APPENDIX 10
Qn. 526.
STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1 APRIL-31 DECEMBER, 1974 (VOTE 9: SUBHEAD E)
Work No. |
Service and Description |
Total Estimate |
Vote 1 April to 31 December 1974 |
Expenditure |
Observations |
1 April to 31 December 1974 |
to 31/3/74 |
to 31/12/74 |
|
|
£ |
£ |
£ |
£ |
£ |
|
1 (1) |
President |
|
|
|
|
|
|
|
Arus an Uachtararáin: Improvements |
11,000 |
10,000 |
8,660.35 |
2,070.88 |
10,731.23 |
Completed |
|
|
|
|
8,660.35 |
|
|
|
|
Oireachtas |
|
|
|
|
|
|
1 (2) |
Leinster House: Installation of Standby Generators |
36,000 |
1,000 |
— |
— |
— |
In Planning |
1 (3) |
Leinster House: Additional Accommodation |
|
30,000 |
— |
— |
— |
Under consideration. |
1 (4) |
Leinster House: Erection of Barriers at Entrance |
20,000 |
|
19,076.44 |
— |
19,076.44 |
In Progress. |
|
|
|
|
19,076.44 |
|
|
|
|
Taoiseach |
|
|
|
|
|
|
2 |
State Apartments: Adaptation of former Stamping Branch |
|
|
|
|
|
|
|
Premises |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
7,000 |
— |
— |
— |
Under consideration. |
2 (A) |
State Apartments: Extension of Automatic Fire Detection |
|
|
|
|
|
|
|
System |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,000.00 |
8,601.62 |
13,601.62 |
Completed. |
|
|
|
|
5,000.00 |
|
|
|
|
Department of Finance |
|
|
|
|
|
|
3 (1) |
Provision of Building for Computer—Stage 1 |
.. |
.. |
325,000 |
20,000 |
35,836.18 |
288,088.63 |
323,924.81 |
Completed. |
3 (2) |
Provision of Building for Computer—Stage 2 |
.. |
.. |
250,000 |
1,000 |
— |
— |
— |
In planning. |
4 |
Fitting out of New Office premises for occupation |
.. |
|
302,000 |
327,692.61 |
— |
— |
|
|
|
|
|
Detailed as follows: |
|
|
|
|
Pearse House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,267.22 |
44,613.68 |
49,880.90 |
In progress. |
|
O’Connell Bridge House, Extension |
.. |
.. |
.. |
|
|
713.36 |
22,230.91 |
22,944.27 |
In Progress |
|
52, St. Stephens Green |
.. |
.. |
.. |
.. |
.. |
|
|
10,236.47 |
75,571.03 |
85,807.50 |
do. |
|
Hume House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
693.98 |
10,769.25 |
11,463.23 |
do. |
|
D’Olier House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
14,920.35 |
35,722.89 |
50,643.24 |
do. |
|
Earlsfort House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
108,005.87 |
130,440.23 |
238,446.10 |
Virtually completed. |
|
Number 1, Grand Canal St. |
.. |
.. |
.. |
.. |
|
|
31,972.99 |
21,818.54 |
53,791.53 |
In progress |
|
Hawkins House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,949.27 |
9,005.33 |
16,954.60 |
Completed. |
|
Ossian House, Pearse St. |
.. |
.. |
.. |
.. |
|
|
85,820.86 |
— |
85,820.86 |
In progress. |
|
Osmond House, Little Ship Street |
.. |
.. |
.. |
|
|
19,531.95 |
— |
19,531.95 |
do. |
|
St. Munchins’ House, Limerick |
.. |
.. |
.. |
.. |
|
|
26,299.51 |
— |
26,299.51 |
do. |
|
Hynes Building, Galway |
.. |
.. |
.. |
.. |
.. |
|
|
505.66 |
18,587.18 |
19,092.84 |
Completed. |
|
Apollo House, Tara Street. |
.. |
.. |
.. |
.. |
|
|
84.86 |
21,998.90 |
22,083.76 |
do. |
|
Phibsboro House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
30.09 |
32,819.27 |
32,849.36 |
do. |
|
3, South Frederick Street. |
.. |
.. |
.. |
.. |
|
|
76.68 |
6,587.32 |
6,664.00 |
do. |
|
39, Dawson Street. |
.. |
.. |
.. |
.. |
.. |
|
|
360.72 |
14,774.12 |
15,134.84 |
do. |
|
Arkle House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,391.34 |
17,658.25 |
24,049.59 |
do. |
|
Bishop Street. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,268.48 |
— |
1,268.48 |
In progress. |
|
Sidmonton Place, Bray |
.. |
.. |
.. |
.. |
.. |
|
|
7,200.00 |
— |
7,200.00 |
do. |
|
Leeson Lane, Dublin |
.. |
.. |
.. |
.. |
.. |
|
|
362.95 |
— |
362.95 |
In planning. |
5 |
Revenue Commissioners: New Offices Dublin Castle |
1,400,000 |
180,000 |
192,254.72 |
1,120,314.07 |
1,312,568.79 |
In Progress |
6 |
Revenue Commissioners: Provision of Additional |
|
|
|
|
|
|
|
Computer Accommodation |
.. |
.. |
.. |
.. |
250,000 |
20,000 |
17,126.40 |
232,100.19 |
249,226.59 |
Completed |
7 |
Revenue Commissioners: Aras Brugha, Adaptations |
93,000 |
10,000 |
12,513.80 |
79,748.90 |
92,262.70 |
do. |
8 |
Revenue Commissioners: 11/13 Upper O’Connell St. |
|
|
|
|
|
|
|
Dublin: Adaptations |
.. |
.. |
.. |
.. |
.. |
42,000 |
8,000 |
2,268.31 |
61,996.14 |
64,264.45 |
do. |
9 |
Monaghan: New Customs Road Station |
.. |
.. |
.. |
60,000 |
10,000 |
661.37 |
1,260.91 |
1,922.28 |
In planning. |
10 |
Carrigans: New Frontier Customs Post |
.. |
.. |
.. |
14,000 |
1,000 |
— |
— |
— |
Deferred. |
11 |
Blacklion: Frontier Customs Post Stage II |
.. |
.. |
|
1,000 |
— |
— |
— |
Under consideration. |
12 |
Dundalk Customs Road Station: Enlargement |
.. |
.. |
|
1,000 |
— |
— |
— |
Site to be acquired. |
13 |
Government Buildings: New Lifts |
.. |
.. |
.. |
30,000 |
1,000 |
— |
— |
— |
In planning. |
14 |
New Office Buildings, Dublin: Erection |
.. |
.. |
.. |
2,500,000 |
138,000 |
8,991.34 |
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
Haddington Road |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
— |
8,691.06 |
8,691.06 |
do. |
|
Shelbourne Road |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,304.43 |
2,414.69 |
4,719.12 |
do. |
|
Ship Street (Dublin Castle) |
.. |
.. |
.. |
.. |
|
|
4,533.75 |
— |
4,533.75 |
do. |
|
Glasnevin (Marlboro House Site) |
.. |
.. |
.. |
.. |
|
|
— |
4,293.30 |
4,293.30 |
do. |
|
13/14 Earlsfort Terrace |
.. |
.. |
.. |
.. |
.. |
|
|
2,153.16 |
4,811.77 |
6,964.93 |
do. |
15 |
15, Merrion Square: Adaptations |
.. |
.. |
.. |
.. |
16,000 |
5,000 |
1,217.45 |
3,090.23 |
4,307.68 |
In progress. |
16 |
Dublin Central Buildings Maintenance Workshops: |
|
|
|
|
|
|
|
Adaptations |
.. |
.. |
.. |
.. |
.. |
.. |
30,000 |
1,000 |
— |
— |
— |
Deferred. |
17 |
Ordnance Survey: New Printing Building |
.. |
.. |
225,000 |
60,000 |
67,984.16 |
3,784.26 |
71,768.42 |
In progress. |
18 (1) |
Ordnance Survey: Improvement of Residential Quarters |
17,000 |
5,000 |
— |
— |
— |
In planning. |
18 (2) |
Ordnance Survey: Provision of Canteen Facilities |
.. |
5,500 |
5,000 |
— |
— |
— |
do. |
19 |
Dundalk: New Government Offices |
.. |
.. |
.. |
|
5,000 |
2,552.27 |
10,819.90 |
13,372.17 |
Deferred. |
20 |
Drogheda: New Government Offices |
.. |
.. |
.. |
116,000 |
7,000 |
3,454.67 |
100,715.79 |
104,170.46 |
Completed. |
21 |
Letterkenny: New Government Offices |
.. |
.. |
.. |
130,000 |
60,000 |
117,118.57 |
57,511.96 |
174,630.53 |
do. |
22 |
Mullingar: New Government Offices |
.. |
.. |
.. |
135,000 |
25,000 |
— |
— |
— |
In planning. |
23 |
Roscommon: New Government Offices |
.. |
.. |
.. |
|
6,000 |
— |
— |
— |
Contract placed. |
24 |
Tralee: New Government Offices |
.. |
.. |
.. |
.. |
25,000 |
2,000 |
48.96 |
26,250.07 |
26,299.03 |
Completed |
25 |
Waterford: New Government Offices |
