APPENDIX 13
STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1976 (VOTE 9: SUBHEAD E)
Work No. |
Service and Description |
Total Estimate |
Vote 1976 |
Expenditure |
Observations |
1976 |
To 31/12/75 |
To 31/12/76 |
|
|
£ |
£ |
£ |
£ |
£ |
|
|
President: |
|
|
|
|
|
|
1 |
Aras an Uachtaráin: Improvements |
.. |
.. |
.. |
20,000·00 |
20,000·00 |
587·65 |
— |
587·65 |
In progress. |
|
|
|
|
587·65 |
|
|
|
|
Oireachtas: |
|
|
|
|
|
|
2 (1) |
Leinster House: Installation of Standby Generator (in |
|
|
|
|
|
|
|
combination with No. 15). |
.. |
.. |
.. |
.. |
.. |
|
15,000·00 |
|
21·25 |
21·25 |
In planning. |
2 (2) |
Leinster House: Additional Accommodation |
.. |
.. |
|
10,000·00 |
— |
96·63 |
96·63 |
Under consideration. |
2 (3) |
Leinster House: Reallocation of space and refurbishing |
.. |
|
5,000·00 |
5,028·19 |
2,772·98 |
7,801·17 |
In progress. |
|
|
|
|
5,028·19 |
|
|
|
|
Taoiseach: |
|
|
|
|
|
|
3 |
State Apartments: Adaptation of former Stamping Branch |
|
|
|
|
|
|
|
premises |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
10,000·00 |
— |
2,640·00 |
2,640·00 |
Deferred. |
|
Finance: |
|
|
|
|
|
|
4 |
Fitting out of Office premises for occupation |
.. |
.. |
|
850,000·00 |
896,058·72 |
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
Grattan Court/No. 1 Grand Canal St. |
.. |
.. |
.. |
|
|
5,701·13 |
87,149·91 |
92,851·04 |
Virtually completed. |
|
Ossian House, Pearse Street |
.. |
.. |
.. |
.. |
.. |
|
|
15,982·71 |
128,590·00 |
144,572·71 |
In progress. |
|
Earlsfort House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
23,622·29 |
254,728·08 |
278,350·37 |
Virtually completed. |
|
52 St. Stephen’s Green |
.. |
.. |
.. |
.. |
.. |
|
|
39,057·43 |
94,253·74 |
133,311·17 |
Virtually completed. |
|
Bishop St. premises (Jacobs) |
.. |
.. |
.. |
.. |
.. |
|
|
6,831·23 |
14,531·79 |
21,363·02 |
Completed. |
|
D’Olier House |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,569·38 |
76,066·60 |
83,635·98 |
do. |
|
Osmond House, Little Ship St. |
.. |
.. |
.. |
.. |
|
|
16,924·67 |
74,587·35 |
91,512·02 |
Virtually completed. |
|
44/45 St. Stephen’s Green |
.. |
.. |
.. |
.. |
.. |
|
|
191·58 |
26,688·75 |
26,880·33 |
do. |
|
Castle House, George’s St. |
.. |
.. |
.. |
.. |
.. |
|
|
39,778·87 |
68,278·40 |
108,057·27 |
Completed. |
|
Ardee Road, Rathmines |
.. |
.. |
.. |
.. |
.. |
|
|
65,122·89 |
63,238·25 |
128,361·14 |
In progress. |
|
Sackville Place (2 floors) |
.. |
.. |
.. |
.. |
.. |
|
|
46,665·34 |
— |
46,665·34 |
do. |
|
Lyon House, O’Connell Street |
.. |
.. |
.. |
.. |
|
|
33,580·46 |
84,817·60 |
118,398·06 |
do. |
|
Townsend Street |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
27,305·92 |
90,303·51 |
117,609·43 |
do. |
|
Setanta Building, Kildare St. |
.. |
.. |
.. |
.. |
.. |
|
|
225,041·99 |
16,498·32 |
241,540·31 |
do. |
|
Clanwilliam Court (Block 1) |
.. |
.. |
.. |
.. |
.. |
|
|
36,557·99 |
28,112·02 |
64,670·01 |
Virtually completed. |
|
Earl House, Dundalk |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
13,456·48 |
37,959·40 |
51,415·88 |
In progress. |
|
Hibernian House, Eyre Sq., Galway |
.. |
.. |
.. |
.. |
|
|
3,340·81 |
15,613·56 |
18,954·37 |
Virtually completed. |
|
Sarsfield House, Limerick |
.. |
.. |
.. |
.. |
.. |
|
|
39,047·03 |
34,841·48 |
73,888·51 |
do. |
|
Norwich Union House, Dawson St. |
.. |
.. |
.. |
.. |
|
|
11,998·09 |
12,196·64 |
24,194·73 |
Completed. |
|
Pearse St., Athlone |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,640·60 |
2,941·67 |
7,582·27 |
do. |
|
49 St. Stephen’s Green |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,021·60 |
1,232·22 |
4,253·82 |
do. |
|
Grattan House, Lower Mount St. |
.. |
.. |
.. |
.. |
|
|
28,375·66 |
6,941·26 |
35,316·92 |
Virtually completed. |
|
Clanwilliam Court (Block 3) |
.. |
.. |
.. |
.. |
.. |
|
|
43,529·20 |
15,455·00 |
58,984·20 |
Completed. |
|
A.C.C. Building, Hatch St. |
.. |
.. |
.. |
.. |
.. |
|
|
4,391·28 |
2,687·63 |
7,078·91 |
do. |
|
19/22 Dame St. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
12,810·79 |
— |
12,810·79 |
do. |
|
Wicklow House, Georges St. |
.. |
.. |
.. |
.. |
|
|
48,999·70 |
— |
48,999·70 |
In progress. |
|
Setanta Building, Nassau St. |
.. |
.. |
.. |
.. |
.. |
|
|
56,597·27 |
— |
56,597·27 |
do. |
|
Sligo Revenue Offices (temporary) |
.. |
.. |
.. |
.. |
|
|
16,333·61 |
— |
16,333·61 |
Completed. |
|
Thurles Revenue Offices (temporary) |
.. |
.. |
.. |
|
|
7,479·09 |
— |
7,479·09 |
do. |
|
Wexford Income Tax Offices |
.. |
.. |
.. |
.. |
.. |
|
|
346·79 |
9,908·19 |
10,254·98 |
do. |
|
Hawkins House (1st floor) |
.. |
.. |
.. |
.. |
.. |
|
|
2748·97 |
— |
2,748·97 |
In progress. |
|
Credit Union Building, Mallow |
.. |
.. |
.. |
.. |
|
|
3,007·71 |
— |
3,007·71 |
do. |
|
51 St. Stephen’s Green (ground and 2nd floors) |
.. |
.. |
|
|
6,000·16 |
— |
6,000·16 |
In progress. |
5 |
New Revenue Offices, Dublin Castle |
.. |
.. |
.. |
1,600,000·00 |
85,000·00 |
59,457·71 |
1,413,668·67 |
1,473,126·38 |
Completed. |
6 |
Revenue Commissioners: Provision of additional computer |
|
|
|
|
|
|
|
accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
260,000·00 |
6,000·00 |
4,884·11 |
252,435·11 |
257,319·22 |
do. |
7 |
Revenue Commissioners: Aras Brugha: Adaptations |
.. |
96,000·00 |
3,000·00 |
7,511·39 |
93,109·23 |
100,620·62 |
do. |
8 |
Clones (Clondergole): New Frontier Customs Post |
.. |
.. |
15,000·00 |
15,000·00 |
— |
— |
— |
In progress. |
9 |
Monaghan: New Customs Road Station |
.. |
.. |
.. |
122,000·00 |
110,000·00 |
116,392·37 |
13,933·45 |
130,325·82 |
Virtually completed. |
10 |
Carrigans: New Frontier Customs Post |
.. |
.. |
.. |
14,000·00 |
1,000·00 |
— |
— |
— |
Deferred. |
11 |
Blacklion Frontier Customs Post, Stage 2 |
.. |
.. |
.. |
|
10,000·00 |
— |
— |
— |
In planning. |
12 |
Dundalk Customs Road Station: Enlargement |
.. |
.. |
|
10,000·00 |
5,387·50 |
— |
5,387·50 |
In progress. |
13 |
Government Buildings: New Lifts |
.. |
.. |
.. |
.. |
35,000·00 |
30,000·00 |
— |
— |
— |
In planning. |
14 |
Government Buildings: Adaptations to South Block |
.. |
325,000·00 |
260,000·00 |
185,980·33 |
64,883·09 |
250,863·42 |
In progress. |
15 |
Government Buildings: Installation of Standby Generator |
|
|
|
|
|
|
|
(in combination with No. 2 (1)) |
.. |
.. |
.. |
.. |
|
15,000·00 |
— |
— |
— |
In planning. |
16 |
Dublin Castle: New Lift |
.. |
.. |
.. |
.. |
.. |
10,000·00 |
7,000·00 |
— |
— |
— |
Under consideration. |
17 |
Law Reform Commission: Accommodation |
.. |
.. |
33,000·00 |
26,000·00 |
15,198·74 |
7,000·00 |
22,198·74 |
Completed. |
18 |
15 Merrion Square: Adaptations |
.. |
.. |
.. |
.. |
85,000·00 |
10,000·00 |
3,054·09 |
12,049·23 |
15,103·32 |
In progress. |
18A |
Stationery Office, Beggar’s Bush: Improvements |
.. |
.. |
8,500·00 |
|
3,696·82 |
— |
3,696·82 |
Virtually completed. |
19 |
Ordnance Survey: New Printing Building |
.. |
.. |
.. |
285,000·00 |
45,000·00 |
79,700·10 |
241,216·25 |
320,916·35 |
do. |
20 |
Ordnance Survey: Improvement of Residential Quarters |
.. |
36,000·00 |
20,000·00 |
276·90 |
6·57 |
283·47 |
Contract placed. |
21 |
Ordnance Survey: Provision of Canteen Facilities |
.. |
.. |
7,000·00 |
6,000·00 |
3,301·20 |
— |
3,301·20 |
In progress. |
22 |
Drogheda New Government Offices |
.. |
.. |
.. |
.. |
131,000·00 |
9,000·00 |
4,973·15 |
121,447·68 |
126,420·83 |
Completed. |
23 |
Letterkenny New Government Offices |
.. |
.. |
.. |
183,000·00 |
4,500·00 |
871·59 |
178,877·73 |
179,749·32 |
do. |
24 |
Mullingar New Government Offices |
.. |
.. |
.. |
.. |
230,000·00 |
50,000·00 |
— |
— |
— |
In planning. |
25 |
Navan New Government Offices |
.. |
.. |
.. |
.. |
|
10,000·00 |
142·56 |
— |
142·56 |
Under consideration. |
26 |
Roscommon New Government Offices |
.. |
.. |
.. |
36,000·00 |
13,500·00 |
7,139·97 |
22,424·00 |
29,563·97 |
Completed. |
27 |
Waterford New Government Offices |
.. |
.. |
.. |
250,000·00 |
50,000·00 |
18,322·45 |
613·98 |
18,936·43 |
In progress. |
28 |
Ballyshannon New Government Offices |
.. |
.. |
.. |
12,000·00 |
12,000·00 |
7,200·00 |
— |
7,200·00 |
Completed. |
29 |
State Laboratory: Additional Accommodation |
.. |
.. |
80,000·00 |
65,000·00 |
5,495·98 |
3,078·55 |
8,574·53 |
In progress. |
30 |
Premises at Earlsfort Terrace: Adaptation for Concert Hall |
|
|
|
|
|
|
|
purposes |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
50,000·00 |
4,383·13 |
— |
4,383·13 |
In planning. |
30A |
Garden of Remembrance: Inscription on back wall |
.. |
|
|
696·08 |
6,385·34 |
7,081·42 |
In progress. |
31 |
Restoration of Royal Hospital, Kilmainham (Stage 11) |
.. |
|
100,000·00 |
53,842·74 |
40,303·42 |
94,146·16 |
do. |
32 |
Scoil Éanna, Rathfarnham: Restoration of Buildings (Stage |
|
|
|
|
|
|
|
11) |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
90,000·00 |
50,000·00 |
27,208·20 |
525·00 |
27,733·20 |
do. |
33 |
Scoil Éanna, Rathfarnham: Natural History Exhibition |
|
|
|
|
|
|
|
Centre, Garages, Stores, etc. |
.. |
.. |
.. |
.. |
10,000·00 |
10,000·00 |
150·76 |
415·23 |
565·99 |
In planning. |
34 |
Killarney National Park (including B.V.M. Park): Muckross |
|
|
|
|
|
|
|
House: Sanitary Services |
.. |
.. |
.. |
.. |
.. |
70,000·00 |
40,000·00 |
29,101·10 |
3,715·48 |
32,816·58 |
In progress. |
35 |
Killarney National Park (including B.V.M. Park): Muckross |
|
|
|
|
|
|
|
House: Improvements |
.. |
.. |
.. |
.. |
.. |
|
6,000·00 |
346·18 |
— |
346·18 |
In planning. |
36 |
Killarney National Park (including B.V.M. Park): Roads |
|
|
|
|
|
|
|
Development |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
40,000·00 |
12,000·00 |
5,040·25 |
4,067·64 |
9,107·89 |
Partly completed. |
37 |
Killarney National Park (including B.V.M. Park): |
|
|
|
|
|
|
|
Developments at Gearhameen |
