Committee Reports::Report - Appropriation Accounts 1970 - 1971::28 February, 1974::Appendix

APPENDIX 6.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1970/71 (VOTE 8: SUBHEAD E).

 

 

 

 

Expenditure

 

Work No.

Service and Description

Total Estimate

Vote 1970/71

1970/71

to 31/3/70

to 31/3/71

Observations

 

 

£

£

£

£

£

 

 

Oireachtas:

 

 

 

 

 

 

1 (1)

Leinster House—Extension and Alterations

..

..

..

760,000

3,500

11,950.49

753,456.39

765,406.88

Completed

1 (2)

Seanad—Provision of Sound Reinforcement System in Seanad

 

 

 

 

 

 

 

Chamber

..

..

..

..

..

..

..

..

6,000

3,924.29

3,924.29

Completed

 

 

 

 

15,874.78

 

 

 

 

Department of an Taoiseach:

 

 

 

 

 

 

2

Dublin Castle, State Apartments—Rebuilding of Drawingroom/

 

 

 

 

 

 

 

Bedroom Block and Main Entrance

..

..

..

..

508,000

20,000

16,856.16

485,816.70

502,672.86

Completed

 

 

 

 

16,856.16

 

 

 

 

Department of Finance:

 

 

 

 

 

 

3

Provision of Central Computing Unit

..

..

..

..

Not yet made

1,000

 

12.00

12.00

In Planning

4

No. 4 Kildare Street: Adaptation Works

..

..

..

11,000

8,000

2,524.20

2,524.20

In Progress

4A

State Buildings Kildare St./Merrion Street—New Electricity

 

 

 

 

 

 

 

Distribution System

..

..

..

..

..

..

41,000

8,248.44

31,346.49

39,594.93

Completed

5 (1)

Additional Accommodation—Arkle House, Lower Mount

 

 

8,242.16

8,242.16

Completed

 

Street, Dublin

..

..

..

..

..

..

 

 

 

 

 

 

5 (2)

Additional Accommodation—Apollo House, Tara Street,

80,000

70,000

15,730.72

15,730.72

Completed

 

Dublin

..

..

..

..

..

..

..

 

 

 

 

 

 

5 (3)

Additional Accommodation—Phibsboro

..

..

..

 

 

17,132.96

17,132.96

Completed

6

Revenue Commissioners—Dublin Castle Stamping Branch—

 

 

 

 

 

 

 

New Premises

..

..

..

..

..

..

..

900,000

300,000

199,221.05

111,459.33

310,680.38

In Progress

7

Revenue Commissioners—Aras Brugha—Fire Precautions and

 

 

 

 

 

 

 

Additional Air Conditioning

..

..

..

..

..

21,500

10,000

2,426.55

6,547.17

8,973.72

Completed

8

Revenue Commissioners—Aras Brugha—Extension to

 

 

 

 

 

 

 

Computer Room

..

..

..

..

..

..

..

6,000

4,000

2,814.49

2,814.49

Virtually completed

9

Revenue Commissioners—11/15 Upper O’Connell Street;

 

 

 

 

 

 

 

Adaptation works

..

..

..

..

..

..

..

25,000

5,000

14,847.43

10,728.03

25,575.46

In Progress

9A

Revenue Commissioners—Aras Brugha, 9/10 Upper O’Connell

 

 

 

 

 

 

 

Street—Adaptations

..

..

..

..

..

..

37,000

 

1,996.00

1,996.00

In Planning.

10

Revenue Commissioners—Kildrum, Co. Donegal: New Frontier

 

 

 

 

 

 

 

Post

..

..

..

..

..

..

..

..

6,500

5,000

4,590.00

4,590.00

Completed

11 (1)

Office of Public Works Dublin: Central Engineering

 

 

 

 

 

 

 

Workshops:—Provision of New Central Heating System

..

..

 

1,000

In Planning

11 (2)

Office of Public Works: Roonagh Point, Co. Mayo—Extension

 

 

 

 

 

 

 

of Pier

..

..

..

..

..

..

..

..

40,500

40,000

In Planning

11 (3)

Office of Public Works Dublin: 51 St. Stephens Green—

 

 

 

 

 

 

 

Adaptations and Improvements

..

..

..

..

..

..