.. |
.. |
.. |
186,000 |
5,000 |
85.70 |
528.28 |
613.98 |
In planning. |
26 |
New Premises for the Institute of Public Administration |
|
|
|
|
|
|
|
and the Dept. of the Public Service Training Centre |
.. |
1,200,000 |
15,000 |
— |
50,949.15 |
50,949.15 |
In planning. |
27 |
State Memorial to the Late President Kennedy |
.. |
.. |
3,810,000 |
2,000 |
— |
137,167.84 |
137,167.84 |
Under Consideration |
28 |
Scoil Eanna, Rathfarnham, Restoration of Buildings, |
|
|
|
|
|
|
|
Stage II |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
16,000 |
525.00 |
— |
525.00 |
In planning. |
29 |
Royal Hospital, Kilmainham Restoration, Stage II |
.. |
|
10,000 |
765.95 |
509.67 |
1,275.62 |
do. |
30 |
Government Buildings South Block: Adaptations |
.. |
|
10,000 |
— |
— |
— |
do. |
31 |
Government Buildings South Block: Installation of |
|
|
|
|
|
|
|
Standby Generators |
.. |
.. |
.. |
.. |
.. |
.. |
|
1,000 |
— |
— |
— |
do. |
32 |
Clare Island: Harbour Improvements |
.. |
.. |
.. |
90,000 |
39,000 |
— |
22,256.00 |
22,256.00 |
In progress. |
33 (1) |
Dún Laoghaire Harbour: Removal of Temporary Car |
|
|
|
|
|
|
|
Ferry Terminal |
.. |
.. |
.. |
.. |
.. |
.. |
10,000 |
1,000 |
2,928.79 |
2,541.84 |
5,470.63 |
do. |
33 (2) |
Dún Laoghaire Harbour: Multi-purpose Ship Facilities |
250,000 |
100,000 |
155,558.00 |
2,392.18 |
157,950.18 |
do. |
34 (1) |
Bourn Vincent National Park: Improvement to Workshops |
|
3,000 |
3,353.00 |
1,081.98 |
4,434.98 |
do. |
34 (2) |
Bourn Vincent National Park: Public Toilets |
.. |
.. |
15,000 |
5,000 |
— |
5,480.63 |
5,480.63 |
do. |
34 (3) |
Bourn Vincent National Park: Mucross House Sanitary |
|
|
|
|
|
|
|
Services |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
50,000 |
2,000 |
— |
729.01 |
729.01 |
In planning. |
34 (4) |
Bourn Vincent National Park: Roads Development |
.. |
|
4,000 |
3,510.92 |
556.72 |
4,067.64 |
In Progress |
35 |
Kilkenny Castle: Restoration of Picture Gallery Wing |
100,000 |
18,000 |
57,622.28 |
15,060.00 |
72,682.28 |
do. |
36 |
Phoenix Park Extension (Islandbridge Park) General |
|
|
|
|
|
|
|
Development Stage I |
.. |
.. |
.. |
.. |
.. |
80,000 |
10,000 |
2,621.02 |
39,502.38 |
42,123.40 |
do. |
36A |
Ballinamore and Ballyconnell Canal Survey |
.. |
.. |
|
|
1,810.44 |
5,879.65 |
7,690.09 |
do. |
37 (1) |
Shannon Navigation: General Improvements |
.. |
.. |
100,000 |
20,000 |
14,771.93 |
75,768.66 |
90,540.59 |
do. |
37 (2) |
Shannon Navigation: New jetty at Hodson Bay |
.. |
40,000 |
7,000 |
— |
373.94 |
373.94 |
In planning. |
37 (3) |
Shannon Navigation: Extension of Pier at Mountshannon |
13,000 |
5,000 |
11,580.04 |
6,171.31 |
17,751.35 |
In progress. |
37 (4) |
Shannon Navigation: General Study |
.. |
.. |
.. |
17,000 |
6,000 |
6,000.00 |
6,028.33 |
12,028.33 |
do. |
37 (5) |
Shannon Navigation: Extension of Quay at Rossmore |
.. |
11,000 |
5,000 |
53,25 |
— |
53.25 |
In planning. |
38 |
National Monuments: Dunmore Caves/Visitor Centre, |
|
|
|
|
|
|
|
Co. Kilkenny |
.. |
.. |
.. |
.. |
.. |
.. |
18,000 |
8,000 |
17,683.60 |
583.30 |
18,266.90 |
In progress. |
39 |
National Monuments: Clonmacnoise Visitor Centre |
.. |
72,000 |
2,000 |
— |
— |
— |
In planning. |
40 |
National Monuments: Cashel, Visitor Centre |
.. |
.. |
25,000 |
10,000 |
2,424.05 |
— |
2,424.05 |
In progress. |
41 |
National Monuments: New Depot at Killarney |
.. |
.. |
|
2,000 |
— |
— |
— |
Deferred. |
42 |
National Monuments: New Depot at Kilkenny |
.. |
.. |
15,000 |
3,000 |
— |
— |
— |
In planning. |
43 |
National Monuments: New Depot at Parkes Castle, Co. |
|
|
|
|
|
|
|
Sligo |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
20,000 |
6,000 |
— |
— |
— |
do. |
44 |
National Monuments: New Depot at Athenry |
.. |
.. |
40,000 |
4,000 |
— |
— |
— |
do. |
|
|
|
|
1,071,014.78 |
|
|
|
|
Department of Justice |
|
|
|
|
|
|
45 |
Garda Headquarters: Technical Bureau: Improvements |
55,000 |
10,000 |
4,276.82 |
24,953.83 |
29,230.65 |
Virtually completed. |
46 |
Garda Headquarters: Improved accommodation for |
|
|
|
|
|
|
|
Commissioners Staff |
.. |
.. |
.. |
.. |
.. |
40,000 |
30,000 |
31,988.56 |
4,500.00 |
36,488.56 |
In progress. |
47 |
Garda Training Centre, Templemore: Adaptations, etc. |
.. |
647,000 |
1,000 |
1,258.00 |
645,571.14 |
646,829.14 |
Completed. |
48 |
Erection of New Garda Stations: |
.. |
.. |
.. |
.. |
|
200,000 |
206,276.48 |
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
Dublin Metropolition Division: |
|
|
|
|
|
|
|
Ballymum |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,801.62 |
29,683.14 |
31,484.76 |
Completed. |
|
Coolock |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,547.17 |
54,025.54 |
55,572.71 |
do. |
|
Store Street |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
47,771.00 |
53,582.70 |
101,353.70 |
In progress. |
|
Mountjoy |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,975.95 |
— |
7,975.95 |
do. |
|
Co. Dublin |
|
|
|
|
|
|
|
Blanchardstown |
.. |
.. |
.. |
.. |
.. |
|
|
4,980.00 |
6,030.00 |
11,010.00 |
Completed. |
|
Howth |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
555.00 |
10,545.00 |
11,100.00 |
do. |
|
Co. Cavan |
|
|
|
|
|
|
|
Belturbet |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,403.87 |
8,747.87 |
11,151.74 |
do. |
|
Co. Cork |
|
|
|
|
|
|
|
Kanturk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
46.37 |
— |
46.37 |
In planning. |
|
Skibbereen |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,950.00 |
2,886.45 |
7,836.45 |
In progress. |
|
Co. Donegal: |
|
|
|
|
|
|
|
Bunbeg |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,375.00 |
4,680.00 |
9,055.00 |
Completed. |
|
Culdaff |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,980.00 |
— |
1,980.00 |
In progress. |
|
Dungloe |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
741.34 |
4,578.00 |
5,319.34 |
Completed. |
|
Raphoe |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
823.01 |
8,925.13 |
9,748.14 |
In progress. |
|
Co. Galway: |
|
|
|
|
|
|
|
Menlough |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
380.00 |
— |
380.00 |
In planning. |
|
Rosmuc |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
11,940.00 |
1,170.00 |
13,110.00 |
Completed. |
|
Co. Kildare: |
|
|
|
|
|
|
|
Clane |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
624.60 |
11,165.52 |
11,790.12 |
Completed. |
|
Naas |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
10,587.00 |
— |
10,587.00 |
In progress. |
|
Co. Kilkenny: |
|
|
|
|
|
|
|
Graiguenamanagh |
.. |
.. |
.. |
.. |
.. |
|
|
650.00 |
12,375.59 |
13,025.59 |
do. |
|
Co. Limerick: |
|
|
|
|
|
|
|
Limerick City: (Divisional Headquarters) |
.. |
.. |
|
|
15,223.51 |
5,240.68 |
20,464.19 |
Tenders invited. |
|
Askeaton |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
550.00 |
11,455.13 |