.. |
.. |
.. |
.. |
.. |
40,000·00 |
25,000·00 |
— |
— |
— |
In planning. |
38 |
Kilkenny Castle: Restoration of Picture Gallery Wing |
.. |
230,000·00 |
45,000·00 |
129,701·02 |
190,843·33 |
320,544·35 |
Virtually completed |
39 |
Phoenix Park: New Park Offices |
.. |
.. |
.. |
.. |
8,000·00 |
2,000·00 |
3,220·31 |
5,018·75 |
8,239·06 |
Completed. |
40 |
Phoenix Park: Public Toilets |
.. |
.. |
.. |
.. |
.. |
|
10,000·00 |
— |
— |
— |
Under consideration. |
41 |
Phoenix Park Extension (Islandbridge Park): General |
|
|
|
|
|
|
|
Development |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
80,000·00 |
20,000·00 |
186·38 |
42,123·40 |
42,309·78 |
Balance of work under review. |
42 |
Glenveagh, Co. Donegal: Car Parks |
.. |
.. |
.. |
|
8,000·00 |
— |
— |
— |
Deferred. |
43 |
Shannon Navigation: General Improvements |
.. |
.. |
120,000·00 |
17,000·00 |
4,613·81 |
105,171·72 |
109,785·53 |
In progress. |
44 |
Shannon Navigation: New Jetty at Hodson Bay |
.. |
.. |
55,000·00 |
25,000·00 |
319·32 |
373·94 |
693·26 |
In planning. |
45 |
Shannon Navigation: Extension of Pier at Mountshannon |
43,000·00 |
2,000·00 |
1,443·97 |
44,704·48 |
46,148·45 |
Completed. |
46 |
Shannon Navigation: Rossmore Quay Improvements |
.. |
20,000·00 |
8,000·00 |
9,092·98 |
11,773·55 |
20,866·53 |
Virtually completed. |
47 |
Shannon Navigation: Portumna Castle: New Harbour |
.. |
35,000·00 |
5,000·00 |
846·89 |
— |
846·89 |
In planning. |
48 |
Shannon Navigation: Lanesboro: New Wharf |
.. |
.. |
10,000·00 |
2,000·00 |
— |
28·35 |
28·35 |
do. |
49 |
Shannon Navigation: Meelick Quay: Improvements |
.. |
11,000·00 |
10,000·00 |
14,607·61 |
— |
14,607·61 |
Virtually completed. |
50 |
Shannon Navigation: Albert Lock, New Jetty |
.. |
.. |
8,000·00 |
4,000·00 |
— |
— |
— |
In planning. |
51 |
Shannon Navigation: Lough Allen Canal: Restoration |
.. |
30,000·00 |
25,000·00 |
10,140·66 |
— |
10,140·66 |
In progress. |
52 |
Shannon Navigation: Athlone New Offices |
.. |
.. |
7,500·00 |
7,500·00 |
4,776·00 |
— |
4,776·00 |
Completed. |
53 |
Shannon Navigation: New Store at Roosky |
.. |
.. |
5,000·00 |
5,000·00 |
— |
— |
— |
In progress. |
54 |
Ballinamore and Ballyconnell Canal: Survey |
.. |
.. |
9,000·00 |
2,000·00 |
870·98 |
8,740·02 |
9,611·00 |
do. |
54A |
National Monuments: Dunmore Cave Visitor Centre |
.. |
28,000·00 |
— |
4,101·90 |
30,336·04 |
34,437·94 |
do. |
55 |
National Monuments: Clonmacnoise Visitor Centre |
.. |
72,000·00 |
5,000·00 |
51·08 |
6,732·05 |
6,783·13 |
do. |
56 |
National Monuments: Cahir Castle Visitor and Exhibition |
|
|
|
|
|
|
|
Centre |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
16,000·00 |
8,000·00 |
7,754·78 |
9,855·55 |
17,610·33 |
do. |
57 |
National Monuments: Rock of Cashel Visitor Centre |
.. |
37,500·00 |
18,500·00 |
15,732·37 |
20,061·23 |
35,793·60 |
do. |
58 |
National Monuments: Kilkenny District Depot |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
15,000·00 |
7,000·00 |
160·62 |
966·84 |
1,127·46 |
do. |
59 |
National Monuments: Sligo District New Depot |
.. |
.. |
20,000·00 |
5,000·00 |
— |
— |
— |
Under consideration. |
60 |
National Monuments: Galway District New Depot |
.. |
40,000·00 |
10,000·00 |
— |
1,921·50 |
1,921·50 |
do. |
61 |
National Monuments: Kerry District New Depot |
.. |
.. |
20,000·00 |
2,000·00 |
— |
— |
— |
do. |
62 |
National Monuments: Mallow District New Depot |
.. |
|
1,000·00 |
— |
— |
— |
do. |
63 |
National Monuments: Trim District New Depot |
.. |
.. |
15,000·00 |
5,000·00 |
729·13 |
— |
729·13 |
do. |
64 |
Clare Island: Harbour Improvements |
.. |
.. |
.. |
154,500·00 |
100,000·00 |
18·00 |
40,805·69 |
40,823·69 |
In progress. |
65 |
Innisbofin, Co. Galway: Harbour Improvements |
.. |
.. |
14,000·00 |
14,000·00 |
— |
— |
— |
Under consideration. |
66 |
Dún Laoghaire Harbour: Multi-purpose Ship Facilities |
.. |
379,000·00 |
42,000·00 |
63,476·16 |
329,468·71 |
392,944·87 |
Completed. |
66B |
3, Exchange Court: Clearance of Site |
.. |
.. |
.. |
— |
— |
200·00 |
— |
200·00 |
In progress. |
|
|
|
|
1,817,858·09 |
|
|
|
|
Public Service: |
|
|
|
|
|
|
67 |
Provision of building for Computer—Stage 1 |
.. |
.. |
367,000·00 |
12,000·00 |
10,506·58 |
354,416·52 |
364,923·10 |
Completed. |
68 |
Provision of building for Computer—Stage 2 |
.. |
.. |
600,000·00 |
350,000·00 |
95,229·08 |
— |
95,229·08 |
In progress. |
69 |
New Premises for the Institute of Public Administration and |
|
|
|
|
|
|
|
|
the Department of the Public Service Training Centre |
.. |
1,500,000·00 |
50,000·00 |
6,996·88 |
56,894·96 |
63,891·84 |
In planning. |
|
|
|
|
112,732·54 |
|
|
|
|
Justice: |
|
|
|
|
|
|
70 |
Garda Headquarters: Technical Bureau: Improvements |
.. |
70,000·00 |
5,000·00 |
1,975·13 |
39,030·08 |
41,005·21 |
Completed. |
71 |
Garda Headquarters: Accommodation for the Garda Band |
32,000·00 |
21,000·00 |
19,061·24 |
10,890·00 |
29,951·24 |
Virtually completed. |
72 |
Garda Headquarters: Transport Garage and Stores: |
|
|
|
|
|
|
|
Extension and improvements |
.. |
.. |
.. |
.. |
.. |
|
10,000·00 |
— |
— |
— |
In planning. |
73 |
Garda Headquarters: Provision of Standby Generator and |
|
|
|
|
|
|
|
Ancillary Works |
.. |
.. |
.. |
.. |
.. |
.. |
40,000·00 |
35,000·00 |
— |
— |
— |
do. |
74 |
Garda Training Centre, Templemore: Swimming Pool: |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
|
10,000·00 |
640·17 |
— |
640·17 |
do. |
75 |
Garda Stations: Erection of new buildings and major |
|
|
|
|
|
|
|
improvement schemes |
.. |
.. |
.. |
.. |
.. |
.. |
|
800,000·00 |
918,983·69 |
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
Dublin Metropolitan Division: |
|
|
|
|
|
|
|
Ballyfermot |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,896·53 |
11,475·00 |
15,371·53 |
Completed. |
|
Cabra |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
817·64 |
— |
817·64 |
In progress. |
|
Finglas |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,015·30 |
— |
1,015·30 |
In planning. |
|
Mountjoy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
17,660·00 |
85,014·13 |
102,674·13 |
Completed. |
|
Store Street |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
14,582·00 |
179,470·70 |
194,052·70 |
do. |
|
Co. Dublin: |
|
|
|
|
|
|
|
Blanchardstown |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
700·00 |
11,010·00 |
11,710·00 |
Completed. |
|
Howth |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
265·28 |
12,249·03 |
12,514·31 |
do. |
|
Irishtown |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,414·33 |
— |
4,414·33 |
In planning. |
|
Lucan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
116·35 |
— |
116·35 |
Under consideration. |
|
Swords |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
48,846·33 |
1,494·50 |
50,340·83 |
In progress. |
|
Co. Clare: |
|
|
|
|
|
|
|
Broadford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
16,200·00 |
— |
16,200·00 |
In progress. |
|
Corofin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
17,635·00 |
4,500·00 |
22,135·00 |
Virtually completed. |
|
Tulla |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
12,600·00 |
— |
12,600·00 |
In progress. |
|
Co. Cork: |
|
|
|
|
|
|
|
Carrignavar |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
11,617·74 |
7,200·00 |
18,817·74 |
do. |
|
Inchigeela |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9,591·82 |
3,600·00 |
13,191·82 |
Virtually completed. |
|
Kanturk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,013·18 |
51·56 |
7,064·74 |
Contract placed. |
|
Midleton |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,376·00 |
5,310·00 |
8,686·00 |
Virtually completed. |
|
Millstreet |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
25,831·09 |
— |
25,831·09 |
do. |
|
Skibbereen |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,460·00 |
13,411·45 |
19,871·45 |
do. |
|
Co. Donegal: |
|
|
|
|
|
|
|
Ballyshannon |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
23,067·25 |
60,544·86 |
83,612·11 |
Virtually completed. |
|
Bunbeg |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,023·02 |
9,055·00 |
10,078·02 |
Completed. |
|
Castlefin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,837·00 |
— |
4,837·00 |
Virtually completed. |
|
Culdaff |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,700·00 |
13,500·00 |
16,200·00 |
Completed. |
|
Letterkenny |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,119·13 |
— |
2,119·13 |
Virtually completed. |
|
Lifford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
56·65 |
— |
56·65 |
In planning. |
|
Newtowncunningham |
.. |
.. |
.. |
.. |
.. |
|
|
5,250·00 |
— |
5,250·00 |
Completed. |
|
Raphoe |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,445·00 |
12,810·26 |
15,255·26 |
do. |
|
Co. Galway: |
|
|
|
|
|
|
|
Kiltullagh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,152·00 |
7,200·00 |
15,352·00 |
Completed. |
|
Rosmuc |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
739·00 |
17,856·59 |
18,595·59 |
do. |
|
Co. Kerry: |
|
|
|
|
|
|
|
Ardfert |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,799·12 |
10,800·00 |
13,599·12 |
In progress. |
|
Fenit |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,200·00 |
— |
7,200·00 |
do. |
|
Co. Kildare: |
|
|
|
|
|
|
|
Clane |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
570·00 |
12,690·12 |
13,260·12 |
Completed. |
|
Kill |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,500·00 |
— |
4,500·00 |
In progress. |
|
Naas |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
13,550·91 |
25,412·00 |
38,962·91 |
Completed. |
|
Co. Kilkenny: |
|
|
|
|
|
|
|
Graiguenamanagh |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
570·00 |
13,855·59 |
14,425·59 |
do. |
|
Co. Laois: |