15,000

2,709.00

6,010.55

8,719.55

In Progress

12

Drogheda—New Offices for various Departments

..

..

115,000

4,000

1,200.00

1,200.00

In Planning

13

Mullingar—New Government Offices

..

..

..

..

20,000

2,500

7,858.20

7,858.20

Completed

13A

Galway Government Offices—Hynes Building

..

..

..

12,000

8,705.45

8,705.45

Virtually completed

13B

Monaghan New Government Offices—Provision of Visitors

 

 

 

 

 

 

 

Reception Building

..

..

..

..

..

..

10,000

7,000.00

7,000.00

Virtually completed

14

Garden of Remembrance—Memorial Sculpture

..

..

38,500

10,000

22,280.34

10,159.85

32,440.19

In Progress

15

State Memorial to the late President J. F. Kennedy

..

..

2,764,000

20,000

25,351.00

73,441.65

98,792.65

In Planning

16

Memorial to Roger Casement in Glasnevin Cemetery

..

..

5,000

3,000

600.00

1,500.00

2,100.00

In progress

17 (1)

Bourn Vincent Memorial Park: Muckross House—Heating and

 

 

 

 

 

 

 

Lighting installations

..

..

..

..

..

..

13,000

13,000

16,122.63

331.97

16,454.60

In progress

17 (2)

Bourn Vincent Memorial Park: Muckross House—Road Works

 

 

 

 

 

 

 

and Provision of Car Park

..

..

..

..

..

11,000

4,000

378.84

4,551.77

4,930.61

In progress

17 (3)

Bourn Vincent Memorial Park: Improvements to Farmyard

..

6,000

2,500

1,527.76

3,692.47

5,220.23

In progress

17 (4)

Bourn Vincent Memorial Park: Toilets at Muckross Gardens

..

3,000

 

1,350.00

1,350.00

In progress

18 (1)

Kilkenny Castle—Development of grounds as Public Park

..

25,000

 

9,448.89

18,257.27

27,706.16

In progress

18A

Dunlaoghaire Harbour—Car Ferry Terminals

..

..

..

1,070,000

 

21,064.19

1,120,276.27

1,141,340.46

Completed

18B

Dunmore Caves, Kilkenny. Visitor Centre

..

..

..

12,000

 

250.00

250.00

In progress

 

 

 

 

402,420.30

 

 

 

 

Department of Justice:

 

 

 

 

 

 

19

Garda Síochána Depot, Phoenix Park—Improvement of

 

 

 

 

 

 

 

Workshop Accommodation

..

..

..

..

..

..

23,000

18,000

12,194.20

698.00

12,892.20

In progress

20

Garda Headquarters—Technical Bureau—Improvements

..

12,000

6,000

13,726.38

4,880.58

18,606.96

In progress

21

Garda Training Centre, Templemore—Adaptations etc.

..

647,000

4,000

148.07

640,492.05

640,640.12

Completed

22

Erection of New Garda Stations

..

..

..

..

..

180,000

155,614.51

 

 

 

 

 

 

 

Detailed as follows:

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

Ballyfermot

..

..

..

..

..

..

..

 

 

27,781.00

9,376.23

37,157.23

In progress

 

Rathmines

..

..

..

..

..

..

..

 

 

11,345.00

4,569.60

15,914.60

In progress

 

Kevin Street

..

..

..

..

..

..

..

 

 

10,575.48

10,575.48

In progress

 

Store Street

..

..

..

..

..

..

..

 

 

748.08

1,000.00

1,748.08

In planning

 

Co. Clare:

 

 

 

 

 

 

 

Ennistymon

..

..

..

..

..

..

..

 

 

8,950.00

15,750.00

24,700.00

Completed

 

Kilrush

..

..

..

..

..

..

..

..

 

 

4,295.00

9,150.71

13,445.71

Completed

 

Co. Cork:

 

 

 

 

 

 

 

Ballydesmond

..

..

..

..

..

..

..

 

 

66.43

1,977.72

2,044.15

Completed

 

Co. Donegal:

 

 

 

 

 

 

 

Dungloe

..

..

..

..

..

..

..

..

 

 

4,353.00

225.00

4,578.00

Completed

 

Co. Dublin:

 

 

 

 

 

 

 

Coolock

..