12,005.13 |
Completed. |
|
Co. Mayo: |
|
|
|
|
|
|
|
Newport |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,564.72 |
13,578.97 |
19,143.69 |
do. |
|
Co. Meath: |
|
|
|
|
|
|
|
Dunboyne |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
199.00 |
9,921.20 |
10,120.20 |
do. |
|
Co. Monaghan: |
|
|
|
|
|
|
|
Emyvale |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,700.00 |
— |
2,700.00 |
In progress. |
|
Co. Offaly: |
|
|
|
|
|
|
|
Shannonbridge |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
9,000.00 |
— |
9,000.00 |
Virtually completed. |
|
Co. Roscommon: |
|
|
|
|
|
|
|
Knockcroghery |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
10,530.00 |
1,440.00 |
11,970.00 |
do. |
|
Co. Waterford: |
|
|
|
|
|
|
|
Waterford City (Divisional Headquarters) |
.. |
.. |
|
|
6,029.18 |
140,671.70 |
146,700.88 |
Completed. |
|
Portlaw |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
26.19 |
10,476.58 |
10,502.77 |
do. |
|
Co. Westmeath: |
|
|
|
|
|
|
|
Ballynacargy |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
12,330.00 |
1,440.00 |
13,770.00 |
Virtually completed. |
|
Ballinahown |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
7,650.00 |
5,400.00 |
13,050.00 |
do. |
|
Kinnegad |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
623.66 |
10,490.26 |
11,113.92 |
Completed. |
|
Multyfarnham |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,645.00 |
12,600.00 |
14,245.00 |
Virtually completed. |
|
Delvin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
680.00 |
11,650.12 |
12,330.12 |
Completed. |
|
Moate |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
657.00 |
12,961.62 |
13,618.62 |
Virtually completed. |
|
Co. Wexford: |
|
|
|
|
|
|
|
Rosslare Strand |
.. |
.. |
.. |
.. |
.. |
|
|
8,100.00 |
— |
8,100.00 |
Completed. |
|
Clonroche |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,750.00 |
— |
6,750.00 |
In progress. |
|
Bunclody |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
550.00 |
11,665.13 |
12,215.13 |
Completed. |
|
Co. Wicklow: |
|
|
|
|
|
|
|
Enniskerry |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
12,721.29 |
3,226.00 |
15,947.29 |
Completed. |
|
Carnew |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
615.00 |
12,770.26 |
13,385.26 |
do. |
49 |
Improvement Schemes at existing Garda Stations |
.. |
|
70,000 |
77,964.97 |
|
|
|
Sub No. |
Dublin Metropolitan Division: |
|
|
Detailed as follows: |
|
|
|
55 |
Cabra |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
438.57 |
— |
438.57 |
do. |
43/57 of 72/73 |
Dublin Castle: Accommodation for Garda Task Force |
|
|
32.01 |
1,822.36 |
1,854.37 |
do. |
43/38 of 72/73 |
Dublin Castle: Detective Unit and Fire Precaution |
|
|
|
|
|
|
|
Works |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
41.84 |
2,210.75 |
2,252.59 |
do. |
31 |
Fitzgibbon St.—Adaptations to 1st and 2nd floors |
.. |
|
|
3,118.00 |
— |
3,118.00 |
In progress. |
46/54 of 73/74 |
Fitzgibbon St.—Improvements to Heating and Lighting |
|
|
910.81 |
408.81 |
1,319.62 |
Completed. |
48 |
Fitzgibbon St.—Improvements to cell accommodation |
|
|
382.57 |
— |
382.57 |
In Progress. |
43/26 of 72/73 |
Fitzgibbon St.—Improvements |
.. |
.. |
.. |
.. |
|
|
344.24 |
7,389.75 |
7,733.99 |
Completed. |
43/55 of 72/73 |
Garda Depot—Canteen, Stores, Adaptations |
.. |
.. |
|
|
19.08 |
1,864.33 |
1,883.41 |
do. |
46/29 of 73/74 |
Garda Depot—Storage Accommodation |
.. |
.. |
|
|
285.20 |
2,885.50 |
3,170.70 |
In progress. |
42 |
Garda Depot—Alteration to Guardroom |
.. |
.. |
|
|
1,479.59 |
— |
1,479.59 |
do. |
50 |
Garda Depot—Crime Branch, Partitioning etc |
.. |
|
|
344.41 |
— |
344.41 |
do. |
35 |
Garda Depot—Crime Branch, Extension of heating etc |
|
|
928.35 |
— |
928.35 |
do. |
62 |
Irishtown |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
195.90 |
— |
195.90 |
do. |
46/50 of 73/74 |
Kilmainham—Adaptations |
.. |
.. |
.. |
.. |
|
|
47.83 |
3,966.92 |
4,014.75 |
do. |
41 |
Santry |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,185.06 |
— |
4,185.06 |
do. |
29 |
Terenure |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,012.00 |
— |
2,012.00 |
do. |
|
Dublin Metropolitian Division (Contd.) |
|
|
|
|
|
|
|
Co. Dublin: |
|
|
|
|
|
|
43/7 of 72/73 |
Balbriggan |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,418.85 |
26.50 |
2,445.35 |
Completed. |
46/58 of 73/74 |
Lusk |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,130.00 |
1,800.00 |
6,930.00 |
do. |
44 |
Skerries |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
315.00 |
— |
315.00 |
do. |
27 |
Cabinteely |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
6,982.00 |
— |
6,982.00 |
In progress. |
|
Co. Clare: |
|
|
|
|
|
|
46/73 of 73/74 |
Mountshannon |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
700.00 |
600.77 |
1,300.77 |
do. |
|
Co. Cork: |
|
|
|
|
|
|
46/35 of 73/74 |
Cork Courthouse—Provision of Warrant Office |
.. |
|
|
432.84 |
639.38 |
1,072.22 |
do. |
26 |
Ballygurteen |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,820.40 |
— |
1,820.40 |
do. |
43/46 of 72/73 |
Bridewell |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
386.51 |
1,115.68 |
1,502.19 |
Completed. |
46/24 of 73/74 |
McCurtain St.—Alterations |
.. |
.. |
.. |
.. |
|
|
611.72 |
1,482.08 |
2,093.80 |
do. |
46/78 of 73/74 |
McCurtain St.—Installation of Heating |
.. |
.. |
|
|
3,410.18 |
594.00 |
4,004.18 |
do. |
46/17 of 73/74 |
St. Lukes |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
22.12 |
579.91 |
602.03 |
In progress. |
49 |
|
|
|
|
|
|
|
Sub. No. |
Co. Cork (Contd.) |
|
|
|
|
|
|
19 |
Union Quay |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
269.18 |
— |
269.18 |
In progress. |
13 |
Timoleague |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
600.00 |
— |
600.00 |
Completed. |
|
Co. Donegal: |
|
|
|
|
|
|
45 |
Provision of Huts at Donegal/Cavan Border |
.. |
.. |
|
|
5,672.17 |
— |
5,672.17 |
In progress. |
33 |
Killybegs |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
355.48 |
— |
355.48 |
Completed. |
|
Co. Galway: |
|
|
|
|
|
|
39 |
Ahascragh |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
900.00 |
— |
900.00 |
Completed. |
36 |
Kilconly |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
159.05 |
— |
159.05 |
In progress. |
46/9 of 73/74 |
Recess |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,051.07 |
1,485.00 |
2,536.07 |
Completed. |
38 |
Tuam |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
657.73 |
— |
657.73 |
do. |
|
Co. Kerry: |
|
|
|
|
|
|
43/54 of 72/73 |
Beaufort |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
389.27 |
1,800.00 |
2,189.27 |
do. |
32/39 of 71/72 |
Farranfore |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
799.00 |
3,998.90 |
4,797.90 |
do. |
|
Co. Kildare: |
|
|
|
|
|
|
58 |