|
|
|
|
|
|
|
Portlaoise |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
23,117·83 |
4,397·34 |
27,515·17 |
In progress. |
|
Co. Leitrim: |
|
|
|
|
|
|
|
Ballinamore |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,125·00 |
— |
7,125·00 |
Virtually completed. |
|
Co. Limerick: |
|
|
|
|
|
|
|
Limerick City: Divisional Headquarters |
.. |
.. |
.. |
|
|
252,166·25 |
202,387·28 |
454,553·53 |
In progress. |
|
Askeaton |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
475·00 |
12,405·13 |
12,880·13 |
Completed. |
|
Bruree |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,362·73 |
16,128·41 |
17,491·14 |
do. |
|
Croom |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,873·95 |
20,900·00 |
26,773·95 |
do. |
|
Newcastlewest |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,656·92 |
64·05 |
5,720·97 |
In planning. |
|
Co. Longford: |
|
|
|
|
|
|
|
Ballinalee |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
18,540·00 |
— |
18,540·00 |
Virtually completed. |
|
Granard |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
88,372·10 |
5,397·13 |
93,769·23 |
Do. |
|
Co. Louth: |
|
|
|
|
|
|
|
Blackrock |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
10,619·96 |
— |
10,619·96 |
Completed. |
|
Dundalk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,772·38 |
— |
5,772·38 |
In planning. |
|
Omeath |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,500·00 |
— |
4,500·00 |
In progress. |
|
Co. Mayo: |
|
|
|
|
|
|
|
Kilkelly |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,874·12 |
19,350·00 |
21,224·12 |
Virtually completed. |
|
Co. Meath: |
|
|
|
|
|
|
|
Enfield |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
11,160·00 |
— |
11,160·00 |
In progress. |
|
Co. Monaghan: |
|
|
|
|
|
|
|
Castleblayney |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
14,745·28 |
2,000·00 |
16,745·28 |
do. |
|
Clones |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
16,178·95 |
— |
16,178·95 |
Virtually completed. |
|
Emyvale |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,186·64 |
6,550·00 |
7,736·64 |
Completed. |
|
Monaghan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,868·50 |
— |
3,868·50 |
In planning. |
|
Co. Offaly: |
|
|
|
|
|
|
|
Shannonbridge |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,225·00 |
16,100·40 |
19,325·40 |
Completed. |
|
Co. Roscommon: |
|
|
|
|
|
|
|
Castlerea |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
40,689·83 |
2,653·68 |
43,343·51 |
In progress. |
|
Knockcroghery |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,150·00 |
15,342·00 |
18,492·00 |
Completed. |
|
Roscommon |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,100·00 |
— |
8,100·00 |
In progress. |
|
Co. Sligo: |
|
|
|
|
|
|
|
Cliffony |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,520·00 |
— |
2,520·00 |
do. |
|
Sligo |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,563·97 |
— |
8,563·97 |
do. |
|
Co. Tipperary: |
|
|
|
|
|
|
|
Cloughjordan |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,922·63 |
13,680·00 |
20,602·63 |
Virtually completed. |
|
Emly |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
12,090·00 |
9,000·00 |
21,090·00 |
do. |
|
Newport |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
16,200·00 |
— |
16,200·00 |
do. |
|
Co. Waterford: |
|
|
|
|
|
|
|
Portlaw |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
25·50 |
12,502·77 |
12,528·27 |
Completed. |
|
Co. Westmeath: |
|
|
|
|
|
|
|
Ballinacargy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,830·00 |
14,955·00 |
18,785·00 |
do. |
|
Ballinahown |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,520·00 |
15,243·00 |
18,763·00 |
do. |
|
Kinnegad |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
380·00 |
12,013·92 |
12,393·92 |
do. |
|
Co. Wexford: |
|
|
|
|
|
|
|
Bunclody |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
380·00 |
12,715·13 |
13,095·13 |
do. |
|
Carrick-on-Bannow |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,100·00 |
— |
8,100·00 |
In progress. |
|
Clonroche |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
950·00 |
11,850·00 |
12,800·00 |
Completed. |
|
Duncannon |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
15,750·00 |
— |
15,750·00 |
Virtually completed. |
|
Rosslare Pier |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
19,475·00 |
— |
19,475·00 |
do. |
|
Rosslare Strand |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,841·11 |
11,350·00 |
13,191·11 |
Completed. |
|
Co. Wicklow: |
|
|
|
|
|
|
|
Blessington |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
8,233·17 |
— |
8,233·17 |
In progress. |
|
Carnew |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
224·20 |
13,385·26 |
13,609·46 |
Completed. |
76 |
Garda Stations: Minor Improvement Schemes |
.. |
.. |
|
150,000·00 |
97,110·85 |
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
Sub No. |
Dublin Metropolitan Division: |
|
|
|
|
|
|
23 |
Bridewell |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,036·65 |
— |
1,036·65 |
Completed. |
70/91 of 75 |
Cabra |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
280·25 |
1,363·15 |
1,643·40 |
do. |
57 |
Clontarf |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,144·92 |
— |
5,144·92 |
do. |
70/92 of 75 |
Crumlin: Improvements to central heating |
.. |
.. |
.. |
|
|
368·74 |
1,729·50 |
2,098·24 |
do. |
14 |
Crumlin: Reglazing of windows |
.. |
.. |
.. |
.. |
|
|
1,211·13 |
— |
1,211·13 |
do. |
85 |
Crumlin: Alterations to accommodation |
.. |
.. |
.. |
|
|
1,134·73 |
— |
1,134·73 |
Virtually completed. |
82 |
Crumlin: Improvements to security |
.. |
.. |
.. |
.. |
|
|
797·08 |
— |
797·08 |
do. |
70/57 of 75 |
Fitzgibbon St.: Fitting out of basement as gymnasium |
.. |
|
|
1,273·14 |
4,340·49 |
5,613·63 |
Completed. |
41 |
Fitzgibbon St.: Improvements to security |
.. |
.. |
.. |
|
|
819·10 |
— |
819·10 |
do. |
40 |
Garda Headquarters, Phoenix Park: Partitioning of Room 69 |
|
|
1,050·81 |
— |
1,050·81 |
do. |
44 |
Garda Headquarters, Phoenix Park: Provision of storage |
|
|
|
|
|
|
|
space |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
158·43 |
— |
158·43 |
do. |
50 |
Garda Headquarters, Phoenix Park: Provision of floor bases |
|
|
|
|
|
|
|
for precision instruments |
.. |
.. |
.. |
.. |
.. |
|
|
111·55 |
— |
111·55 |
In progress. |
67 |
Garda Headquarters, Phoenix Park: Partitioning of Mess |
|
|
89·32 |
— |
89·32 |
do. |
51 |
Garda Headquarters, Phoenix Park: Laying of concrete kerbs |
|
|
894·86 |
— |
894·86 |
Completed. |
47 |
Garda Headquarters, Phoenix Park: Alterations to roof |
.. |
|
|
112·30 |
— |
112·30 |
do. |
48 |
Garda Headquarters, Phoenix Park: Provision and erection |
|
|
|
|
|
|
|
of flagpole |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
417·15 |
— |
417·15 |
do. |
92 |
Garda Headquarters, Phoenix Park:Erection of new ceiling |
|
|
18·45 |
— |
18·45 |
In progress. |
84 |
Garda Headquarters, Dublin Castle: Provision of glazed |
|
|
|
|
|
|
|
doors in prefab |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
250·70 |
— |
250·70 |
do. |
102 |
Garda Headquarters, Dublin Castle: Provision of canteen |
|
|
|
|
|
|
|
facilities in prefab |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
372·60 |
— |
372·60 |
do. |
70/83 of 75 |
Garda Depot: St. John’s Road: Provision of traffic barrier, |
|
|
|
|
|
|
|
etc. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
662·91 |
349·43 |
1,012·34 |
Completed. |
49/50 of 74 |
Garda Depot: St. John’s Rd.: Crime Branch, Partitioning, |
|
|
|
|
|
|
|
etc. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
712·35 |
524·05 |
1,236·40 |
do. |
Sub No. |
|
|
|
|
|
|
|
70/88 of 75 |
Garda Depot: St. John’s Rd.: Partitioning, etc. |
.. |
.. |
|
|
428·30 |
900·00 |
1,328·30 |
Virtually completed. |
49/42 of 74 |
Garda Depot: St. John’s Rd.: Alterations to Guardroom |
|
|
39·53 |
3,338·00 |
3,377·53 |
Completed. |
46/29 of 73/74 |
Garda Depot: St. John’s Rd.: Storage Accommodation |
.. |
|
|
1,774·64 |
3,170·70 |
4,945·34 |
do. |
70/94 of 75 |
Garda Technical Bureau, St. John’s Rd.: Installation of |
|
|
|
|
|
|
|
photographic equipment |
.. |
.. |
.. |
.. |
.. |
|
|
525·28 |
1,364·58 |
1,889·86 |
Completed. |
49/41 of 74 |
Santry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
134·31 |
9,434·52 |
9,568·83 |
do. |
70/78 of 75 |
Stepaside: Garda Huts at British Ambassador’s Residence: |
|
|
|
|
|
|
|
Adaptations |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,552·87 |
1,838·14 |
3,391·01 |
do. |
81 |
Sundrive Road |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,967·91 |
— |
1,967·91 |
Virtually completed. |
49/29 of 74 |
Terenure |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
78·00 |
2,955·65 |
3,033·65 |
Completed. |
70/69 of 75 |
Whitehall |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
344·35 |
1,068·08 |
1,412·43 |
do. |
|
Co. Dublin: |
|
|
|
|
|
|
70 |
Balbriggan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
561·30 |
— |
561·30 |
do. |
8 |
Blackrock |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,177·50 |
— |
1,177·50 |
do. |
46/58 of 73/74 |
Lusk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,532·33 |
6,930·00 |
9,462·33 |
do. |
30 |
Malahide |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,166·99 |
— |
1,166·99 |
Completed. |
|
Co. Cavan: |
|
|
|
|
|
|
70/27 of 75 |
Ballyconnell |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
513·52 |
900·00 |
1,413·52 |
In progress. |
|
Co. Clare: |
|
|
|
|
|
|
70/12 of 75 |
Carrigaholt |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,289·00 |
2,700·00 |
3,989·00 |
do. |
7 |
Ennis |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,355·00 |
— |
5,355·00 |
do. |
39 |