..

..

..

..

..

..

..

 

 

3,829.95

23,781.08

27,611.03

Completed

 

Dundrum

..

..

..

..

..

..

..

 

 

19,050.00

10,824.20

29,874.20

Completed

 

Raheny

..

..

..

..

..

..

..

..

 

 

21,903.00

3,313.55

25,216.55

In progress

 

Co. Gaway:

 

 

 

 

 

 

 

Clifden

..

..

..

..

..

..

..

..

 

 

9,558.00

9,558.00

In progress

 

Co. Kildare:

 

 

 

 

 

 

 

Droichead Nua

..

..

..

..

..

..

..

 

 

1,089.73

17,425.33

18,515.06

Completed

 

Co. Laols:

 

 

 

 

 

 

 

Ballickmoyler (Arles)

..

..

..

..

..

..

 

 

333.87

5,646.40

5,980.27

Completed

 

Co. Leitrim:

 

 

 

 

 

 

 

Kiltyclogher

..

..

..

..

..

..

..

 

 

6,750.00

6,750.00

In progress

 

Co. Limerick:

 

 

 

 

 

 

 

Rathkeale

..

..

..

..

..

..

..

..

 

 

1,757.57

6,840.00

8,597.57

Completed

 

Castleconnell

..

..

..

..

..

..

..

 

 

1,156.76

7,155.00

8,311.76

Completed

 

Limerick City

..

..

..

..

..

..

..

 

 

2,040.00

2,040.00

In planning

 

Co. Meath:

 

 

 

 

 

 

 

Ballivor

..

..

..

..

..

..

..

..

 

 

1,330.00

4,708.24

6,038.24

Completed

 

Slane

..

..

..

..

..

..

..

..

 

 

100.00

8,180.16

8,280.16

Completed

 

Co. Offaly:

 

 

 

 

 

 

 

Birr

..

..

..

..

..

..

..

..

..

 

 

7,200.00

7,200.00

In progress

 

Co. Sligo:

 

 

 

 

 

 

 

Aclare

..

..

..

..

..

..

..

..

 

 

4,410.00

3,240.00

7,650.00

Virtually completed

 

Co. Tipperary:

 

 

 

 

 

 

 

Portroe

..

..

..

..

..

..

..

..

 

 

3,510.00

3,600.00

7,110.00

Virtually completed

 

Co. Waterford:

 

 

 

 

 

 

 

Ardmore

..

..

..

..

..

..

..

..

 

 

588.24

7,267.85

7,856.09

Completed

 

Waterford

..

..

..

..

..

..

..

..

 

 

2,000.00

2,000.00

In progress

 

Co. Westmeath:

 

 

 

 

 

 

 

Moate

..

..

..

..

..

..

..

..

 

 

84.75

84.75

In planning

 

Ballinahowen

..

..

..

..

..

..

..

 

 

10.00

10.00

Under consideration

 

Co. Wexford:

 

 

 

 

 

 

 

Clonroche

..

..

..

..

..

..

..

..

 

 

2.65

5.00

7.65

In planning

 

Co. Wicklow:

 

 

 

 

 

 

 

Enniskerry

..

..

..

..

..

..

..

..

 

 

796.00

796.00

In planning

23

Improvement schemes at existing Garda Stations

..

..

 

55,000

64,909.78

 

 

 

 

 

 

 

Detailed as follows:

 

 

 

Sub. No.

Dublin Metropolitan Division:

 

 

 

 

 

 

27/83 of 69/70

Garda H.Q. Depot

..

..

..

..

..

..

..

 

 

283.00

52.95

335.95

Completed

31/46 of 68/69

Garda H.Q. Phoenix Park (Stationery Section)

..

..

..

 

 

6.73

1,923.70

1,930.43

Completed

41

Garda Depot Phoenix Park, Room 68

..

..

..

..

 

 

271.00

271.00

Completed

67

Garda Depot Phoenix Park, Adaptations

..

..

..

 

 

528.50

528.50

Completed

31/71 of 68/69

Central Detective Unit, Ship Street

..

..

..

..

 

 

83.80

7,707.15

7,790.95

Completed

27/27 of 69/70

Garda Huts, Aras An Uachtaráin

..

..

..

..

..