Maynooth |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,530.00 |
— |
1,530.00 |
do. |
|
Co. Kilkenny: |
|
|
|
|
|
|
9 |
Mooncoin |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
4,950.00 |
— |
4,950.00 |
In progress. |
31/15 of 68/69 |
Stoneyford |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,226.96 |
1,380.00 |
2,606.96 |
Completed. |
|
Co. Laois: |
|
|
|
|
|
|
21 |
Portlaoise |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,053.90 |
— |
1,053.90 |
do. |
39 Sub. No. |
|
|
|
|
|
|
|
|
Co. Limerick: |
|
|
|
|
|
|
32/20 of 71/72 |
Kilfinane |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
42.06 |
1,456.89 |
1,498.95 |
Completed. |
46/16 of 73/74 |
Kilmeedy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
900.00 |
900.00 |
1,800.00 |
In progress. |
24 |
Mary St. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
248.14 |
— |
248.14 |
Completed. |
46/74 of 73/74 |
William St. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
630.00 |
300.00 |
930.00 |
In progress. |
|
Co. Longford: |
|
|
|
|
|
|
46/21 of 73/74 |
Garda Houses, Longford |
.. |
.. |
.. |
.. |
|
|
164.82 |
1,050.00 |
1,214.82 |
Completed. |
46/34 of 73/74 |
Longford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3.25 |
4,115.00 |
4,118.25 |
In progress. |
|
Co. Louth: |
|
|
|
|
|
|
15 |
Drogheda |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,350.00 |
— |
1,350.00 |
do. |
|
Co. Mayo: |
|
|
|
|
|
|
43/18 of 72/73 |
Ballycroy |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
398.52 |
630.00 |
1,028.52 |
Virtually completed. |
16 |
Balmullet |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
260.00 |
— |
260.00 |
Completed. |
12 |
Ballindine |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,350.00 |
— |
1,350.00 |
In progress. |
14 |
Foxford |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
491.00 |
— |
491.00 |
Completed. |
28 |
Westport |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
585.00 |
— |
585.00 |
In progress. |
|
Co. Meath: |
|
|
|
|
|
|
46/86 of 73/74 |
Dunboyne |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
238.88 |
741.00 |
979.88 |
Completed. |
49 |
|
|
|
|
|
|
|
Sub. No. |
Co. Offaly: |
|
|
|
|
|
|
30 |
Geashill |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,380.00 |
— |
3,380.00 |
In progress. |
|
Co. Roscommon: |
|
|
|
|
|
|
25 |
Loughglynn |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
273.00 |
— |
273.00 |
Completed. |
|
Co. Sligo: |
|
|
|
|
|
|
46/57 of 73/74 |
Sligo |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
975.00 |
9,000.00 |
9,975.00 |
In progress. |
|
Co. Tipperary: |
|
|
|
|
|
|
3 |
Ballinure |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,600.00 |
— |
3,600.00 |
do. |
32/25 of 71/72 |
Clogheen |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
900.00 |
1,530.00 |
2,430.00 |
Completed. |
46/6 of 73/74 |
Clonmel |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
712.00 |
720.00 |
1,432.00 |
In progress. |
46/65 of 73/74 |
Dundrum |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,850.00 |
90.00 |
2,940.00 |
do. |
|
Co. Westmeath: |
|
|
|
|
|
|
18 |
Mullingar |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,413.53 |
— |
1,413.53 |
Completed. |
|
Co. Wexford: |
|
|
|
|
|
|
27/52 of 69/70 |
Ferns |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
590.88 |
3,562.50 |
4,153.38 |
do. |
50 |
Provision of Alternative Accommodation for Garda |
|
|
|
|
|
|
|
Personnel at Dublin Castle |
.. |
.. |
.. |
.. |
70,000 |
3,000 |
5,350.00 |
64,203.95 |
69,553.95 |
In progress. |
50A |
Provision of Accommodation for Female Clerical |
|
|
|
|
|
|
|
Assistants in Garda Stations |
.. |
.. |
.. |
.. |
|
|
1,764.23 |
6,716.73 |
8,480.96 |
do. |
51 |
Dublin: Temporary Accommodation for Courts |
.. |
250,000 |
50,000 |
1,067.50 |
— |
1,067.50 |
Under consideration. |
52 |
Dublin: New Permanent Courts |
.. |
.. |
.. |
|
3,000 |
— |
— |
— |
do. |
53 |
Houses for Married Members of the Garda Siochána |
.. |
|
1,000 |
4,894.00 |
1,142,547.00 |
1,147,441.00 |
|
|
|
|
|
334,840.56 |
|
|
|
|
Department of Education |
|
|
|
|
|
|
54 |
Athlone: New Offices |
.. |
.. |
.. |
.. |
.. |
550,000 |
191,000 |
82,760.41 |
48,879.18 |
131,639.59 |
In progress. |
55 |
Marlboro St., Dublin: Improvement to Heating |
.. |
18,000 |
4,000 |
— |
— |
— |
Under consideration. |
55A |
Central Model Schools: General Improvements |
.. |
100,000 |
|
40,607.67 |
752.29 |
41,359.96 |
In progress. |
56 |
National Museum: Improvement to Lighting |
.. |
.. |
|
1,000 |
— |
— |
— |
Under consideration. |
57 |
National Museum: Stonework |
.. |
.. |
.. |
.. |
|
1,000 |
— |
— |
— |
do. |
58 |
Dublin Preventive Centre Finglas |
.. |
.. |
.. |
450,000 |
10,000 |
9,398.81 |
430,100.42 |
439,509.23 |
In progress. |
59 |
National Schools: Grants for building, enlarging, |
|
|
|
|
|
|
|
enclosing etc. |
.. |
.. |
.. |
.. |
.. |
.. |
|
5,030,000 |
7,590,579.41 |
|
|
|
|
|
|
|
7,723,346.30 |
|
|
|
|
Department of Lands |
|
|
|
|
|
|
60 |
Castlebar: New Offices |
.. |
.. |
.. |
.. |
.. |
700,000 |
264,000 |
274,649.56 |
183,764.89 |
458,414.45 |
In progress. |
|
|
|
|
274,649.56 |
|
|
|
61 |
Botanic Gardens: Office and Toilet Accommodation |
.. |
7,000 |
6,000 |
9,000.00 |
— |
9,000.00 |
In progress. |
62 |
Regional Veterinary and Dairy Produce Laboratories |
.. |
280,000 |
30,000 |
44,554.42 |
220,817.10 |
265,371.52 |
do. |
63 |
Abbotstown Farm: New Milking Parlour |
.. |
.. |
14,100 |
8,000 |
840.00 |
1.52 |
841.52 |
do. |
64 |
Abbotstown Farm: Farm Managers Residence |
.. |
.. |
9,000 |
5,000 |
— |
— |
— |
In planning. |
65 |
Abbotstown Farm: Incinerator |
.. |
.. |
.. |
.. |
26,000 |
20,000 |
— |
— |
— |
do. |
66 |
Abbotstown Farm: Accommodation for Scientific and |
|
|
|
|
|
|
|
Research Staff (Fisheries) |
.. |
.. |
.. |
.. |
125,000 |
5,000 |
— |
— |
— |
do. |
67 |
Backweston Farm: New Farm Buildings |
.. |
.. |
69,000 |
2,000 |
1,000.00 |
66,915.65 |
67,915.65 |
In progress. |
68 |
Tully West, Co. Kildare: Performance Testing Station for |
|
|
|
|
|
|
|
Beef Bulls |
.. |
.. |
.. |
.. |
.. |
.. |
64,000 |
6,000 |
21,217.65 |
55,268.53 |
76,486.18 |
do. |
69 |
Thorndale: Butter Testing Station |
.. |
.. |
.. |
|
3,000 |
— |
— |
— |
In planning. |
70 |
Thorndale: Pig Progeny Testing Station |
.. |
.. |
14,000 |
10,000 |
8,150.00 |
5,863.20 |
14,013.20 |
In progress. |
71 |
Thorndale: Alterations to old Laboratory |
.. |
.. |
40,000 |
15,000 |
— |
— |
— |
In planning. |
72 |
Kildalton College: Adaptations |
.. |
.. |
.. |
.. |
|
7,000 |
21.70 |
— |
21.70 |
do. |
73 |
Kildalton College: New Water Supply |
.. |
.. |
.. |
31,000 |
8,000 |
— |
780.95 |
780.95 |
do. |
74 |
Kildalton College: House for Superintendent |
.. |
.. |
|
3,000 |
— |
— |
— |
do. |
75 |
Carlow District: Veterinary Office |
.. |
.. |
.. |
65,000 |
15,000 |