Miltown Malbay |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
540·00 |
— |
540·00 |
do. |
|
Co. Cork: |
|
|
|
|
|
|
64 |
Adrigole |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,440·00 |
— |
1,440·00 |
In progress. |
13 |
Barrack St: Laying tarmac |
.. |
.. |
.. |
.. |
|
|
4,598·09 |
— |
4,598·09 |
Completed. |
Sub No. |
|
|
|
|
|
|
|
9 |
Barrack St.: Provision of extra bedrooms |
.. |
.. |
|
|
355·89 |
— |
355·89 |
Completed. |
35 |
Durrus |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
925·28 |
— |
925·28 |
do. |
55 |
Macroom |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,200·00 |
— |
1,200·00 |
Virtually completed. |
70/54 of 75 |
Mallow Road |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
64·65 |
565·00 |
629·65 |
Completed. |
46/78 of 73/74 |
MacCurtain St.: Installation of Heating |
.. |
.. |
.. |
|
|
929·75 |
4,004·18 |
4,933·93 |
Completed. |
49/13 of 74 |
Timoleague |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
234·50 |
600·00 |
834·50 |
do. |
1 |
Union Quay |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,154·90 |
— |
1,154·90 |
In progress. |
|
Co. Donegal: |
|
|
|
|
|
|
58 |
Bundoran |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,350·00 |
— |
1,350·00 |
do. |
38 |
Falcarragh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
365·00 |
— |
365·00 |
Completed. |
77 |
Killybegs |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
900·00 |
— |
900·00 |
In progress. |
70/35 of 75 |
Letterkenny: Improvements to cells, etc. |
.. |
.. |
.. |
|
|
2,398·00 |
1,350·00 |
3,748·00 |
do. |
49/45 of 74 |
Provision of huts at Donegal/Cavan border |
.. |
.. |
|
|
263·72 |
6,945·63 |
7,209·35 |
Virtually completed. |
|
Co. Galway: |
|
|
|
|
|
|
49/39 of 74 |
Ahascragh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
123·16 |
900·00 |
1,023·16 |
Completed. |
70/29 of 75 |
Eglinton St. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
209·51 |
1,700·00 |
1,909·51 |
do. |
59 |
Loughrea |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,260·00 |
— |
1,260·00 |
In progress. |
62 |
Spiddal |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,438·70 |
— |
2,438·70 |
Completed. |
|
Co. Kerry: |
|
|
|
|
|
|
70/81 of 75 |
Lauragh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,221·00 |
1,829·00 |
3,050·00 |
Virtually completed. |
29 |
Portmagee |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,960·00 |
— |
3,960·00 |
do. |
63 |
Sneem |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
400·00 |
— |
400·00 |
Completed. |
Sub No. |
|
|
|
|
|
|
|
|
Co. Kildare: |
|
|
|
|
|
|
42 |
Celbridge |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
620·80 |
— |
620·80 |
Completed. |
70/65 of 75 |
Droichead Nua |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
840·00 |
4,770·00 |
5,610·00 |
Virtually completed. |
|
Co. Kilkenny: |
|
|
|
|
|
|
49/9 of 74 |
Mooncoin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
300·00 |
8,000·00 |
8,300·00 |
do. |
|
Co. Laois: |
|
|
|
|
|
|
33 |
Rathdowney |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
394·00 |
— |
394·00 |
Completed. |
|
Co. Leitrim: |
|
|
|
|
|
|
70/15 of 75 |
Keshcarrigan |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
449·41 |
1,260·00 |
1,709·41 |
do. |
34 |
Kiltyclogher |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
564·13 |
— |
564·13 |
do. |
65 |
Kinlough |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
450·00 |
— |
450·00 |
In progress. |
|
Co. Limerick: |
|
|
|
|
|
|
99 |
Ballingarry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
734·63 |
— |
734·63 |
Completed. |
43/33 of 72/73 |
Ballyneety |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
118·15 |
3,030·00 |
3,148·15 |
do. |
70/16 of 75 |
Bruff |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,890·00 |
3,240·00 |
5,130·00 |
In progress. |
46/16 of 73/74 |
Kilmeedy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
827·00 |
2,925·00 |
3,752·00 |
do. |
70/37 of 75 |
Mary St. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
138·22 |
691·97 |
830·19 |
Completed. |
|
Co. Longford: |
|
|
|
|
|
|
70/40 of 75 |
Longford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
146·04 |
1,525·00 |
1,671·04 |
do. |
16 |
Smear |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
349·52 |
— |
349·52 |
do. |
|
Co. Louth: |
|
|
|
|
|
|
4 |
Clogherhead |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
450·00 |
— |
450·00 |
do. |
Sub No. |
|
|
|
|
|
|
|
49/15 of 74 |
Drogheda |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
395·00 |
2,070·00 |
2,465·00 |
Completed. |
70/93 of 75 |
Dundalk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
358·00 |
3,223·58 |
3,581·58 |
do. |
|
Co. Mayo: |
|
|
|
|
|
|
54 |
Achill Sound |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,650·00 |
— |
2,650·00 |
In progress. |
36 |
Ballina |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,330·14 |
— |
1,330·14 |
Completed. |
49/12 of 74 |
Ballindine |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
642·37 |
2,418·54 |
3,060·91 |
do. |
52 |
Kilmaine |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,289·92 |
— |
1,289·92 |
do. |
|
Co. Meath: |
|
|
|
|
|
|
17 |
Trim |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,600·00 |
— |
3,600·00 |
Virtually completed. |
|
Co. Monaghan: |
|
|
|
|
|
|
26 |
Castleblayney |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
896·00 |
— |
896·00 |
Completed. |
|
Co. Offaly: |
|
|
|
|
|
|
18 |
Banagher |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
650·00 |
— |
650·00 |
do. |
70/9 of 75 |
Kinnitty |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
732·97 |
2,250·00 |
2,982·97 |
do. |
|
Co. Sligo: |
|
|
|
|
|
|
46/57 of 73/74 |
Sligo |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,900·00 |
11,400·00 |
13,300·00 |
do. |
|
Co. Tipperary: |
|
|
|
|
|
|
49/3 of 74 |
Ballinure |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
119·18 |
5,430·00 |
5,549·18 |
do. |
3 |
Cappawhite |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
990·00 |
— |
990·00 |
Virtually completed. |
12 |
Tipperary |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,732·76 |
— |
2,732·76 |
do. |
|
Co. Waterford: |
|
|
|
|
|
|
43 |
Tramore |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
558·26 |
— |
558·26 |
Completed. |
Sub No. |
Co. Westmeath: |
|
|
|
|
|
|
43/12 of 72/73 |
Athlone |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
362·26 |
1,901·33 |
2,263·59 |
Completed. |
20 |
Mullingar: Improvements to cells |
.. |
.. |
.. |
|
|
2,093·48 |
— |
2,093·48 |
do. |
49 |
Mullingar: Installation of Central Heating and |
|
|
|
|
|
|
|
improvements to lighting |
.. |
.. |
.. |
.. |
.. |
|
|
3,300·00 |
— |
3,300·00 |
In progress. |
|
Co. Wexford: |
|
|
|
|
|
|
68 |
Courtown Harbour |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
522·21 |
— |
522·21 |
Completed. |
5 |
Gorey |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,026·25 |
— |
1,026·25 |
do. |
77 |
Provision of alternative accommodation for Garda Personnel |
|
|
|
|
|
|
|
at Dublin Castle |
.. |
.. |
.. |
.. |
.. |
.. |
80,000·00 |
10,000·00 |
14,881·94 |
69,939·94 |
84,821·88 |
Completed. |
78 |
Dublin: New Temporary Courts |
.. |
.. |
.. |
.. |
250,000·00 |
50,000·00 |
— |
2,668·75 |
2,668·75 |
Under consideration. |
79 |
Dublin: New Permanent Courts |
.. |
.. |
.. |
.. |
|
10,000·00 |
— |
— |
— |
do. |
|
|
|
|
1,052,653·02 |
|
|
|
|
Education: |
|
|
|
|
|
|
80 |
Athlone: New Offices |
.. |
.. |
.. |
.. |
.. |
.. |
850,000·00 |
350,000·00 |
320,642·28 |
359,311·22 |
679,953·50 |
In progress. |
81 |
National Museum: Improvement of Lighting |
.. |
.. |
65,000·00 |
65,000·00 |
— |
— |
— |
In planning. |
82 |
National Museum: Stonework |
.. |
.. |
.. |
.. |
|
5,000·00 |
— |
— |
— |
Deferred. |
83 |
National Museum: Fitting out of additional premises |
.. |
|
20,000·00 |
— |
— |
— |
Under consideration. |
84 |
National Library: Adaptation of premises at Kildare Street |
|
25,000·00 |
1,576·32 |
— |
1,576·32 |
In planning. |
85 |
National Library: Adaptation of premises at Leinster Lane |
30,000·00 |
20,000·00 |
— |
— |
— |
Under consideration. |
86 |
National Library: Improvement of Lighting |
.. |
.. |
|
15,000·00 |
— |
— |
— |
do. |
87 |
Dublin Preventive Centre, Finglas |
.. |
.. |
.. |
.. |
460,000·00 |
12,000·00 |
721·61 |
448,545·77 |
449,267·38 |
Completed. |
|
|
|
|
322,940·21 |
|
|
|
|
Lands: |
|
|
|
|
|
|
88 |
Castlebar: New Offices |
.. |
.. |
.. |
.. |
.. |
1,115,000·00 |
250,000·00 |
351,145·03 |
860,173·64 |
1,211,318·67 |
Virtually completed. |
89 |
Bray Forestry Offices: Adaptations |
.. |
.. |
.. |
.. |
24,000·00 |
6,000·00 |
5,398·62 |
25,128·14 |
30,526·76 |
Completed. |
|
|
|
|
356,543·65 |
|
|
|
|
Gaeltacht: |
|
|
|
|
|
|
90 |
Galway: New Offices |
.. |
.. |
.. |
.. |
.. |
.. |
225,000·00 |
100,000·00 |
— |
— |
— |
In planning. |
|
|
|
|
— |
|
|
|
|
Agriculture and Fisheries: |
|
|
|
|
|
|
91 |
Botanic Gardens: Developments (Herbarium, etc.) |
.. |
|
5,000·00 |
2,893·55 |
— |
2,893·55 |
do. |
92 |
Botanic Gardens: Staff Canteen |
.. |
.. |
.. |
.. |
15,000·00 |
15,000·00 |
— |
— |
— |
do. |
93 |
Regional Veterinary and Dairy Produce Laboratories |
.. |
324,000·00 |
11,000·00 |
6,962·93 |
307,962·81 |
314,925·74 |
Completed. |
94 |
Abbotstown Farm: New Milking Parlour |
.. |
.. |
.. |
32,000·00 |
12,000·00 |
8,422·83 |
19,004·52 |
27,427·35 |
do. |
95 |
Abbotstown Farm: Farm Manager’s Residence |
.. |
.. |
20,000·00 |
20,000·00 |
— |
— |
— |
In planning. |
96 |
Abbotstown Farm: Incinerator |
.. |
.. |
.. |
.. |
30,000·00 |
30,000·00 |
— |
— |
— |
Contract placed. |
97 |
Abbotstown Farm: Loose Box Accommodation |
.. |
.. |
50,000·00 |
10,000·00 |
— |
— |
— |
In planning. |
98 |