 

 

620.75

462.28

1,083.03

In progress

52

Garda Hut at City Gate, do

..

..

..

..

..

 

 

1,143.00

1,143.00

Completed

76

Garda Hut at Greenfield Rd., Sutton

..

..

..

..

 

 

295.00

295.00

Completed

85

An Taoiseach’s Residence, Rathgar, Protection Hut

..

..

 

 

6.50

6.50

In progress

31/58 of 68/69

Bridewell

..

..

..

..

..

..

..

..

 

 

63.70

1,491.03

1,554.73

Completed

Sub. No.

 

 

 

 

 

 

 

27/55 of 69/70

Clontarf

..

..

..

..

..

..

..

..

 

 

140.37

395.04

535.41

Completed

65

Crumlin

..

..

..

..

..

..

..

..

 

 

525.00

525.00

Completed

38

Dalkey

..

..

..

..

..

..

..

..

 

 

570.57

570.57

In progress

54

Dunlaoghaire

..

..

..

..

..

..

..

 

 

1,715.96

1,715.96

Completed

32/16 of 67/68

Finglas

..

..

..

..

..

..

..

..

 

 

663.55

2,902.57

3,566.12

Completed

27/71 of 69/70

Irishtown

..

..

..

..

..

..

..

..

 

 

109.32

400.69

510.01

Completed

27/67 of 69/70

Pearse Street

..

..

..

..

..

..

..

..

 

 

6.25

414.94

421.19

Completed

27/90 of 69/70

Rathfarnham

..

..

..

..

..

..

..

 

 

30.64

70.37

101.01

Completed

 

Co. Carlow:

 

 

 

 

 

 

31/16 of 68/69

Borris

..

..

..

..

..

..

..

..

..

 

 

518.20

1,708.00

2,226.20

Completed

 

Co. Cavan:

 

 

 

 

 

 

27/41 of 69/70

Finea

..

..

..

..

..

..

..

..

..

 

 

360.00

860.00

1,220.00

Completed

31/72 of 68/69

Shercock

..

..

..

..

..

..

..

..

 

 

107.25

720.00

827.25

Completed

27/35 of 69/70

Cavan

..

..

..

..

..

..

..

..

 

 

1,895.00

47.50

1,942.50

In progress

27/31 of 69/70

Tullyvin

..

..

..

..

..

..

..

..

 

 

133.85

1,580.00

1,713.85

Completed

Sub. No.

Co. Clare:

 

 

 

 

 

 

27/44 of 69/70

Quin

..

..

..

..

..

..

..

..

..

 

 

386.28

1,064.00

1,450.28

Completed

 

Co. Cork:

 

 

 

 

 

 

27/94 of 69/70

Union Quay—Immigration Office

..

..

..

..

..

 

 

399.90

277.77

677.67

Completed

27/87 of 69/70

Union Quay (Improvements)

..

..

..

..

..

 

 

715.40

401.93

1,117.33

Completed

27/95 of 69/70

Douglas

..

..

..

..

..

..

..

..

 

 

211.37

280.02

491.39

Completed

27/70 of 69/70

Goleen

..

..

..

..

..

..

..

..

 

 

1,145.00

855.00

2,000.00

Completed

31/68 of 68/69

Glengarriff

..

..

..

..

..

..

..

..

 

 

66.67

1,072.40

1,139.07

Completed

32/98 of 67/68

Ballyvourney

..

..

..

..

..

..

..

..

 

 

218.19

475.00

693.19

Completed

27/30 of 69/70

Union Quay

..

..

..

..

..

..

..

..

 

 

287.94

60.48

348.42

Completed

32/27 of 67/68

Newmarket

..

..

..

..

..

..

..

..

 

 

305.00

195.00

500.00

Completed

44

Rathduff

..

..

..

..

..

..

..

..

 

 

990.00

990.00

In progress

49

Glenville

..

..

..

..

..

..

..

..

 

 

815.00

815.00

In progress

Sub. No.

Co. Cork:

 

 

 

 

 

 

31/34 of 68/69

Passage West

..

..

..

..

..

..

..

 

 

270.00

2,161.00

2,431.00

Completed

 

Co. Donegal:

 

 

 

 

 

 

42

Kerrykeel

..

..

..

..

..

..

..

..