19,853.13 |
44,165.25 |
64,018.38 |
In progress. |
76 |
Provision of Storage Accommodation for Departmental |
|
|
|
|
|
|
|
Records, etc. |
.. |
.. |
.. |
.. |
.. |
.. |
80,000 |
16,000 |
19,600.16 |
60,890.76 |
80,490.92 |
do. |
77 |
Spike Island: Quarantine Station Extension |
.. |
.. |
|
30,000 |
5,820.69 |
— |
5,820.69 |
Under consideration |
78 |
Ballyhaise Agricultural School: Sewage Disposal |
.. |
68,000 |
5,000 |
2,743.46 |
— |
2,743.46 |
In planning |
79 |
Raphoe District Veterinary Office: Erection |
.. |
.. |
|
3,000 |
— |
— |
— |
do. |
80 |
New Office Block, Kildare Place: Fitting out, Furnishing |
|
|
|
|
|
|
|
etc... |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
1,000,000 |
100,000 |
469,950.31 |
850,381.72 |
1,320,332.03 |
In progress. |
|
|
|
|
602,751.52 |
|
|
|
81 |
Mullingar: New Meteorological Station |
.. |
.. |
14,000 |
1,000 |
1,222.90 |
13,026.68 |
14,249.58 |
Virtually completed. |
|
|
|
|
1,222.90 |
|
|
|
|
Department of Posts and Telegraphs |
|
|
|
|
|
|
82 |
Aldboro House: Adaptations |
.. |
.. |
.. |
.. |
|
1,000 |
— |
1,465.19 |
1,465.19 |
Under consideration. |
83 |
Baldoyle: New Sorting Office |
.. |
.. |
.. |
.. |
66,000 |
25,000 |
37,705.54 |
2,109.05 |
39,814.59 |
In progress. |
84 |
Central Sorting Office: Ventilation |
.. |
.. |
.. |
180,000 |
70,000 |
81,863.85 |
4,784.53 |
86,648.38 |
do. |
85 |
Clondalkin Polefield: Resurfacing |
.. |
.. |
.. |
20,000 |
5,000 |
— |
— |
— |
Under consideration. |
86 |
Dundrum: Computer Building |
.. |
.. |
.. |
.. |
90,000 |
10,000 |
10,040.29 |
82,128.03 |
92,168.32 |
In progress. |
87 |
Dundrum: Engineering Training Centre |
.. |
.. |
.. |
40,000 |
3,000 |
825.62 |
5,184.00 |
6,099.62 |
In planning. |
88 |
Fairview: New Sorting Office |
.. |
.. |
.. |
.. |
|
2,000 |
— |
— |
— |
do. |
89 |
Finglas: Extension to Sorting Office |
.. |
.. |
.. |
13,000 |
1,000 |
— |
— |
— |
do. |
90 |
G.P.O.: New Lifts |
.. |
.. |
.. |
.. |
.. |
.. |
|
4,000 |
— |
— |
— |
do. |
91 |
G.P.O.: Philatelic Sales Office |
.. |
.. |
.. |
.. |
8,000 |
5,000 |
— |
— |
— |
do. |
92 |
G.P.O.: Adaptation of Accommodation formerly used by |
|
|
|
|
|
|
|
R.T.E. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
3,000 |
685.19 |
— |
685.19 |
In progress. |
93 |
Phibsboro Post Office: Extension |
.. |
.. |
.. |
.. |
65,000 |
20,000 |
14,995.09 |
43,973.87 |
58,968.96 |
do. |
94 |
St. John’s Rd. Depot: New Paint Store |
.. |
.. |
.. |
8,000 |
1,000 |
10,095.08 |
— |
10,095.08 |
Completed. |
95 |
St. John’s Rd. Depot: Alterations to Sprinkler System |
12,000 |
12,000 |
— |
— |
— |
In planning. |
95A |
St. John’s Rd. Depot: Warehouses etc. |
.. |
.. |
.. |
|
|
10,592.63 |
317,249.28 |
327,841.91 |
In progress. |
96 |
Stillorgan: New Sorting Office |
.. |
.. |
.. |
.. |
80,000 |
2,000 |
— |
1,301.80 |
1,301.80 |
Under consideration. |
96A |
Townsend St.: New Offices: Fitting Out |
.. |
.. |
.. |
|
|
18,521.36 |
95,373.85 |
113,895.21 |
Virtually completed. |
97 |
Ballinlough Sorting Office, Cork: Adaptations |
.. |
.. |
7,000 |
5,000 |
— |
— |
— |
In Planning |
98 |
Ballyhaunis Post Office: Modernisation |
.. |
.. |
.. |
20,000 |
4,000 |
— |
109.19 |
109.19 |
In planning. |
99 |
Cavan New Post Office |
.. |
.. |
.. |
.. |
.. |
80,000 |
2,000 |
178.76 |
82,230.85 |
82,409.61 |
Completed. |
100 |
Clonmel New Post Office |
.. |
.. |
.. |
.. |
.. |
58,500 |
10,000 |
901.23 |
4,388.25 |
5,289.48 |
In planning. |
101 |
Donegal New Post Office |
.. |
.. |
.. |
.. |
.. |
135,000 |
30,000 |
2,898.00 |
2,986.70 |
5,884.70 |
In progress. |
102 |
Dungarvan New Post Office |
.. |
.. |
.. |
.. |
50,000 |
20,000 |
15,727.47 |
24,983.05 |
40,710.52 |
do. |
103 |
Enniscorthy Post Office: Improvements |
.. |
.. |
.. |
10,000 |
2,000 |
941.35 |
— |
941.35 |
In planning. |
103A |
Ceanannus Mor Post Office: Alterations |
.. |
.. |
.. |
9,000 |
|
4,950.00 |
— |
4,950.00 |
In progress. |
104 |
Letterkenny Post Office: Extension |
.. |
.. |
.. |
47,000 |
8,000 |
7,802.17 |
— |
7,802.17 |
In progress. |
105 |
Limerick Post Office: Improvements |
.. |
.. |
.. |
|
2,000 |
1,180.33 |
— |
1,180.33 |
In planning. |
106 |
Listowel New Post Office |
.. |
.. |
.. |
.. |
.. |
42,000 |
25,000 |
15,351.00 |
5,715.00 |
21,066.00 |
In progress. |
107 |
Longford New Post Office |
.. |
.. |
.. |
.. |
.. |
90,000 |
5,000 |
— |
— |
— |
In planning. |
108 |
Mullingar New Post Office |
.. |
.. |
.. |
.. |
.. |
150,000 |
5,000 |
— |
— |
— |
do. |
109 |
Shannon New Post Office |
.. |
.. |
.. |
.. |
.. |
|
15,000 |
6,685.94 |
1,060.43 |
7,746.37 |
In progress. |
110 |
Tipperary New Post Office |
.. |
.. |
.. |
.. |
.. |
130,000 |
10,000 |
1,599.34 |
2,310.00 |
3,909.34 |
In planning. |
111 |
Waterford Post Office: Improvements |
.. |
.. |
.. |
60,000 |
5,000 |
— |
— |
— |
do. |
|
|
|
|
243,540.24 |
|
|
|
|
Department of Foreign Affairs |
|
|
|
|
|
|
112 |
Ottawa Embassy: Extension and Improvements |
.. |
|
2,000 |
— |
109.24 |
109.24 |
do. |
112A |
New York—United Nations Mission—Chancery |
.. |
20,000 |
|
4,330.35 |
— |
4,330.35 |
In progress. |
113 |
Embassy to the Holy Sea: Adaptations |
.. |
.. |
.. |
30,000 |
5,000 |
26,707.90 |
46,431.50 |
73,139.40 |
do. |
114 |
E.E.C. Mission Brussels: Fitting out of New Office |
.. |
27,000 |
5,000 |
5,296.95 |
21,570.03 |
26,866.98 |
do. |
114A |
E.E.C. Conferences, Dublin: Provision of Facilities |
.. |
110,000 |
|
56,926.92 |
— |
56,926.92 |
do. |
115 |
Iveagh House: Provision of Strong Room |
.. |
.. |
12,000 |
3,000 |
3,059.54 |
9,457.98 |
12,517.52 |
Completed. |
116 |
Embassy at Tokyo: Fitting out for occupation |
.. |
.. |
|
35,000 |
9,725.12 |
26.64 |
9,751.76 |
In progress. |
117 |
Embassy at Moscow (includes Staff Residence): Fitting out for occupation |
.. |
.. |
.. |
.. |
.. |
|
35,000 |
52,185.90 |
— |
52,185.90 |
In progress. |
118 |
Embassy at Luxembourg: Fitting out for occupation |
.. |
|
25,000 |
19,709.00 |
555.60 |
20,264.60 |
do. |
119 |
Embassy at Geneva: Fitting out for occupation |
.. |
8,000 |
8,000 |
3,297.40 |
4,973.75 |
8,271.15 |
do. |
120 |
Embassy at Lagos: Erection |
.. |
.. |
.. |
.. |
— |
1,000 |
— |
— |
— |
In planning. |
120A |
Embassy at Bonn: Fitting out of New Office |
.. |
.. |
12,000 |
|
13,284.16 |
— |
13,284.16 |
In progress. |
|
|
|
|
194,523.24 |
|
|
|
121 |
Minor New Works not exceeding £5,000 each |
.. |
.. |
|
100,000 |
128,785.58 |
|
|
|
122 |
Urgent and Unforseen Works |
.. |
.. |
.. |
.. |
|
14,000 |
— |
|
|
|
123 |
Balances of Expenditure on works of prior years which |
|
|
|
|
|
|
|
might not have been completed on 1st April, 1974 |
.. |
|
40,000 |
38,004.74 |
|
|
|
|
Original |
|
7,993,000 |
10,645,416.21 |
Receipt from |
|
|
|
Supplementary |
|
2,561,000 |
(—)10,000.00 |
Vote 50 |
|
|
|
|
|
10,554,000 |
10,635,416.21 |
|
|
|
DETAILS OF NO. 121—MINOR NEW WORKS
Work No. |