Abbotstown Farm: Accommodation for Scientific and |
|
|
|
|
|
|
|
Research Staff (Fisheries) |
.. |
.. |
.. |
.. |
.. |
270,000·00 |
160,000·00 |
34,307·86 |
— |
34,307·86 |
In progress. |
98A |
Abbotstown Farm: Improvements |
.. |
.. |
.. |
.. |
12,000·00 |
— |
5,167·51 |
— |
5,167·51 |
do. |
99 |
Tully West, Co. Kildare: Performance Testing Station for |
|
|
|
|
|
|
|
Beef Bulls |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
83,000·00 |
6,000·00 |
210·27 |
76,656·36 |
76,866·63 |
Completed. |
100 |
Tully West, Co. Kildare: Office Accommodation |
.. |
.. |
23,000·00 |
20,000·00 |
— |
— |
— |
In planning. |
101 |
Thorndale: New Butter and Seed Testing Stations |
.. |
|
10,000·00 |
— |
— |
— |
do. |
102 |
Thorndale: Pig Progeny Testing Station |
.. |
.. |
.. |
21,000·00 |
1,000·00 |
1,229·12 |
19,601·20 |
20,830·32 |
Completed. |
103 |
Thorndale: Alterations to Old Laboratory |
.. |
.. |
.. |
90,000·00 |
50,000·00 |
2,140·39 |
221·18 |
2,361·57 |
In planning. |
104 |
Kildalton College: Adaptations |
.. |
.. |
.. |
.. |
|
10,000·00 |
— |
21·70 |
21·70 |
do. |
105 |
Kildalton College: New Water Supply |
.. |
.. |
.. |
40,000·00 |
20,000·00 |
20·88 |
805·48 |
826·36 |
In planning. |
106 |
Kildalton College: Residences for Superintendent and two |
|
|
|
|
|
|
|
Inspectors |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
60,000·00 |
20,000·00 |
2,007·61 |
— |
2,007·61 |
do. |
107 |
Raphoe District Veterinary Office |
.. |
.. |
.. |
.. |
100,000·00 |
70,000·00 |
5,001·23 |
25·00 |
5,026·23 |
In planning. |
108 |
Veterinary College, Ballsbridge: Animal Unit Laboratory |
.. |
18,000·00 |
10,000·00 |
— |
— |
— |
do. |
108A |
Veterinary College, Ballsbridge: Anatomy Department Cold |
|
|
|
|
|
|
|
Room |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
16,000·00 |
|
2,700·00 |
— |
2,700·00 |
In progress. |
109 |
Cattle Quarantine Station |
.. |
.. |
.. |
.. |
.. |
|
10,000·00 |
— |
5,820·69 |
5,820·69 |
Under consideration. |
110 |
Ballyhaise Agricultural College: Sewage Disposal |
.. |
.. |
75,000·00 |
15,000·00 |
— |
2,743·46 |
2,743·46 |
In progress—cost being borne on Dept. of Agriculture Vote. |
111 |
Ballyhaise Agricultural College: Field Water Supply |
.. |
10,000·00 |
5,000·00 |
1,221·34 |
— |
1,221·34 |
Under consideration. |
112 |
Ballyhaise Agricultural College: New Accommodation |
.. |
|
5,000·00 |
79·20 |
— |
79·20 |
In planning. |
113 |
Clonakilty Agricultural College: Residence for |
|
|
|
|
|
|
|
Superintendent |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
22,000·00 |
5,000·00 |
— |
— |
— |
do. |
114 |
Mellowes Agricultural College, Athenry: New Cottages and |
|
|
|
|
|
|
|
Gate Lodge |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
73,000·00 |
45,000·00 |
— |
— |
— |
do. |
115 |
New Office Block, Kildare Place: Fitting out, furnishing, etc. |
1,700,000·00 |
110,000·00 |
110,274·41 |
1,583,731·94 |
1,694,006·35 |
Virtually completed. |
116 |
Fisheries Field Research Station, Dunmore East: Extension |
16,000·00 |
5,000·00 |
— |
157·79 |
157·79 |
In planning. |
|
|
|
|
182,639·13 |
|
|
|
|
Transport and Power: |
|
|
|
|
|
|
117 |
Training School and Synoptic Reporting Station, Murrough, |
|
|
|
|
|
|
|
Co. Galway |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
130,000·00 |
30,000·00 |
7,538·36 |
— |
7,538·36 |
do. |
118 |
Claremorris: New Meteorological Station |
.. |
.. |
.. |
18,000·00 |
15,000·00 |
— |
— |
— |
Tenders invited. |
119 |
Johnstown Castle: New Meteorological Station |
.. |
.. |
|
40,000·00 |
— |
— |
— |
In planning. |
|
|
|
|
7,538·36 |
|
|
|
|
Posts and Telegraphs: |
|
|
|
|
|
|
120 |
Baldoyle: New Sorting Office |
.. |
.. |
.. |
.. |
73,000·00 |
5,000·00 |
4,875·64 |
78,033·74 |
82,909·38 |
Completed. |
121 |
Central Sorting Office: Ventilation |
.. |
.. |
.. |
.. |
268,000·00 |
5,000·00 |
19,386·12 |
236,791·88 |
256,178·00 |
Virtually completed. |
122 |
Clondalkin Polefield: Resurfacing |
.. |
.. |
.. |
.. |
20,000·00 |
5,000·00 |
— |
— |
— |
Under consideration. |
123 |
Dundrum: Engineering Training Centre |
.. |
.. |
.. |
131,000·00 |
1,000·00 |
701·32 |
7,541·82 |
8,243·14 |
Deferred. |
124 |
Fairview: New Sorting Office |
.. |
.. |
.. |
.. |
|
1,000·00 |
— |
99·86 |
99·86 |
In planning. |
125 |
Finglas: Extension to Sorting Office |
.. |
.. |
.. |
25,000·00 |
10,000·00 |
— |
— |
— |
In planning. |
126 |
G.P.O.: Philatelic Sales Office |
.. |
.. |
.. |
.. |
8,000·00 |
1,000·00 |
901·37 |
7,220·00 |
8,121·37 |
Completed. |
127 |
Lyon House, Dublin: Partitioning, etc. |
.. |
.. |
.. |
53,000·00 |
14,000·00 |
11,569·03 |
38,829·23 |
50,398·26 |
do. |
128 |
Phibsboro Post Office: Extension |
.. |
.. |
.. |
.. |
86,000·00 |
5,000·00 |
1,804·06 |
86,393·98 |
88,198·04 |
Virtually completed. |
129 |
St. John’s Rd., Depot: Alterations to Sprinkler System |
.. |
11,500·00 |
1,000·00 |
2,098·97 |
10,320·25 |
12,419·22 |
Completed. |
129A |
16/17 Princes St. (Holroyd & Jones premises): Adaptations |
16,700·00 |
— |
9,235·30 |
— |
9,235·30 |
In progress. |
130 |
Ballinlough Sorting Office, Cork: Adaptations |
.. |
.. |
28,000·00 |
20,000·00 |
— |
111·00 |
111·00 |
Tenders received. |
131 |
Ballyhaunis Post Office: Modernisation |
.. |
.. |
.. |
23,000·00 |
20,000·00 |
5,792·95 |
504·53 |
6,297·48 |
In progress. |
132 |
Ballymote Post Office: Improvements to Post Master’s |
|
|
|
|
|
|
|
Accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
5,000·00 |
5,000·00 |
— |
— |
— |
Under consideration. |
133 |
Bray Post Office: Extension |
.. |
.. |
.. |
.. |
.. |
5,000·00 |
5,000·00 |
— |
— |
— |
Under consideration. |
133A |
Castlerea Post Office: Improvements |
.. |
.. |
.. |
12,000·00 |
— |
4,500·00 |
— |
4,500·00 |
In progress. |
134 |
Clonakilty Post Office: Alterations and provision of garage |
6,000·00 |
5,000·00 |
— |
— |
— |
In planning. |
135 |
Clonmel New Post Office |
.. |
.. |
.. |
.. |
.. |
202,000·00 |
59,000·00 |
6,376·83 |
9,289·48 |
15,666·31 |
In progress. |
136 |
Cobh Post Office: Modernisation |
.. |
.. |
.. |
.. |
35,000·00 |
33,000·00 |
31,610·33 |
— |
31,610·33 |
Virtually completed. |
137 |
Cork (Brian Boru St.) Sorting Office: Extension |
.. |
.. |
|
10,000·00 |
— |
— |
— |
In planning. |
138 |
Donegal New Post Office |
.. |
.. |
.. |
.. |
.. |
250,000·00 |
112,000·00 |
124,097·46 |
104,293·44 |
228,390·90 |
In progress. |
139 |
Dungarvan New Post Office |
.. |
.. |
.. |
.. |
.. |
63,000·00 |
10,000·00 |
9,723·60 |
54,631·54 |
64,355·14 |
Completed. |
140 |
Enniscorthy Post Office: Improvements |
.. |
.. |
.. |
45,000·00 |
43,000·00 |
1,703·79 |
941·35 |
2,645·14 |
In planning. |
141 |
Letterkenny Post Office: Extension |
.. |
.. |
.. |
.. |
50,000·00 |
5,000·00 |
11,315·98 |
41,975·17 |
53,291·15 |
Virtually completed. |
142 |
Limerick Post Office: Improvements |
.. |
.. |
.. |
|
6,000·00 |
— |
1,180·33 |
1,180·33 |
In planning. |
143 |
Listowel New Post Office |
.. |
.. |
.. |
.. |
.. |
73,000·00 |
25,000·00 |
17,243·41 |
53,961·86 |
71,205·27 |
Virtually completed. |
144 |
Longford New Post Office |
.. |
.. |
.. |
.. |
.. |
90,000·00 |
40,000·00 |
|
— |
— |
In planning. |
145 |
Mullingar New Post Office |
.. |
.. |
.. |
.. |
.. |
150,000·00 |
60,000·00 |
5,224·30 |
1,046·69 |
6,270·99 |
do. |
146 |
Roscommon Post Office: Modernisation |
.. |
.. |
.. |
10,000·00 |
7,000·00 |
— |
— |
— |
In planning. |
147 |
Shannon New Post Office |
.. |
.. |
.. |
.. |
.. |
270,000·00 |
5,000·00 |
4,040·54 |
11,246·37 |
15,286·91 |
do. |
148 |
Thurles Post Office: Modernisation |
.. |
.. |
.. |
.. |
|
2,000·00 |
— |
— |
— |
Under consideration. |
149 |
Tipperary New Post Office |
.. |
.. |
.. |
.. |
.. |
170,000·00 |
40,000·00 |
1,705·00 |
3,909·34 |
5,614·34 |
In planning. |
149A |
Togher, Cork, New Sorting Office: Fitting out |
.. |
10,000·00 |
— |
8,877·00 |
— |
8,877·00 |
Virtually completed. |
150 |
Waterford Post Office: Improvements |
.. |
.. |
.. |
60,000·00 |
5,000·00 |
— |
— |
— |
In planning. |
|
|
|
|
282,783·00 |
|
|
|
|
Defence: |
|
|
|
|
|
|
151 |
G.H.Q.: Provision of Printing Building |
.. |
.. |
.. |
10,000·00 |
10,000·00 |
— |
— |
— |
Contract placed. |
152 |
G.H.Q.: Improvement works |
.. |
.. |
.. |
.. |
20,000·00 |
16,000·00 |
6,476·80 |
— |
6,476·80 |
In progress. |
|
|
|
|
6,476·80 |
|
|
|
|
Foreign Affairs: |
|
|
|
|
|
|
153 |
Ottawa Embassy Residence: Extension and Improvement |
|
23,000·00 |
1,250·98 |
133·44 |
1,384·42 |
Awaiting Dept., Finance sanction. |
154 |
Ottawa Embassy Chancery: Extension |
.. |
.. |
.. |
|
20,000·00 |
33,609·29 |
— |
33,609·29 |
In progress. |
155 |
U.N. Mission, New York: Fitting out of new offices |
.. |
50,000·00 |
10,000·00 |
6,850·20 |
39,316·15 |
46,166·35 |
Completed. |
156 |
Embassy at Luxembourg: Fitting out for occupation |
.. |
50,000·00 |
3,000·00 |
6,849·56 |
47,013·62 |
53,863·18 |
do. |
157 |
Embassy at Moscow (including Staff Residence): Fitting out |
|
|
|
|
|
|
|
for occupation |
.. |
.. |
.. |
.. |
.. |
.. |
125,000·00 |
12,000·00 |
22,107·56 |
113,540·69 |
135,648·25 |
Virtually completed. |
158 |
Embassy at Lagos: Erection of new residence |
.. |
.. |
|
5,000·00 |
— |
— |
— |
In planning. |
159 |
Embassy at Paris: Improvements |
.. |
.. |
.. |
.. |
65,000·00 |
50,000·00 |
56,997·58 |
15,002·74 |
72,000·32 |
Virtually completed. |
160 |
Embassy at Beirut: Fitting out for occupation |
.. |
.. |
|
21,000·00 |
3,991·75 |
16,150·43 |
20,142·18 |
In progress. |
161 |
Embassy at Vienna: Fitting out for occupation |
.. |
.. |
65,000·00 |
60,000·00 |
27,581·25 |
2,471·04 |
30,052·29 |
do. |
162 |
Embassy at Madrid: Fitting out of new offices |
.. |
.. |
15,500·00 |
12,000·00 |
11,471·34 |
3,302·30 |
14,773·64 |
Completed. |
163 |
Embassy at Lisbon: Fitting out of new offices |
.. |
.. |
|
20,000·00 |