 

 

1,215.00

1,215.00

In progress

78

Churchill

..

..

..

..

..

..

..

..

 

 

810.00

810.00

In progress

60

Carrick

..

..

..

..

..

..

..

..

 

 

2,044.03

2,044.03

In progress

 

Co. Dublin:

 

 

 

 

 

 

63

Balbriggan

..

..

..

..

..

..

..

..

 

 

280.30

280.30

Completed

73

Glencairn (Huts for Garda)

..

..

..

..

..

 

 

517.83

517.83

In progress

 

Co. Galway:

 

 

 

 

 

 

7

Lettermore

..

..

..

..

..

..

..

..

 

 

476.73

476.73

In progress

43

Mountbellew

..

..

..

..

..

..

..

..

 

 

352.60

352.60

In progress

58

Kilconly

..

..

..

..

..

..

..

..

 

 

1,530.00

1,530.00

In progress

74

Loughgeorge

..

..

..

..

..

..

..

..

 

 

1,100.00

1,100.00

In progress

32/35 of 67/68

Corofin

..

..

..

..

..

..

..

..

 

 

236.31

1,918.24

2,154.55

Completed

22/42 of 66/67

Kilcolgan

..

..

..

..

..

..

..

..

 

 

342.86

1,613.06

1,955.92

Completed

22/15 of 66/67

Barnaderg

..

..

..

..

..

..

..

..

 

 

396.51

1,835.76

2,232.27

Completed

77

Letterfrack

..

..

..

..

..

..

..

..

 

 

315.50

315.50

In progress

Sub. No.

Co. Kerry:

 

 

 

 

 

 

14

Camp

..

..

..

..

..

..

..

..

 

 

1,360.46

1,360.46

In progress

22/37 of 66/67

Castleisland

..

..

..

..

..

..

..

..

 

 

830.99

1,485.00

2,315.99

Completed

32

Glenbeigh

..

..

..

..

..

..

..

..

 

 

1,425.43

1,425.43

In progress

86

Killarney

..

..

..

..

..

..

..

..

 

 

269.00

269.00

In progress

31/35 of 68/69

Tarbert

..

..

..

..

..

..

..

..

 

 

782.28

2,880.00

3,662.28

Completed

 

Co. Kildare:

 

 

 

 

 

 

48

Athy

..

..

..

..

..

..

..

..

..

 

 

4,050.00

4,050.00

In progress

50

Monasterevin

..

..

..

..

..

..

..

 

 

350.00

350.00

In progress

32/56 of 67/68

Robertstown

..

..

..

..

..

..

..

 

 

1,486.00

129.75

1,615.75

In progress

 

Co. Kilkenny:

 

 

 

 

 

 

32/26 of 67/68

Inistiogue

..

..

..

..

..

..

..

..

 

 

720.00

1,260.00

1,980.00

In progress

 

Co. Limerick:

 

 

 

 

 

 

27/72 of 69/70

Hospital

..

..

..

..

..

..

..

..

 

 

1,523.00

495.00

2,018.00

Completed

36

Kilmeedy

..

..

..

..

..

..

..

..

 

 

160.00

160.00

Completed

51

Ballingarry

..

..

..

..

..

..

..

..

 

 

765.00

765.00

In progress

79

Edward Street

..

..

..

..

..

..

..

 

 

107.50

107.50

In progress

Sub. No.

Co. Longford:

 

 

 

 

 

 

27/50 of 69/70

Newtowncashel

..

..

..

..

..

..

..

 

 

780.73

1,530.00

2,310.73

Completed

27/58 of 69/70

Smear

..

..

..

..

..

..

..

..

..

 

 

378.00

972.00

1,350.00

In progress

 

Co. Mayo:

 

 

 

 

 

 

61

Ballyvary

..

..

..

..

..

..

..

..

 

 

1,800.00

1,800.00

In progress

26

Balla

..

..

..

..

..

..

..

..

..

 

 

816.50

816.50

Completed

71

Ballycroy

..

..

..

..

..

..

..

..

 

 

138.50

138.50

Completed

23

Kiltimagh

..

..

..

..

..

..

..

..

 

 

1,065.97

1,065.97

In progress

 

Co. Meath:

 

 

 

 

 

 

62

Ceanannus Mor

..