Service and Description |
Total Estimate |
Vote 1 April to 31 December 1974 |
Expenditure |
Observations |
1 April to 31 December 1974 |
to 31/3/74 |
to 31/12/74 |
|
|
£ |
£ |
£ |
£ |
£ |
|
|
President |
|
|
|
|
|
|
19 |
Arus An Uachtaráin—Back Gate Lodge: Provision of |
|
|
|
|
|
|
|
Bathroom, etc. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
777.71 |
— |
777.71 |
In progress. |
93 |
Aras An Uachtaráin—Back Gate Lodge: New Boat House |
|
|
3,398.06 |
— |
3,398.06 |
Completed. |
88 |
Back Gate Lodge and Kitchen Garden Cottage—Electrical |
|
|
|
|
|
|
|
installation |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,117.22 |
— |
1,117.22 |
In progress. |
|
Oireachtas |
|
|
|
|
|
|
106 |
Leinster House—Provision of Room for Librarian |
.. |
|
|
1,287.84 |
— |
1,287.84 |
Completed. |
|
Department of Taoiseach |
|
|
|
|
|
|
49 |
Griffith Barracks (Central Statistics Office)—Fire Escape |
|
|
1,700.00 |
— |
1,700.00 |
In progress. |
140 |
State Apartments Dublin Castle:—Presidental |
|
|
|
|
|
|
|
Inauguration |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
282.60 |
— |
282.60 |
Completed. |
|
Department of Finance |
|
|
|
|
|
|
118 |
Athlone Government Offices—Heating System |
.. |
|
|
659.87 |
— |
659.87 |
In progress. |
103/48 of 73/74 |
Castlebar Government Offices—Resurfacing of yard |
.. |
|
|
812.59 |
2,070.00 |
2,882.59 |
Completed. |
128 |
Carlow Government Offices—Heating System |
.. |
.. |
|
|
113.73 |
— |
113.73 |
In progress. |
67 |
St. Martins House—National Science Council |
.. |
.. |
|
|
227.21 |
— |
227.21 |
Completed. |
103/50 of 73/74 |
Valuation Office, Ely Place—Adaptations |
.. |
.. |
|
|
134.91 |
68.50 |
203.41 |
In progress. |
39 |
Wexford Government Offices—Heating System |
.. |
.. |
|
|
1,840.18 |
— |
1,840.18 |
do. |
|
Revenue Commissioners |
|
|
|
|
|
|
66 |
Aras Brugha—Provision of Store |
.. |
.. |
.. |
.. |
|
|
357.53 |
— |
357.53 |
Completed. |
141 |
Dundalk—Renovations |
.. |
.. |
.. |
.. |
.. |
|
|
1,053.04 |
— |
1,053.04 |
In progress. |
71 |
Dundalk—Roden House: Conversion |
.. |
.. |
.. |
|
|
367.77 |
— |
367.77 |
In Progress |
103/160 of 73/74 |
Dun Laoghaire Harbour—New Clearing Station |
.. |
|
|
3,284.85 |
70.20 |
3,355.05 |
do. |
42 |
Ennis—Electrical Works Etc. |
.. |
.. |
.. |
.. |
|
|
285.24 |
— |
285.24 |
Completed. |
59 |
Government Buildings, Cork—Electrical Works Etc. |
.. |
|
|
592.46 |
— |
592.46 |
Completed. |
103/18 of 73/74 |
Kilkenny Garda Station—Accommodation for Revenue |
|
|
|
|
|
|
|
Staff |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
53.78 |
1,793.54 |
1,847.32 |
do. |
125 |
Lord Edward St., Dublin—Heating System |
.. |
.. |
|
|
158.84 |
— |
158.84 |
In progress. |
111 |
14, St. Stephen’s Green—Adaptations |
.. |
.. |
.. |
|
|
237.99 |
— |
237.99 |
do. |
103/17 of 73/74 |
Waterford Customs and Excise Office—Storage Heating |
|
|
439.02 |
600.00 |
1,039.02 |
Completed. |
84/97 of 72/73 |
Waterford Income Tax Office—Storage Heating |
.. |
|
|
490.13 |
1,000.00 |
1,490.13 |
do. |
103/118 of 73/74 |
Wexford Tax Office—Adaptations |
.. |
.. |
.. |
|
|
1,044.25 |
784.70 |
1,828.95 |
In progress. |
|
Office of Public Works |
|
|
|
|
|
|
103/38 of 73/74 |
Bourn Vincent Memorial Park—Bus park at Torc |
.. |
|
|
2,056.96 |
3,450.71 |
5,507.67 |
Completed. |
18 |
Bourn Vincent Memorial Park —Car park at |
|
|
|
|
|
|
|
Carrigafreaghane |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
835.50 |
— |
835.50 |
In progress. |
103/30 of 73/74 |
Phoenix Park—Children’s playground |
.. |
.. |
.. |
|
|
1,736.80 |
774.00 |
2,510.80 |
do. |
103/159 of 73/74 |
Phoenix Park—Whitefields: Provision of Central Heating |
|
|
67.00 |
1,281.00 |
1,348.00 |
Completed. |
103/97 of 73/74 |
St. Stephen’s Green—Supts. Residence: Provision of |
|
|
|
|
|
|
|
Central Heating |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
48.00 |
983.46 |
1,031.46 |
do. |
121 |
St. Stephen’s Green—Supt’s. Residence: Centre piece |
.. |
|
|
60.00 |
— |
60.00 |
do. |
147 |
Kenmare Estate—Water Supply |
.. |
.. |
.. |
.. |
|
|
592.03 |
— |
592.03 |
do. |
85 |
Shannon Navigation—Portumna Toll House—Sanitary |
|
|
|
|
|
|
|
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,025.00 |
— |
2,025.00 |
In progress. |
54 |
Royal Hospital—Provision of Bathroom etc. at West Ave. |
|
|
|
|
|
|
|
Cottage |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,426.59 |
— |
1,426.59 |
In progress. |
53 |
Dún Laoghaire Harbour—Provision of Store at |
|
|
|
|
|
|
|
Car-ferry terminal |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
88.43 |
— |
88.43 |
do. |
72 |
Drainage Maintenance Workshop, Lifford— |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,748.95 |
— |
2,748.95 |
do. |
74 |
Drainage Maintenance Workshop, Limerick— |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,207.50 |
|
3,207.50 |
do. |
103/127 of 73/74 |
City Hall, Cork—Stand at Science and Technology |
|
|
|
|
|
|
|
Exhibition 1974 |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
49.16 |
515.00 |
564.16 |
Completed. |
|
Department of the Public Service |
|
|
|
|
|
|
103/82 of 73/74 |
72-76 St. Stephen’s Green—Adaptations |
.. |
.. |
|
|
207.87 |
4,150.25 |
4,358.12 |
do. |
87 |
72-76 St. Stephen’s Green—Security Works |
.. |
.. |
|
|
473.46 |
— |
473.46 |
In progress. |
115 |
72-76 St. Stephen’s Green—Partitioning etc. |
.. |
.. |
|
|
36.92 |
— |
36.92 |
do. |
|
Department of Justice |
|
|
|
|
|
|
103/42 of 73/74 |
Four Courts—Toilet Accommodation |
.. |
.. |
.. |
|
|
117.83 |
1,491.52 |
1,609.35 |
Completed. |
55 |
Four Courts—Amplification System |
.. |
.. |
.. |
|
|
853.23 |
— |
853.23 |
do. |
112 |
Four Courts—Improvements: Chief Justices’ Chambers |
|
|
24.58 |
— |
24.58 |
In progress. |
38 |
39 Dawson Street—Partitioning |
.. |
.. |
.. |
.. |
|
|
287.47 |
— |
287.47 |
Completed. |
81 |
Public Record Office—Improvement Works |
.. |
.. |
|
|
117.98 |
— |
117.98 |
In progress. |
76 |
128 Lower Baggot Street—Adaptations to Basement |
.. |
|
|
21.00 |
— |
21.00 |
do. |
|
Department of Local Government |
|
|
|
|
|
|
103/123 of 73/74 |
Parkgate Hall Driving Test Centre—Provision of Public |
|
|
|
|
|
|
|
Toilet |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
59.57 |
338.22 |
397.79 |
Completed. |
17 |
Waterford Driving Test Centre—Improvements |
.. |
|
|
1,350.00 |
— |
1,350.00 |
In progress. |
|
Department of Education |
|
|
|
|
|
|
103/107 of 73/74 |
Limerick Model School—Accommodation for |
|
|
|
|
|
|
|
Inspectorate |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
264.33 |
164.91 |
429.24 |
In progress. |
120 |
National Library—Partitioning and Electrical Works |
.. |
|
|
31.05 |
— |
31.05 |
do. |
10 |
National Museum—Provision of sales cubicles |
.. |
.. |
|
|
978.25 |
— |
978.25 |
Completed. |
61 |
National Museum—Improvement of Sanitary |
|