741·04 |
— |
741·04 |
In planning. |
164 |
Embassy at Canberra: Erection of new residence |
.. |
.. |
|
15,000·00 |
3,406·90 |
— |
3,406·90 |
do. |
165 |
Consulate General at Boston: Fitting out of new offices |
.. |
15,700·00 |
12,000·00 |
11,946·31 |
3,694·62 |
15,640·93 |
Completed. |
166 |
Consulate General at Chicago: Fitting out of new offices |
7,000·00 |
7,000·00 |
3,976·40 |
— |
3,976·40 |
do. |
167 |
Consulate General at New York: Improvements |
.. |
.. |
|
30,000·00 |
1,978·29 |
— |
1,978·29 |
In progress. |
167A |
Mission to E.E.C. at Brussels: Furnishing of residence |
.. |
11,000·00 |
|
811·71 |
— |
811·71 |
do. |
167B |
Embassy at London: Adaptations |
.. |
.. |
.. |
.. |
9,000·00 |
|
32·79 |
— |
32·79 |
do. |
|
|
|
|
193,602·95 |
|
|
|
|
Social Welfare: |
|
|
|
|
|
|
168 |
Manorhamilton Employment Exchange: extension |
.. |
|
1,000·00 |
— |
— |
— |
In planning. |
169 |
Dún Laoghaire Employment Exchange: Fitting out |
.. |
|
14,000·00 |
— |
— |
— |
Under consideration. |
169A |
Arklow Employment Exchange: Conversion works |
.. |
5,200·00 |
|
4,035·12 |
— |
4,035·12 |
Virtually completed. |
|
|
|
|
4,035·12 |
|
|
|
|
General: |
|
|
|
|
|
|
170 |
Sundry Departments: New Buildings |
.. |
.. |
.. |
|
2,500,000·00 |
1,212,461·72 |
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
93-99 Lower Leeson St. |
.. |
.. |
.. |
.. |
.. |
|
|
150,334·17 |
144,488·52 |
294,822·69 |
In progress. |
|
Ship St. (Dublin Castle) |
.. |
.. |
.. |
.. |
.. |
|
|
830·48 |
10,949·91 |
11,780·39 |
In planning. |
|
Infirmary Road: New H.Q. for Department of Defence |
|
|
42,783·16 |
14,000·00 |
56,783·16 |
In planning. |
|
Blocks 8, 9 and 10, Dublin Castle |
.. |
.. |
.. |
|
|
29,533·53 |
6,185·09 |
35,718·62 |
In progress. |
|
14-17 Upper Merrion St |
.. |
.. |
.. |
.. |
.. |
|
|
5,285·70 |
1,759·76 |
7,045·46 |
In planning. |
|
Beggar’s Bush, Haddington Road |
.. |
.. |
.. |
.. |
|
|
118,907·25 |
15,191·06 |
134,098·31 |
do. |
|
Shelbourne Road, Ballsbridge |
.. |
.. |
.. |
.. |
|
|
185,194·66 |
46,622·19 |
231,816·85 |
In progress. |
|
Sligo Temporary Revenue Offices |
.. |
.. |
.. |
.. |
|
|
41,999·65 |
46,593·15 |
88,592·80 |
do. |
|
Waterford Temporary Revenue Offices |
.. |
.. |
.. |
|
|
14,710·08 |
40,379·00 |
55,089·08 |
Virtually completed. |
|
New Garda H.Q., Phoenix Park (Stage I) |
.. |
.. |
|
|
466,860·65 |
20,039·05 |
486,899·70 |
In progress. |
|
Thurles Temporary Revenue Offices |
.. |
.. |
.. |
|
|
28,358·47 |
13,500·00 |
41,858·47 |
Virtually completed. |
|
Kilkenny Temporary Revenue Offices |
.. |
.. |
.. |
|
|
18,721·93 |
18,540·00 |
37,261·93 |
do. |
|
13-14 Earlsfort Terrace |
.. |
.. |
.. |
.. |
.. |
|
|
55,697·84 |
36,964·93 |
92,662·77 |
In progress. |
|
44-45 Merrion Square |
.. |
.. |
.. |
.. |
.. |
|
|
— |
266·87 |
266·87 |
Deferred. |
|
Marlborough House, Glasnevin: New H.Q. for |
|
|
|
|
|
|
|
Meteorological Service |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
53,244·15 |
— |
53,244·15 |
In progress. |
171 |
Minor New Works not exceeding £5,000 each |
.. |
.. |
|
230,000·00 |
|
|
|
Details appended. |
|
|
|
|
158,095·04 |
|
|
|
172 |
Urgent and Unforeseen Works |
.. |
.. |
.. |
.. |
|
12,000·00 |
— |
|
|
|
173 |
Minor balances of Expenditure (not provided for above) on works of prior years which may not be completed on 1st |
|
|
|
|
|
|
|
January, 1976 |
.. |
.. |
.. |
.. |
.. |
.. |
|
65,000·00 |
33,555·72 |
|
|
Details appended. |
|
|
|
|
5,749,531·19 |
|
|
|
|
|
|
|
|
|
|
|
DETAILS OF No. 171—MINOR NEW WORKS
Work No. |
Service and Description |
Total Estimate |
Vote 1976 |
Expenditure |
Observations |
1976 |
To 31/12/75 |
To 31/12/76 |
|
|
£ |
£ |
£ |
£ |
£ |
|
Sub No. |
President: |
|
|
|
|
|
|
56 |
Aras an Uachtaráin: Improvements to grounds |
.. |
.. |
|
|
1,958·22 |
|
1,958·22 |
Completed. |
|
Taoiseach: |
|
|
|
|
|
|
151/136 of 75 |
Bust and Portrait of late President Childers |
.. |
.. |
|
|
1,027·50 |
2,500·00 |
3,527·50 |
Completed. |
121/49 of 74 |
Griffith Barracks (Central Statistics Office): Fire escape |
.. |
|
|
47·06 |
5,195·74 |
5,242·80 |
do. |
174 |
State Apartments: Inauguration of President |
.. |
.. |
|
|
3,344·50 |
— |
3,344·50 |
In progress. |
Sub No. |
Finance: |
|
|
|
|
|
|
151/74 of 75 |
Credit Union Buildings, O’Brien St. Mallow: Partitioning, |
|
|
|
|
|
|
|
decoration, etc. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
648·68 |
912·00 |
1,560·68 |
Completed. |
57 |
Government Buildings: Improvements to toilet facilities |
.. |
|
|
1,343·03 |
— |
1,343·03 |
do. |
151/22 of 75 |
Stationery Office, Beggar’s Bush: Lighting system |
.. |
.. |
|
|
519·09 |
346·14 |
865·23 |
do. |
109 |
State Laboratory, Upper Merrion St.: Provision of bench in |
|
|
|
|
|
|
|
Laboratory |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
766·67 |
— |
766·67 |
In progress. |
151/126 of 75 |
Valuation Office, 5/6 Ely Place: Provision of tea room |
.. |
|
|
928·56 |
948·19 |
1,876·75 |
Virtually completed. |
78 |
Valuation Office, 5/6 Ely Place: Adaptations for P.A.B.X. |
|
|
|
|
|
|
|
equipment |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
798·04 |
— |
798·04 |
In progress. |
151/120 of 75 |
3 South Frederick Street: Partitioning |
.. |
.. |
.. |
|
|
34·89 |
59·85 |
94·74 |
Completed. |
|
Revenue Commissioners: |
|
|
|
|
|
|
138 |
Aras Brugha: Improvements to lift |
.. |
.. |
.. |
.. |
|
|
484·10 |
— |
484·10 |
Completed. |
51 |
Carrickarnon Frontier Post: Extension |
.. |
.. |
.. |
|
|
2,157·42 |
— |
2,157·42 |
do. |
103/26 of 73/74 |
Cobh Custom House: Heating and lighting improvements |
|
|
90·74 |
442·00 |
532·74 |
do. |
116 |
Dundalk Customs Road Station: Erection of Prefab Office |
|
|
3,000·00 |
— |
3,000·00 |
In progress. |
103/160 of 73/74 |
Dún Laoghaire Harbour: New clearing station |
.. |
.. |
|
|
9·80 |
5,234·69 |
5,244·49 |
Completed. |
151/127 of 75 |
Inishannon Frontier Post, Co. Monaghan: Supply and |
|
|
|
|
|
|
|
erection of timber structure |
.. |
.. |
.. |
.. |
|
|
126·18 |
3,500·00 |
3,626·18 |
Virtually completed. |
76 |
Ferryhill Frontier Post: Improvements |
.. |
.. |
.. |
|
|
2,562·33 |
— |
2,562·33 |
Completed. |
147 |
Hume House: Provision of canteen facilities |
.. |
.. |
|
|
4·86 |
— |
4·86 |
In progress. |
73 |
Kilclean Frontier Post: Provision of new building |
.. |
|
|
3,531·22 |
— |
3,531·22 |
Completed. |
39 |
Moybridge Customs Station, Co. Monaghan: Provision of |
|
|
|
|
|
|
|
portals |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
857·00 |
— |
857·00 |
do. |
110 |
Pearse House: Addition to fire alarm system |
.. |
.. |
|
|
280·42 |
— |
280·42 |
do. |
29 |
Sligo Custom House: Provision of flourescent lighting |
.. |
|
|
889·46 |
— |
889·46 |
do. |
Sub No. |
|
|
|
|
|
|
|
83 |
St. Martins House: Partitioning |
.. |
.. |
.. |
.. |
|
|
827·65 |
— |
827·65 |
Completed. |
42 |
Swanlinbar, Co. Cavan: Installation of storage heating |
.. |
|
|
503·65 |
— |
503·65 |
do. |
84 |
Former Ulster Bank Premises, Waterford: Improvements |
|
|
2,609·91 |
— |
2,609·91 |
do. |
151/130 of 75 |
Former Ulster Bank Premises,Waterford: Electrical |
|
|
|
|
|
|
|
installation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
248·00 |
3,131·29 |
3,379·29 |
do. |
93 |
Wexford Tax Office: Alterations |
.. |
.. |
.. |
.. |
|
|
904·98 |
— |
904·98 |
do. |
151/166 of 75 |
19/22 Dame St., Dublin: Renovations |
.. |
.. |
.. |
|
|
2,189·22 |
322·35 |
2,511·57 |
do. |
|
Office of Public Works: |
|
|
|
|
|
|
35 |
Furniture Production Unit, Inchicore: Provision of fans |
.. |
|
|
874·72 |
— |
874·72 |
do. |
50 |
Accounts Branch, 52 St. Stephen’s Green: Electrical |
|
|
|
|
|
|
|
installation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
564·60 |
— |
564·60 |
do. |
139 |
B.V.M. Park, Killarney, Superintendent’s Residence: |
|
|
|
|
|
|
|
Heating installation |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
864·00 |
— |
864·00 |
In progress. |
114 |
Bonham St., Furniture Store: Electrical works |
.. |
.. |
|
|
494·91 |
— |
494·91 |
do. |
121/74 of 74 |
Drainage Maintenance Depot, Limerick: Improvements |
.. |
|
|
313·67 |
6,695·37 |
7,009·04 |
Completed. |
121/53 of 74 |
Dún Laoghaire Harbour: Provision of store at car ferry |
|
|
|
|
|
|
|
terminal |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
38·38 |
253·74 |
292·12 |
Completed. |
151/142 of 75 |
Furniture Division, Rathmines: Provision of Canteen |
|
|
|
|
|
|
|
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,677·98 |
324·36 |
3,002·34 |
Virtually completed. |
151/93 of 75 |
Furniture Division, Rathmines: Electrical installations |
.. |
|
|
17·05 |
487·57 |
504·62 |
Completed. |
121/72 of 74 |
Drainage Maintenance Depot, Lifford: New Office and |
|
|
|
|
|
|
|
Store |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
125·00 |
6,657·20 |
6,782·20 |
do. |
151/157 of 75 |
Drainage Maintenance Depot, Lifford: New Workshop |
.. |
|
|
15·27 |
1,721·45 |
1,736·72 |
do. |
Sub No. |
|
|
|
|
|
|
|
151/125 of 75 |
Harbour Master’s House, Howth: Provision of Central |
|
|
|
|
|
|
|
Heating |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
72·00 |
1,370·00 |
1,442·00 |
Completed. |
98 |
Phoenix Park: Provision of hut at Cabra gate |
.. |
.. |
|
|
1,869·37 |
— |
1,869·37 |
In progress. |
1 |
Phoenix Park: Staff room at Soccer Pavilion |
.. |
.. |
|
|
38·40 |
— |
38·40 |
do. |
137 |
R.D.S. Ballsbridge: Erection of horticultural display stand |
|
|
307·84 |
— |
307·84 |
Completed. |
89 |
St. Stephen’s Green Park: Provision of Pre-fab Office |
.. |
|
|
1,236·31 |
— |
1,236·31 |
Virtually completed. |
130 |
Accounts Branch, 52, St. Stephen’s Green: Improvements |
.. |
|
|
1,392·22 |
— |
1,392·22 |
do. |
121/85 of 74 |
Shannon Navigation: Portumna Toll House: Sanitary |
|
|
|
|
|
|