..

..

..

..

..

..

 

 

2,160.00

2,160.00

In progress

87

Dunshaughlin

..

..

..

..

..

..

..

 

 

650.00

650.00

In progress

33

Summerhill

..

..

..

..

..

..

..

..

 

 

1,425.00

1,425.00

In progress

 

Co. Offaly:

 

 

 

 

 

 

27/65 of 69/70

Rhode

..

..

..

..

..

..

..

..

 

 

710.00

810.00

1,520.00

In progress

35

Tullamore

..

..

..

..

..

..

..

..

 

 

810.00

810.00

In progress

 

Co. Roscommon:

 

 

 

 

 

 

13

Ballyforan

..

..

..

..

..

..

..

..

 

 

1,467.25

1,467.25

In progress

27/46 of 69/70

Tarmonbarry

..

..

..

..

..

..

..

 

 

244.11

1,400.00

1,644.11

Completed

18

Taughmaconnell

..

..

..

..

..

..

..

 

 

117.75

117.75

In progress

16

Tulsk

..

..

..

..

..

..

..

..

..

 

 

1,800.00

1,800.00

In progress

Sub. No.

Co. Sligo:

 

 

 

 

 

 

27/32 of 69/70

Enniscrone

..

..

..

..

..

..

..

..

 

 

800.00

1,000.00

1,800.00

In progress

27/61 of 69/70

Riverstown

..

..

..

..

..

..

..

..

 

 

507.75

900.00

1,407.75

Completed

 

Co. Tipperary:

 

 

 

 

 

 

27/43 of 69/70

Dolla

..

..

..

..

..

..

..

..

 

 

336.15

1,080.00

1,416.15

Completed

27/56 of 69/70

Dundrum

..

..

..

..

..

..

..

..

 

 

245.37

600.00

845.37

Completed

40

Moyne

..

..

..

..

..

..

..

..

 

 

325.50

325.50

Completed

27/47 of 69/70

New Inn

..

..

..

..

..

..

..

..

 

 

1,033.55

900.00

1,933.55

Completed

57

Templemore

..

..

..

..

..

..

..

..

 

 

1,115.05

1,115.05

Completed

70

Thurles

..

..

..

..

..

..

..

..

 

 

155.27

155.27

In progress

 

Co. Westmeath:

 

 

 

 

 

 

27/91 of 69/70

Ballynacargy

..

..

..

..

..

..

..

..

 

 

181.75

700.00

881.75

In progress

27/38 of 69/70

Rathowen

..

..

..

..

..

..

..

..

 

 

209.07

300.00

509.07

Completed

 

Co. Wexford:

 

 

 

 

 

 

27/52 of 69/70

Ferns

..

..

..

..

..

..

..

..

..

 

 

2,957.50

225.00

3,182.50

Completed

34

Oulart

..

..

..

..

..

..

..

..

 

 

1,503.00

1,503.00

In progress

27/24 of 69/70

Kilmore Quay

..

..

..

..

..

..

..

 

 

1,238.00

900.00

2,138.00

Completed

Sub. No.

Co. Wicklow:

 

 

 

 

 

 

24

Rathdrum

..

..

..

..

..

..

..

..

 

 

307.50

307.50

Completed

59

Greystones

..

..

..

..

..

..

..

..

 

 

294.49

294.49

Completed

Work No.

Provision of alternative accommodation for Garda Síochána at

 

 

 

 

 

 

24

Dublin Castle

..

..

..

..

..

..

..

60,000

60,000

15,789.12

15,789.12

In progress

25

Courts of Justice: Renewal of defective stonework

..

..

60,000

25,000

18,110.36

18,355.00

36,465.36

Virtually completed

25A

Land Registry—Additional Accommodation—Stage II

..

 

 

7,400.44

261,560.58

268,961.02

Completed

 

 

 

 

287,892.87

 

 

 

 

Department of Education:

 

 

 

 

 

 

26

Athlone—New Offices

..

..

..

..

..

..

1,250,000

25,000

10,376.73

2,157.08

12,533.81

In planning

27

National Library and Museum—Renewal of stonework—Stage

 

 

 

 

 

 

 

III

..

..

..

..

..

..

..

..

..

