Premises): |
|
|
|
|
|
|
|
Adaptations |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,195.40 |
9,235.30 |
12,430.70 |
do. |
86 of 74 |
Dundrum Computer Building |
.. |
.. |
.. |
.. |
|
|
325.00 |
99,123.39 |
99,448.39 |
do. |
|
Foreign affairs |
|
|
|
|
|
|
162 of 76 |
Embassy at Madrid: Fitting out of new offices |
.. |
.. |
|
|
27.07 |
14,773.64 |
14,800.71 |
do. |
155 of 76 |
U.N. Mission, New York: Fitting out of new offices |
.. |
|
|
110.07 |
46,166.35 |
46,276.42 |
do. |
156 of 76 |
Embassy at Luxembourg: Fitting out for occupation |
.. |
|
|
201.13 |
53,863.18 |
54,064.31 |
do. |
165 of 76 |
Consulate General at Boston: Fitting out of new offices |
.. |
|
|
415.51 |
15,640.93 |
16,056.44 |
do. |
166 of 76 |
Consulate General at Chicago: Fitting out of new offices |
|
|
437.98 |
3,976.40 |
4,414.38 |
do. |
|