|
|
|
|
|
|
Accommodation etc. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,348.82 |
— |
1,348.82 |
In progress. |
103/54 of 73/74 |
Sligo former Technical School—Accommodation for |
|
|
|
|
|
|
|
Inspectorate |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
866.42 |
2,134.54 |
3,000.96 |
do. |
|
Department of Lands |
|
|
|
|
|
|
103/25 of 73/74 |
Land Commission—23/34 Upper Merrion St.—Transfer |
|
|
|
|
|
|
|
of Court .. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,063.30 |
2,241.01 |
3,304.31 |
Completed. |
84/41 of 72/73 |
Land Commission—Rear of 23 Upper Merrion St. Storage |
|
|
|
|
|
|
|
access and car park improvements |
.. |
.. |
.. |
|
|
313.90 |
740.95 |
1,054.85 |
do. |
95 |
Land Commission—23 Upper Merrion St.—Provision of |
|
|
|
|
|
|
|
Training Facilities |
.. |
.. |
.. |
.. |
.. |
|
|
1,111.08 |
— |
1,111.08 |
do. |
103/29 of 73/74 |
Kinnity Castle, Birr—Adaptations |
.. |
.. |
.. |
|
|
290.44 |
3,770.00 |
4,060.44 |
do. |
29 |
Kinnity Castle, Birr—Provision of Central Heating |
.. |
|
|
4,746.70 |
— |
4,746.70 |
do. |
|
Department of Agriculture and Fisheries |
|
|
|
|
|
|
103/76 of 73/74 |
Abbotstown Farm Research Laboratory—Adaptations to |
|
|
|
|
|
|
|
piggery |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
2,197.64 |
834.56 |
3,032.20 |
In progress. |
103/79 of 73/74 |
Abbotstown Farm Research Laboratory—Provision of |
|
|
|
|
|
|
|
Store |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
216.65 |
2,307.97 |
2,524.62 |
Completed. |
103/98 of 73/74 |
Abbotstown Farm Research Laboratory—Central Heating |
|
|
|
|
|
|
|
in Directors House |
.. |
.. |
.. |
.. |
.. |
|
|
65.10 |
1,280.41 |
1,345.51 |
do. |
82 |
Abbotstown Farm Research Laboratory—Improvements |
|
|
|
|
|
|
|
to Dairy |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
241.83 |
— |
241.83 |
In progress. |
94 |
Abbotstown Farm Research Laboratory—Adaptations to |
|
|
|
|
|
|
|
Small Animal Unit |
.. |
.. |
.. |
.. |
.. |
|
|
948.49 |
— |
948.49 |
Completed. |
100 |
Abbotstown Farm Research Laboratory—Heating System |
|
|
|
|
|
|
|
—Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
928.29 |
— |
928.29 |
In progress. |
103/117 of 73/74 |
Abbotstown Farm Research Laboratory—Provision of |
|
|
|
|
|
|
|
A.I. Research Unit |
.. |
.. |
.. |
.. |
.. |
|
|
1,455.60 |
814.50 |
2,270.10 |
do. |
15 |
Ballyhaise Agricultural College—New Shower Unit |
.. |
|
|
1,937.10 |
— |
1,937.10 |
Completed. |
56 |
Ballyhaise Agricultural College—Well Boring |
.. |
.. |
|
|
3,197.02 |
— |
3,197.02 |
do. |
77 |
Ballyhaise Agricultural College—Improvements to House |
|
|
|
|
|
|
|
Masters House |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
345.00 |
— |
345.00 |
In progress. |
78 |
Ballyhaise Agricultural College—Erection of Retaining |
|
|
|
|
|
|
|
Walls |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,420.00 |
— |
3,420.00 |
Completed. |
102 |
Backweston Farm—Improvement of heating system |
.. |
|
|
1,299.33 |
— |
1,299.33 |
In progress. |
103/81 of 73/74 |
Ballsbridge Veterinary College—Improved toilet and |
|
|
|
|
|
|
|
canteen facilities |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
289.45 |
3,127.28 |
3,416.73 |
do. |
73 |
Ballsbridge Veterinary College—New microbiology |
|
|
|
|
|
|
|
unit |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,157.71 |
— |
1,157.71 |
do. |
103/84 of 73/74 |
Ballsbridge Veterinary College,—Improvement of teaching |
|
|
|
|
|
|
|
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
222.90 |
3,224.37 |
3,447.27 |
Completed. |
28 |
Castletownbere—Provision of Field Laboratory |
.. |
|
|
6,511.72 |
— |
6,511.72 |
In progress. |
58 |
Chantilly Field Station—Laboratory improvements |
.. |
|
|
120.52 |
— |
120.52 |
do. |
103/90 of 73/74 |
Kildalton Abbey—Provision of cooking equipment |
.. |
|
|
32.06 |
1,573.57 |
1,605.63 |
do. |
103/137 of 73/74 |
Ennis District Veterinary Office—Alterations |
.. |
.. |
|
|
398.49 |
300.00 |
698.49 |
Completed. |
84/45 of 72/73 |
Mellows Agricultural College—Supts. Residence: |
|
|
|
|
|
|
|
Improvements |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,074.55 |
3,416.94 |
4,491.49 |
do. |
84/95 of 72/73 |
Mellows Agricultural College—Erection of building to |
|
|
|
|
|
|
|
house generator |
.. |
.. |
.. |
.. |
.. |
|
|
1,585.92 |
2,554.00 |
4,139.92 |
do. |
70 |
Munster Institute—Improved kitchen equipment |
.. |
|
|
991.94 |
— |
991.94 |
In progress. |
86 |
Munster Institute—Improvements to Poultry Processin |
|
|
|
|
|
|
|
building |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
578.09 |
— |
578.09 |
In progress. |
103/35 of 73/74 |
Thorndale Laboratory—Provision of cattle crush chute |
|
|
335.78 |
512.99 |
848.77 |
Completed. |
45 |
Thorndale Laboratory—Provision of meal store |
.. |
|
|
92.68 |
— |
92.68 |
In progress. |
103/31 of 73/74 |
Thorndale Laboratory—Improvement of entrance |
.. |
|
|
6.21 |
3,706.47 |
3,712.68 |
Completed. |
|
Department of Labour |
|
|
|
|
|
|
143 |
Bray Employment Exchange—Adaptations |
.. |
.. |
|
|
1,000.00 |
— |
1,000.00 |
In progress. |
62 |
Manpower Service, Athlone—Storage heating |
.. |
.. |
|
|
365.80 |
— |
365.80 |
Completed. |
50 |
Manpower Service, Clonmel—Fitting out |
.. |
.. |
|
|
401.25 |
— |
401.25 |
do. |
84/12 of 72/73 |
Manpower Services, Ballybofey—Conversion of premises |
|
|
|
|
|
|
|
(Finn College) |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
466.27 |
1,161.44 |
1,627.71 |
do. |
35 |
Manpower Service, Limerick—Partitioning etc. |
.. |
.. |
|
|
75.50 |
— |
75.50 |
In progress. |
74/98 of 71/72 |
Manpower Service, Waterford—Adaptations |
.. |
.. |
|
|
500.00 |
4,258.41 |
4,758.41 |
Completed. |
64 |
Manpower Service, O’Connell Bridge House—Partitioning |
|
|
1,066.98 |
— |
1,066.98 |
Completed. |
103/69 of 73/74 |
Ansley House—Tea Room facilities |
.. |
.. |
.. |
|
|
9.77 |
645.01 |
654.78 |
do. |
103/41 of 73/74 |
Werburgh St. Employment Exchange—Provision of |
|
|
|
|
|
|
|
protective grill and counter |
.. |
.. |
.. |
.. |
.. |
|
|
488.06 |
482.00 |
970.00 |
do. |
75 |
Department of Industry and Commerce |
|
|
|
|
|
|
|
|
|
|
|
Kildare Street—Adaptations |
.. |
.. |
.. |
.. |
|
|
937.55 |
— |
937.55 |
In progress. |
20 |
Kildare Street—Partitioning |
.. |
.. |
.. |
.. |
|
|
1,306.19 |
— |
1,306.19 |
Completed. |
14 |
Geological Survey Office, Hume St.—Stores for |
|
|
|
|
|
|
|
Equipment etc. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
126.49 |
— |
126.49 |
In progress. |
|
Department of Transport and Power |
|
|
|
|
|
|
74/35 of 71/72 |
Cork Mercantile Marine Office—Improvements |
.. |
|
|
35.25 |
4,042.63 |
4,077.88 |
Completed. |
84/60 of 72/73 |
Valentia Radio Station—Improvements to Married |
|
|
|
|
|
|
|
Quarters |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
984.50 |
2,668.00 |