50,000

15,000

35,550.00

1,911.55

37,461.55

In progress

28

National Schools. Grants for Building, Enlarging, Enclosing etc.

 

3,000,000

3,358,445.68

 

3,358,445.68

 

29

Dublin Preventive Centre

..

..

..

..

..

..

309,750

140,000

149,230.00

168,089.14

317,319.14

In progress

30

St. Conleth’s Reformatory, Daingean—Improvements

..

..

85,000

4,000

3,500.81

604.29

4,105.10

Under review

31

Dublin Institute for Advanced Studies—Accommodation

..

127,000

60,000

104,307.91

25,611.60

129,919.51

In progress

32

National College of Art—Additional accommodation

..

..

12,000

8,000

10,346.04

1,279.18

11,625.22

Completed

 

 

 

 

3,671,757.17

 

 

 

 

Department of Lands:

 

 

 

 

 

 

33

Castlebar—New Offices

..

..

..

..

..

..

1,650,000

35,000

13,324.50

4,527.39

17,851.89

In planning

34

Upper Merrion St. Dublin—Nos. 21-29 and 31-33—

 

 

 

 

 

 

 

Improvement of Electrical and Heating installations

..

..

..

35,000

5,000

31,150.21

3,887.59

35,037.80

In progress

34a

Land Commission—Accommodation for Management Services

 

 

 

 

 

 

 

Unit and Fire Protection Work for Computer Area

..

..

7,000

 

7,026.65

5,511.16

12,537.81

Completed

35

Shelton Abbey Forestry School—Improvement of Sewage

 

 

 

 

 

 

 

Disposal System and provision of Water Supply for Fire Fighting

11,000

1,000

426.97

426.97

In planning

 

 

 

 

51,928.33

 

 

 

 

Department of Agriculture and Fisheries:

 

 

 

 

 

 

36

Botanic Gardens—Improvement of Glasshouse Heating

..

6,000

5,000

5,534.95

42.30

5,577.25

Completed

37

Regional Veterinary and Dairy Produce Laboratories

..

..

202,500

50,000

27,657.00

124,042.63

151,699.63

Completed

38 (1)

Abbotstown Farm: Experimental Animals’ Accommodation

..

155,000

11,000

29,338.07

136,964.86

166,302.93

Completed

38 (2)

Abbotstown Farm: New Post Mortem Unit

..

..

..

28,000

20,000

11,870.66

1,553.75

13,424.41

In progress

38 (3)

Abbotstown Farm: New Laboratory Block

..

..

..

125,000

4,000

11,666.33

292.80

11,959.13

In progress

38 (4)

Abbotstown Farm: Adaptation of outbuildings to form

 

 

 

 

 

 

 

additional Laboratories

..

..

..

..

..

..

25,000

1,000

6,271.10

6,271.10

In progress

38 (5)

Abbotstown Farm: Adaptations to top floor, west block,

 

 

 

 

 

 

 

farmyard buildings

..

..

..

..

..

..

..

10,000

1,000

 

 

 

Under review

38 (6)

Abbotstown Farm: Experimental Piggery

..

..

..

21,000

1,000

 

 

 

Under review

38 (7)

Abbotstown Farm: Pig Disease etc. Research Laboratories

..

21,000

1,000

270.00

270.00

Under review

39

Backweston Farm: New Farm Buildings

..

..

..

..

52,000

1,000

2,146.93

600.00

2,746.93

In planning

40

Ballyhaise Agricultural School—Performance Testing Station

 

 

 

 

 

 

 

for Beef Bulls

..

..

..

..

..

..

..

40,000

1,000

114.60

114.60

Under consideration

40A

Ballyhaise Agricultural School—Sewerage Scheme

..

..

14,000

4,683.12

8,590.64

13,273.76

Virtually completed

41

Mellowes Agricultural College Athenry—Improvement of water

 

 

 

 

 

 

 

supply

..

..

..

..

..

..

..

..

24,000

3,000

15,840.27

15,840.27

Completed

42

Thorndale, Drumcondra—Additional Laboratory

 

 

 

 

 

 

 

accommodation

..

..

..

..

..

..

..

..

..

19,000

4,000

4,941.16

15,837.51

20,778.67

Completed

42A

Ennis Agricultural Office—Extension

..

..

..

..