|
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
133·52 |
2,529·00 |
2,662·52 |
Completed. |
151/160 of 75 |
26/27 Upper Pembroke St.: Fitting out |
.. |
.. |
.. |
|
|
11·20 |
31·50 |
42·70 |
In progress. |
|
Public Service: |
|
|
|
|
|
|
126 |
Computer Building, Inchicore: Provision of temporary |
|
|
|
|
|
|
|
canteen facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,587·47 |
— |
2,587·47 |
Completed. |
|
Justice: |
|
|
|
|
|
|
151/138 of 75 |
Four Courts: Adaptations to Taxing Master’s Office |
.. |
|
|
192·58 |
1,083·15 |
1,275·73 |
Completed. |
151/137 of 75 |
Four Courts: Kitchen and toilet improvements |
.. |
.. |
|
|
83·85 |
364·82 |
448·67 |
do. |
69 |
Four Courts: Provision of Security Hut |
.. |
.. |
.. |
|
|
639·93 |
— |
639·93 |
do. |
149 |
Four Courts: Probate Office: Partitioning |
.. |
.. |
.. |
|
|
351·97 |
— |
351·97 |
In progress. |
59 |
Land Registry: Provision of Dark Room |
.. |
.. |
.. |
|
|
2,856·51 |
— |
2,856·51 |
Completed. |
12 |
Phibsboro Tower: Accommodation for Garda |
|
|
|
|
|
|
|
Representative Body |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
21·53 |
— |
21·53 |
In progress. |
145 |
Public Records Office: Partitioning Room 20 |
.. |
.. |
|
|
147·58 |
— |
147·58 |
do. |
151/12 of 75 |
Registry of Deeds: Adaptations |
.. |
.. |
.. |
.. |
|
|
1,195·49 |
1,401·05 |
2,596·54 |
Virtually completed. |
Sub. No. |
|
|
|
|
|
|
|
53 |
Registry of Deeds: Improvements to windows |
.. |
.. |
|
|
640·27 |
— |
640·27 |
Completed. |
131 |
Registry of Deeds: Provision of storage accommodation and |
|
|
|
|
|
|
|
improvements to kitchen |
.. |
.. |
.. |
.. |
.. |
|
|
1,137·93 |
— |
1,137·93 |
In progress. |
101 |
72/76 St. Stephen’s Green: Partitioning of Room 518 |
.. |
|
|
592·25 |
— |
592·25 |
Completed. |
151 |
128 Lr. Baggot St.: Improvements to rest room and dining |
|
|
|
|
|
|
|
room |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
184·16 |
— |
184·16 |
In progress. |
151/70 of 75 |
Training Centre, Fitzgibbon St.: Erection of toilet block |
.. |
|
|
1·60 |
4,803·83 |
4,805·43 |
Completed. |
47 |
Welfare Office, Galway: Erection of counter and screen |
.. |
|
|
348·00 |
— |
348·00 |
do. |
|
Local Government: |
|
|
|
|
|
|
27 |
Driving Test Centre, Parkgate Hall, Conyngham Road: |
|
|
|
|
|
|
|
Double glazing of windows of Interview Room |
.. |
.. |
|
|
520·71 |
— |
520·71 |
Completed. |
97 |
Driving Test Centre, 85 Ballymun Ave.,: Fitting out |
.. |
|
|
1,849·15 |
— |
1,849·15 |
Virtually completed. |
94 |
O’Connell Bridge House: Partitioning (2nd, 10th and 11th |
|
|
|
|
|
|
|
floors) |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,032·80 |
— |
1,032·80 |
In progress. |
151/128 of 75 |
O’Connell Bridge House: Partitioning (5th floor) |
.. |
.. |
|
|
1·53 |
266·06 |
267·59 |
Completed. |
|
Education: |
|
|
|
|
|
|
74/95 of 71/72 |
Central Model Schools: Storage Accommodation |
.. |
.. |
|
|
502·16 |
895·84 |
1,398·00 |
Completed. |
103/107 of 73/74 |
Limerick Model School: Accommodation for Inspectorate |
|
|
2,779·27 |
3,759·24 |
6,538·51 |
In progress. |
28 |
Limerick Model School (Girls): Installation of Electricaire |
|
|
|
|
|
|
|
and thermal storage units |
.. |
.. |
.. |
.. |
.. |
|
|
1,710·00 |
— |
1,710·00 |
do. |
151/26 of 75 |
Marlboro St.: Adaptations |
.. |
.. |
.. |
.. |
.. |
|
|
177·34 |
265·82 |
443·16 |
Completed. |
135 |
National Gallery: Provision of Darkroom |
.. |
.. |
.. |
|
|
232·06 |
— |
232·06 |
In progress. |
134 |
National Gallery: Installation of frescoes |
.. |
.. |
.. |
|
|
134·24 |
— |
134·24 |
do. |
121/120 of 74 |
National Library: Partitioning and Electrical Works |
.. |
|
|
192·89 |
1,672·94 |
1,865·83 |
Completed. |
Sub. No. |
|
|
|
|
|
|
|
151/35 of 75 |
National Museum: Adaptations |
.. |
.. |
.. |
.. |
|
|
961·79 |
2,653·26 |
3,615·05 |
Completed. |
80/174 of 69/70 |
National Museum: Provision of Humidifiers |
.. |
.. |
|
|
102·00 |
2,093·07 |
2,195·07 |
do. |
84/15 of 72/73 |
No. 29 Marlboro St.: Information Centre |
.. |
.. |
.. |
|
|
2,244·47 |
351·02 |
2,595·49 |
do. |
45 |
Talbot House, Marlboro St.: Provision of ramp |
.. |
.. |
|
|
925·24 |
— |
925·24 |
do. |
31 |
Talbot House, Marlboro St.: Provision of double glazing |
|
|
1,515·18 |
— |
1,515·18 |
do. |
132 |
Training College Building, Marlboro St.: Improvements |
.. |
|
|
433·97 |
— |
433·97 |
In progress. |
151/76 of 75 |
21 Fitzwilliam Square, Higher Education Authority: Fire |
|
|
|
|
|
|
|
precautionary works |
.. |
.. |
.. |
.. |
.. |
|
|
1,583·11 |
3,525·11 |
5,108·22 |
do. |
|
Lands: |
|
|
|
|
|
|
151/89 of 75 |
Kinnity Castle, Birr: Improvements |
|
|
417·13 |
454·10 |
871·23 |
Completed. |
107 |
Mullingar Land Commission Offices: Partitions |
|
|
1,200·00 |
— |
1,200·00 |
Virtually completed. |
133 |
83 Merrion Square: Provision of storage heating |
|
|
2,632·50 |
— |
2,632·50 |
In progress. |
121/95 of 74 |
23 Upper Merrion St.: Provision of training facilities |
.. |
|
|
454·82 |
1,111·08 |
1,565·90 |
Completed. |
153 |
21 Upper Merrion St.: Alterations and Improvements to Luncheon Club |
|
|
946·95 |
— |
946·95 |
In progress. |
|
Agriculture and Fisheries: |
|
|
|
|
|
|
36 |
Abbotstown Farm: Provision of cycle shed and weigh bridge |
|
|
1,598·38 |
— |
1,598·38 |
do. |
60 |
Abbotstown Farm: Provision of cattle grid and sheeting of |
|
|
|
|
|
|
|
shed |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,789·74 |
— |
2,789·74 |
Completed. |
92 |
Abbotstown Farm: Provision of window in office of animal |
|
|
|
|
|
|
|
house |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
719·80 |
— |
719·80 |
Virtually completed. |
140 |
Abbotstown Farm: Supply and erection of diesel storage |
|
|
|
|
|
|
|
tank |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
400·46 |
— |
400·46 |
In progress. |
Sub. No. |
|
|
|
|
|
|
|
111 |
Mellowes Agricultural College: Provision of petrol pump |
|
|
598·80 |
— |
598·80 |
Completed. |
151/13 of 75 |
Ballyhaise Agricultural College: Heating installation |
|
|
57·00 |
1,076·01 |
1,133·01 |
do. |
121/78 of 74 |
Ballyhaise Agricultural College: Erection of retaining walls |
|
|
771·14 |
3,420·00 |
4,191·14 |
do. |
52 |
Ballyhaise Agricultural College: Improvements to ball-alley |
|
|
|
|
|
|
|
floor |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
292·00 |
— |
292·00 |
do. |
143 |
Ballyhaise Agricultural College: Improvements to kitchen |
|
|
692·16 |
— |
692·16 |
In progress. |
86 |
Backweston Farm: Improvements to kitchen and provision |
|
|
|
|
|
|
|
of bathroom |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,862·92 |
— |
2,862·92 |
Completed. |
46 |
Backweston Farm: Provision of oil storage tanks |
|
|
2,309·75 |
— |
2,309·75 |
do. |
58 |
Backweston Farm: Extension to cottage |
.. |
.. |
|
|
1,729·26 |
— |
1,729·26 |
Virtually completed. |
144 |
Ballsbridge Veterinary College: Alterations and |
|
|
|
|
|
|
|
Improvements in Rooms 12 and 13 |
.. |
.. |
.. |
.. |
|
|
666·77 |
— |
666·77 |
In progress. |
88 |
Ballsbridge Veterinary College: Partitioning consulting room |
|
|
2,017·86 |
— |
2,017·86 |
do. |
120 |
Ballsbridge Veterinary College: Partitioning Immunology |
|
|
|
|
|
|
|
Laboratory |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,323·59 |
— |
3,323·59 |
do. |
160 |
Ballsbridge Veterinary College: Provision of cold room for |
|
|
|
|
|
|
|
microbiology unit |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
113·76 |
— |
113·76 |
do. |
121/73 of 74 |
Ballsbridge Veterinary College: New microbiology unit |
|
|
125·00 |
4,404·12 |
4,529·12 |
Completed. |
151/83 of 75 |
Botanic Gardens: Supply of new aluminium ladders for |
|
|
|
|
|
|
|
fern house |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
739·35 |
235·90 |
975·25 |
do. |
121/28 of 74 |
Castletownbere: Provision of Field Laboratory |
.. |
|
|
1,399·50 |
8,089·52 |
9,489·02 |
do. |
43 |
Chantilly Field Station: Provision of New E.S.B. Switch- |
|
|
|
|
|
|
|
board |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
603·43 |
— |
603·43 |
do. |
104 |
Farm Development Service, Birr: Alterations |
.. |
.. |
|
|
1,119·60 |
— |
1,119·60 |
do. |
159 |
Farm Development Service, Carrick-on-Shannon: Provision |
|
|
|
|
|
|
|
of accommodation |
.. |
.. |
.. |
.. |
.. |
|
|
668·22 |
— |
668·22 |
do. |
Sub. No. |
|
|
|
|
|
|
|
75 |
Farm Development Service, Longford: Improvements to |
|
|
|
|
|
|
|
pre-fab, offices |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,943·60 |
— |
1,943·60 |
Completed. |
102 |
Hume House, Ballsbridge: Partitioning |
.. |
.. |
|
|
1,340·03 |
— |
1,340·03 |
do. |
106 |
Hynes Building, Galway: Alterations to partitions |
.. |
|
|
1,186·39 |
— |
1,186·39 |
do. |
62 |
Sligo (Dunally) Regional Veterinary Laboratory: Provision |
|
|
|
|
|
|
|
of offal house |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
794·00 |
— |
794·00 |
do. |
64 |
Thorndale Pig Progeny Testing Station: Provision of |
|
|
|
|
|
|
|
wire guards on windows |
.. |
.. |
.. |
.. |
|
|
556·40 |
— |
556·40 |
do. |
85 |
Tipperary Veterinary Office: Electrical rewiring |
.. |
.. |
|
|
1,033·02 |
— |
1,033·02 |
Virtually completed. |
|
Labour: |
|
|
|
|
|
|
37 |
Manpower Service, Ballina: Improvements |
.. |
.. |
.. |
|
|
1,964·27 |
— |
1,964·27 |
Completed. |
171 |
Manpower Service, Limerick: Fitting out |
.. |
.. |
.. |
|
|
4,915·85 |
— |
4,915·85 |
do. |
74/98 of 71/72 |
Manpower Service, Waterford: Adaptations |
.. |
.. |
|
|
1,645·00 |
4,758·41 |
6,403·41 |
do. |
|
Industry and Commerce: |
|
|
|
|
|
|
121/75 of 74 |
Kildare St.,: Adaptations |
.. |
.. |
.. |
.. |
|
|
183·32 |
5,912·09 |
6,095·41 |
In progress. |
|
Transport and Power: |
|
|
|
|
|
|
67 |
26/27 Eden Quay: Conversion of caretaker’s quarters to |
|
|
|
|
|
|
|