3,652.50 |
do. |
52 |
Kildare Street—Additional Accommodation |
.. |
.. |
|
|
997.39 |
— |
997.39 |
In progress. |
|
Department of Posts and Telegraphs |
|
|
|
|
|
|
103/153 of 73/74 |
G.P.O., Dublin—Improvements |
.. |
.. |
.. |
.. |
|
|
11,680.62 |
1,784.95 |
13,465.57 |
In progress. |
84 |
G.P.O., Dublin—Improvements to windows |
.. |
.. |
|
|
1,572.37 |
— |
1,572.37 |
Completed. |
103/63 of 73/74 |
St. John’s Road Depot—Provision of store |
.. |
.. |
|
|
742.65 |
809.41 |
1,552.06 |
do. |
103/51 of 73/74 |
Stores Depot, Infirmary Road—Erection of prefab dining |
|
|
|
|
|
|
|
room |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
133.75 |
348.41 |
482.16 |
do. |
90 |
Central Sorting Office—Security improvements |
.. |
.. |
|
|
762.50 |
— |
762.50 |
In progress. |
97 |
Central Sorting Office—Improvement of Dining Club |
|
|
|
|
|
|
|
facilities |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,687.65 |
— |
1,687.65 |
do. |
103/131 of 73/74 |
Sandwith St. Garage—Provision of parking area |
.. |
|
|
307.63 |
68.53 |
376.16 |
Completed. |
84/48 of 72/73 |
Hammam Buildings, 11/13 Upper O’Connell Street— |
|
|
|
|
|
|
|
Internal adaptations |
.. |
.. |
.. |
.. |
.. |
|
|
1.61 |
3,079.49 |
3,081.10 |
do. |
139 |
Priory Hall (Tallaght) Post Office—Adaptations |
.. |
.. |
|
|
2,177.09 |
— |
2,177.09 |
In progress. |
103/115 of 73/74 |
Ballina Post Office—New floor in Sorting Office, etc |
.. |
|
|
655.00 |
600.00 |
1,255.00 |
Completed. |
117 |
Carlow Post Office—Improvements to heating system |
.. |
|
|
360.07 |
— |
360.07 |
In progress. |
57 |
Castlebar Post Office—Alterations |
.. |
.. |
.. |
|
|
4,050.00 |
— |
4,050.00 |
do. |
43 |
Fenian House, Dublin—Partitioning etc. |
.. |
.. |
|
|
2,579.72 |
— |
2,579.72 |
do. |
68 |
Roscommon Post Office—Provision of petrol pump |
.. |
|
|
421.01 |
— |
421.01 |
Completed. |
41 |
Sligo Post Office—Alterations to yard entrance |
.. |
.. |
|
|
325.00 |
— |
325.00 |
do. |
65 |
Tuam Post Office—Sanitary accommodation |
.. |
.. |
|
|
3,330.00 |
— |
3,330.00 |
In progress. |
44 |
Westport Post Office—Sanitary accommodation |
.. |
|
|
900.00 |
— |
900.00 |
do. |
40 |
Wexford Post Office—Provision of fire escape |
.. |
.. |
|
|
1,272.50 |
— |
1,272.50 |
Completed. |
|
Department of Defence |
|
|
|
|
|
|
103/52 of 73/74 |
G.H.Q., Parkgate Street—Adaptations |
.. |
.. |
.. |
|
|
482.78 |
967.16 |
1,449.94 |
In progress. |
103/73 of 73/74 |
G.H.Q., Parkgate Street—Improvements to toilets |
.. |
|
|
71.00 |
413.08 |
484.08 |
Completed. |
101 |
Red House—Infirmary Road—Improved heating system |
|
|
401.85 |
— |
401.85 |
do. |
74/46 of 71/72 |
Coláiste Caoimhin—Inprovements |
.. |
.. |
.. |
|
|
27.25 |
4,524.88 |
4,552.13 |
In progress. |
|
Department of Foreign Affairs |
|
|
|
|
|
|
30 |
30 Earlsfort Terrace—Central heating |
.. |
.. |
.. |
|
|
990.00 |
— |
990.00 |
Completed. |
103/102 of 73/74 |
Brussels Embassy—Fitting out of new offices |
.. |
.. |
|
|
822.21 |
479.88 |
1,302.09 |
In progress. |
25 |
The Hague Embassy Residence—New Bathroom |
.. |
|
|
1,496.21 |
— |
1,496.21 |
Completed. |
|
Department of Social Welfare |
|
|
|
|
|
|
32 |
Kilmallock Social Welfare Office—Adaptations |
.. |
.. |
|
|
366.29 |
— |
366.29 |
do. |
103/41 of 73/74 |
Granard Social Welfare Office—New Building |
.. |
.. |
|
|
1,393.84 |
1,710.00 |
3,103.84 |
In progress. |
|
Department of Health |
|
|
|
|
|
|
89 |
Custom House—Adaptations to General Register Office |
|
|
878.07 |
— |
878.07 |
do. |
109 |
Custom House—Tiling of corridors |
.. |
.. |
.. |
|
|
262.90 |
— |
262.90 |
do. |
DETAILS OF NO. 123—MINOR BALANCES OF EXPENDITURE
Work No. |
Service and Description |
Total Estimate |
Vote 1 April to 31 December 1974 |
Expenditure |
Observations |
1 April to 31 December 1974 |
to 31/3/74 |
to 31/12/74 |
|
Oireachtas |
£ |
£ |
£ |
£ |
£ |
|
1 (1) of 71/72 |
Leinster House—Extension and alterations |
.. |
.. |
|
|
1,000.00 |
770,968.92 |
771,968.92 |
Completed. |
|
Department of an Taoiseach |
|
|
|
|
|
|
3A of 72/73 |
State Apartments, Dublin Castle—Rebuilding of Drawing Room, |
|
|
|
|
|
|
|
|
|
Bedroom, Block and Main Entrance |
.. |
.. |
|
|
3,091.45 |
527,899.90 |
530,991.35 |
do. |
|
Department of Finance |
|
|
|
|
|
|
5 of 72/3 |
4 Kildare St.—Improvements |
.. |
.. |
.. |
.. |
|
|
68.13 |
29,650.50 |
29718.63 |
do. |
21 of 72/3 |
Garden of Remembrance—Inscription on back wall |
.. |
|
|
150.00 |
6,235.34 |
6,385.34 |
Design completed. |
29 (1) of 73/74 |
Scoil Eanna, Rathfarnham—Restoration of building |
|
|
|
|
|
|
|
(Stage 1) |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
5,417.26 |
39,074.55 |
44,491.81 |
Completed. |
|
Department of Education |
|
|
|
|
|
|
55 of 73/4 |
Dublin Institute for Advanced Studies—(Accommodation) |
|
|
1,807.74 |
190,519.06 |
192,326.80 |
Completed. |
40A of 71/2 |
Coláiste Mhuire, 28 Parnell Square—Adaptations |
.. |
|
|
846.00 |
13,000.00 |
13,846.00 |
do. |
|
Department of Labour |
|
|
|
|
|
|
53 of 71/2 |
Belmullet—New Government Offices |
.. |
.. |
.. |
|
|
2,780.50 |
10,566.77 |
13,347.27 |
Completed. |
|
Department of Agriculture and Fisheries |
|
|
|
|
|
|
60/1 of 73/4 |
Abbotstown Farm—New Laboratory Block |
.. |
.. |
|
|
509.21 |
150,929.58 |
151,438.79 |
do. |
61 of 72/3 |
Dunmore East Harbour—Field Research Station |
.. |
|
|
120.03 |
6,376.28 |
6,496.31 |
do. |
66A of 73/4 |
Veterinary College, Ballsbridge—Extra Accommodation |
|
|
149.97 |
6,248.44 |
6,398.41 |
do. |
55 of 72/3 |
Abbotstown Farm—Experimental Animals |
|
|
|
|
|
|
|
Accommodation |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
3,779.06 |
179,671.26 |
183,450.32 |
do. |
|
Department of Posts and Telegraphs |
|
|
|
|
|
|
79 of 73/4 |
Glenageary—New Sorting Office |
.. |
.. |
.. |
.. |
|
|
781.56 |
61,526.56 |
62,308.12 |
do. |
90A of 73/4 |
Kilmallock Post Office—Alterations and improvements |
.. |
|
|
1,731.18 |
4,320.00 |
6,051.18 |
do. |
80 of 73/4 |
Harmonstown Sorting Office—Extension |
.. |
.. |
.. |
|
|
2,143.20 |
13,778.69 |
15,921.89 |
do. |
86 of 73/4 |
Castlebar—Engineering Headquarters and Garage |
.. |
|
|
580.20 |
4,075.00 |
4,655.20 |
Completed. |
72 of 73/4 |
Blackrock Post Office—Modernisation |
.. |
.. |
.. |
|
|
187.03 |
11,046.71 |
11,233.74 |
do. |
95 of 73/4 |
Nenagh—New Post Office |
.. |
.. |
.. |
.. |
|
|
7,336.53 |
80,252.65 |
87,589.18 |
do. |
|
Department of Defence |
|
|
|
|
|
|
81 of 72/3 |
Parkgate Street—Alterations |
.. |
.. |
.. |
.. |
|
|
4.15 |
11,688.72 |
11,692.87 |
do. |
99A of 73/74 |
Parkgate Street—Installation of Automatic Central |
|
|
|
|
|
|
|
Heating |
.. |
.. |
.. |
.. |
.. |
.. |
.. |
|
|
1,691.00 |
5,011.78 |
6,702.78 |
do. |
|
Department of Social Welfare |
|
|
|
|
|
|
102A of 73/74 |
Aras Mhic Dhiarmada—Computer |
.. |
.. |
.. |
|
|
3,830.54 |
31,910.52 |
35,741.06 |
do. |
|