offices |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,754·63 |
— |
3,754·63 |
do. |
|
Posts and Telegraphs: |
|
|
|
|
|
|
96 |
Aldboro House: Improvements to toilets |
.. |
.. |
.. |
|
|
706·84 |
— |
706·84 |
Completed. |
74 |
Athlone Post Office: Alterations |
.. |
.. |
.. |
.. |
|
|
766·60 |
— |
766·60 |
In progress. |
Sub No. |
|
|
|
|
|
|
|
103/115 of 73/74 |
Ballina Post Office, Co. Mayo: New floor in Sorting Office, |
|
|
|
|
|
|
|
etc. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
221·10 |
1,255·00 |
1,476·10 |
Virtually completed. |
118 |
Boyne Centre, Drogheda: Fitting out new offices |
.. |
.. |
|
|
1,066·00 |
— |
1,066·00 |
Completed. |
151/68 of 75 |
Brian Boru St. Sorting Office, Cork: Improvements |
.. |
|
|
544·57 |
3,643·81 |
4,188·38 |
Virtually completed. |
55 |
Bray Post Office: Improvements to toilets |
.. |
.. |
.. |
|
|
955·00 |
— |
955·00 |
Completed. |
121/57 of 74 |
Castlebar Post Office: Alterations |
.. |
.. |
.. |
.. |
|
|
349·00 |
4,900·00 |
5,249·00 |
do. |
103 |
Central Sorting Office: Provision of rain-water pipes and |
|
|
|
|
|
|
|
gutters |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
485·00 |
— |
485·00 |
do. |
121/97 of 74 |
Central Sorting Office: Improvements to tea room |
.. |
.. |
|
|
553·29 |
4,040·86 |
4,594·15 |
do. |
70 |
College House, Townsend St.: Partitioning in Savings Bank |
|
|
481·03 |
— |
481·03 |
do. |
125 |
Clonakilty Post Office: Improvements |
.. |
.. |
.. |
|
|
1,800·00 |
— |
1,800·00 |
In progress. |
108 |
Churchtown Sorting Office: Security Works |
.. |
.. |
.. |
|
|
862·13 |
— |
862·13 |
Completed. |
72 |
Copley St., Post Office Garage, Cork: Erection of partitions |
|
|
|
|
|
|
|
and sliding doors |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
543·00 |
— |
543·00 |
do. |
141 |
Crumlin Sorting Office: Removal of internal walls |
.. |
|
|
746·69 |
— |
746·69 |
In progress. |
121/43 of 74 |
Fenian House: Partitioning and fitting out |
.. |
.. |
.. |
|
|
186·25 |
3,496·62 |
3,682·87 |
Completed. |
90 |
Fenian House: Partitioning |
.. |
.. |
.. |
.. |
.. |
|
|
443·93 |
— |
443·93 |
do. |
151/39 of 75 |
G.P.O.: Partitioning |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
801·70 |
1,353·51 |
2,155·21 |
do. |
119 |
G.P.O.: Adaptations to 2nd floor |
.. |
.. |
.. |
.. |
|
|
2,040·87 |
— |
2,040·87 |
In progress. |
87 |
Glenageary Post Office: Alterations to canopy |
.. |
.. |
|
|
410·97 |
— |
410·97 |
Completed. |
65 |
James’ St. Post Office: Erection of canopy |
.. |
.. |
.. |
|
|
654·10 |
— |
654·10 |
do. |
100 |
Kilrush Post Office: Improvements |
.. |
.. |
.. |
.. |
|
|
447·96 |
— |
447·96 |
do. |
151/122 of 75 |
Navan Post Office: Improvements |
.. |
.. |
.. |
.. |
|
|
780·89 |
1,107·00 |
1,887·89 |
do. |
151/86 of 75 |
Rathmines Post Office: Improvements |
.. |
.. |
.. |
|
|
1,052·37 |
4,437·55 |
5,489·92 |
do. |
121/139 of 74 |
Tallaght Post Office (Priory Hall): Adaptations |
.. |
.. |
|
|
548·50 |
7,366·46 |
7,914·96 |
do. |
44 |
Thurles Post Office: Interim improvements |
.. |
.. |
|
|
3,600·00 |
— |
3,600·00 |
In progress. |
121/65 of 74 |
Tuam Post Office: Sanitary accommodation |
.. |
.. |
|
|
246·00 |
4,684·98 |
4,930·98 |
Completed. |
|
Defence: |
|
|
|
|
|
|
Sub No. |
|
|
|
|
|
|
|
115 |
Coláiste Chaoimhín: Adaptations for introduction of |
|
|
|
|
|
|
|
P.A.Y.E. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
647·00 |
— |
647·00 |
Completed. |
151/99 of 75 |
G.H.Q., Parkgate St.: Provision of fire escape |
.. |
.. |
|
|
532·87 |
703·23 |
1,236·10 |
do. |
151/144 of 75 |
G.H.Q., Parkgate St.: Adaptations to room 10 |
.. |
.. |
|
|
5·10 |
863·33 |
868·43 |
do. |
151/33 of 75 |
G.H.Q., Parkgate St.: Adaptations to Communications |
|
|
|
|
|
|
|
Centre |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,591·57 |
382·26 |
2,973·83 |
In progress. |
71 |
G.H.Q., Parkgate St.: Improvements to sanitary |
|
|
|
|
|
|
|
accommodation in Minister’s suite |
.. |
.. |
.. |
.. |
.. |
|
|
395·32 |
— |
395·32 |
Completed. |
148 |
G.H.Q., Parkgate St.: Improvements to ladies’ toilets |
.. |
|
|
483·08 |
— |
483·08 |
In progress. |
30 |
Infirmary Road: Erection of security fence |
.. |
.. |
.. |
|
|
159·86 |
— |
159·86 |
do. |
|
Foreign Affairs: |
|
|
|
|
|
|
121/30 of 74 |
30 Earlsfort Terrace: Central Heating |
.. |
.. |
.. |
|
|
2,474·75 |
990·00 |
3,464·75 |
Completed. |
|
Social Welfare: |
|
|
|
|
|
|
163 |
Aras Mhic Dhiarmada: Adaptations to 2nd floor |
.. |
.. |
|
|
754·89 |
— |
754·89 |
do. |
95 |
D’Olier House: Improvements to lighting |
.. |
.. |
.. |
|
|
1,221·72 |
— |
1,221·72 |
Virtually completed. |
121/143 of 74 |
Bray Employment Exchange: Adaptations |
.. |
.. |
.. |
|
|
27·19 |
3,353·92 |
3,381·11 |
Completed. |
38 |
Galway Employment Exchange: Fire alarm system |
.. |
|
|
608·44 |
— |
608·44 |
do. |
32 |
Mullingar Employment Exchange: Building of boundary |
|
|
|
|
|
|
|
wall |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
775·43 |
— |
775·43 |
do. |
129 |
Thurles Employment Exchange: Adaptations and |
|
|
|
|
|
|
|
improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,277·06 |
— |
1,277·06 |
Virtually completed. |
146 |
Werburgh St., Employment Exchange: Conversion of |
|
|
|
|
|
|
|
heating system to oil fired |
.. |
.. |
.. |
.. |
.. |
|
|
1,856·30 |
— |
1,856·30 |
Completed. |
117 |
Oisin House: Additions to fire alarm system |
.. |
.. |
|
|
373·38 |
— |
373·38 |
do. |
Sub No. |
|
|
|
|
|
|
|
151/111 of 75 |
Aras Mhic Dhiarmada and Phibsboro Tower: Installation of |
|
|
|
|
|
|
|
electric hand-driers |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
80·04 |
767·50 |
847·54 |
Completed. |
|
Health: |
|
|
|
|
|
|
151/88 of 75 |
Custom House, Dublin: Improvements to ladies’ cloakroom |
|
|
92·55 |
1,122·95 |
1,215·50 |
Virtually Completed. |
61 |
Hawkins House, Dublin: Partitioning of Room 427 |
.. |
|
|
259·65 |
— |
259·65 |
Completed. |
DETAILS OF No. 173—MINOR BALANCES OF EXPENDITURE
Work No. |
Service and Description |
Total Estimate |
Vote 1976 |
Expenditure |
Observations |
1976 |
To 31/12/75 |
To 31/12/76 |
|
|
£ |
£ |
£ |
£ |
£ |
|
|
Oireachtas: |
|
|
|
|
|
|
1(1) of 71/72 |
Leinster House: Extension and alterations |
.. |
.. |
.. |
|
|
296·78 |
771,968·92 |
772,265·70 |
Completed. |
|
Taoiseach: |
|
|
|
|
|
|
3A of 72/73 |
State Apartments: Rebuilding of Drawing Room/Bedroom |
|
|
|
|
|
|
|
Block and Main Entrance |
.. |
.. |
.. |
.. |
.. |
|
|
51·98 |
532,247·35 |
532,299·33 |
do. |
2A of 74 |
State Apartments: Extension of automatic fire detection |
|
|
|
|
|
|
|
system |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,285·99 |
13,601·62 |
14,887·61 |
do. |
|
Finance: |
|
|
|
|
|
|
26 of 68/69 |
Economic and Social Research Institute: New |
|
|
|
|
|
|
|
accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
80·06 |
65·95 |
146·01 |
Project reviewed. |
|
Revenue Commissioners: |
|
|
|
|
|
|
8 of 75 |
11/13 Upper O’Connell St.,: Adaptations |
.. |
.. |
.. |
|
|
261·64 |
64,552·20 |
64,813·84 |
Completed. |
Sub No. |
Office of Public Works: |
|
|
|
|
|
|
14A of 72/73 |
52, St. Stephen’s Green: Provision of lift and bridges |
.. |
|
|
3,410·11 |
21,988·34 |
25,398·45 |
Completed. |
34 of 75 |
Killarney National Park (including B.V.M. Park): Public |
|
|
|
|
|
|
|
toilets |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,670·11 |
8,213·80 |
9,883·91 |
do. |
|
Justice: |
|
|
|
|
|
|
66 of 75 |
Garda Headquarters: Improved Accommodation for |
|
|
|
|
|
|
|
Commissioner’s staff |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
698·08 |
43,013·87 |
43,711·95 |
do. |
|
Education: |
|
|
|
|
|
|
79A of 75 |
Central Model Schools: General Improvements |
.. |
.. |
|
|
2,374·11 |
102,204·27 |
104,578·38 |
do. |
55 of 73/74 |
Dublin Institute for Advanced Studies: Accommodation |
.. |
|
|
210·50 |
193,495·70 |
193,706·20 |
do. |
|
Agriculture and Fisheries: |
|
|
|
|
|
|
60(1) of 73/74 |
Abbotstown Farm: New Laboratory Block |
.. |
.. |
|
|
8,652·58 |
156,412·09 |
165,064·67 |
do. |
107A of 75 |
Provision for storage accommodation for Departmental |
|
|
|
|
|
|
|
records, etc. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,993·63 |
97,332·39 |
100,326·02 |
do. |
|
Transport and Power: |
|
|
|
|
|
|
109A of 75 |
Meteorological Office, 44 Upper O’Connell St.: Air |
|
|
|
|
|
|
|
conditioning, etc. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
368·90 |
7,248·27 |
7,617·17 |
do. |
|
Posts and Telegraphs: |
|
|
|
|
|
|
72 of 73/74 |
Blackrock Post Office, Co. Dublin: Modernisation |
.. |
|
|
3,442·56 |
12,084·27 |
15,526·83 |
do. |
86 of 73/74 |
Castlebar Engineering Headquarters and Garage |
.. |
.. |
|
|
150·00 |
6,485·05 |
6,635·05 |
do. |
99 of 74 |
Cavan New Post Office |
.. |
.. |
.. |
.. |
.. |
|
|
573·63 |
83,266·75 |
83,840·38 |
do. |
86 of 74 |
Dundrum Computer Building |
.. |
.. |
.. |
.. |
.. |
|
|
2,341·54 |
96,781·85 |
99,123·39 |
do. |
Sub No. |
|
|
|
|
|
|
|
117 of 75 |
G.P.O.: Adaptations of accommodation formerly used |
|
|
|
|
|
|
|
by R.T.E. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
377·45 |
10,203·44 |
10,580·89 |
Completed. |
79 of 73/74 |
Glenageary new Sorting Office, Co. Dublin |
.. |
.. |
.. |
|
|
65·45 |
63,084·74 |
63,150·19 |
do. |
95 of 73/74 |
Nenagh New Post Office |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
46·34 |
97,708·80 |
97,755·14 |
do. |
95A of 1974 |
St. John’s Rd. Depot: Warehouses, etc. |
.. |
.. |
.. |
|
|
3,364·29 |
329,139·05 |
332,503·34 |
do. |
|
Foreign Affairs: |
|
|
|
|
|
|
142 of 1975 |
Embassy at Tokyo: Fitting out for occupation |
.. |
.. |
|
|
269·00 |
105,867·42 |
106,136·42 |
do. |
141 of 1975 |
Accommodation for E.E.C. meetings in Dublin in 1975 |
.. |
|
|
570·99 |
267,841·91 |
268,412·90 |
do. |
|