5,365

 

4,590.00

4,590.00

Virtually completed

43

Construction Works at Major Fishery Harbours and Payments

 

 

 

 

 

 

 

to Fishery Harbour Centres Fund

..

..

..

..

3,500,000

500,000

201,190.93

 

 

 

 

 

 

 

Detailed as follows:

 

 

 

 

Castletownbere

..

..

..

..

..

..

..

 

 

120,711.10

305,374.93

426,086.03

In progress

 

Dunmore East

..

..

..

..

..

..

..

 

 

65,335.26

475,795.30

541,130.56

In progress

 

Galway

..

..

..

..

..

..

..

..

 

 

131.46

29,300.78

29,432.24

In progress

 

Howth

..

..

..

..

..

..

..

..

 

 

10,577.13

22,066.75

32,643.88

In progress

 

Killybegs

..

..

..

..

..

..

..

..

 

 

4,435.98

208,321.70

212,757.68

In progress

44

Works of Economic Development

..

..

..

..

700,000

160,000

141,890.41

 

 

 

 

 

 

 

Detailed as follows:

 

 

 

 

Ballyoonan Quay

..

..

..

..

..

..

..

 

 

5.09

460.27

465.36

Completed

 

Burtonport Survey

..

..

..

..

..

..

..

 

 

2,127.10

14,626.30

16,753.40

Completed

 

Howth

..

..

..

..

..

..

..

..

 

 

64,661.38

400,816.50

465,477.88

In progress

 

Killala

..

..

..

..

..

..

..

..

 

 

16,928.69

9,944.46

26,873.15

In progress

 

Kilmore Quay

..

..

..

..

..

..

..

 

 

37,084.66

17,189.50

54,274.16

In progress

 

Reen Castletownshend

..

..

..

..

..

..

 

 

7,504.88

7,633.82

15,138.70

In progress

 

Renard Point

..

..

..

..

..

..

..

 

 

1,880.61

30,887.42

32,768.03

Completed

 

Skerries

..

..

..

..

..

..

..

..

 

 

11,698.00

17,683.00

29,381.00

In progress

45

Galway Fisheries Research Station—Erection

..

..

..

200,000

1,000

1,500.00

1,500.00

Under consideration

 

 

 

 

452,165.26

 

 

 

 

Department of Labour:

 

 

 

 

 

 

46

Clifden: New Employment Exchange

..

..

..

..

11,000

10,000

7,290.00

7,290.00

In progress

 

 

 

 

7,290.00

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

47

Dublin—Amiens Street Former Sorting Office—Adaptations

..

7,000

5,000

2,788.47

802.77

3,591.24

In progress

47A

Aldboro House—New Strongroom

..

..

..

..

5,500

 

4,864.64

 

4,864.64

Completed

48

Dublin—New Warehousing etc. Accommodation

..

..

295,000

10,000

5,577.15

270,122.83

275,699.98

In progress

48A

Dublin—10 Parnell Square—Adaptations

..

..

..

 

 

4,513.22

14,070.07

18,583.29

In progress

49

Dublin—Ballyfermot—New Sorting Office

..

..

..

40,000

25,000

16,121.00

4,675.49

20,796.49

In progress

49A

Dublin—Clondalkin Pole Field Store

..

..

..

..

9,100

 

1,620.00

1,620.00

In progress

50

Dublin—Extension of Phibsboro Post Office

..

..

..

53,000

5,000

37.90

37.90

In planning

50A

Dublin—Phibsboro Postal Training Centre—Partitioning etc.

 

 

4,183.11

526.93

4,710.04

Completed

51

Cahirciveen—New Post Office

..

..

..

..

..

6,000

5,000

7,560.09

7,560.09

Virtually completed

52

Cavan—New Post Office

..

..

..

..

..

..

63,000

40,000

11,684.44

5,362.76

17,047.20

In progress

53

Claremorris—New Post Office

..

..

..

..

..

42,000

2,000

3,723.28

29,374.78

33,098.06

Completed

54

Clonmel Post Office—Extension

..

..

..

..

..

44,000

2,000

848.25

848.25

In planning

54A

Cork Head Post Office—Provision of Strongroom

..

..

5,400

 

254.82

 

254.82

In progress

55

Donegal: New Post Office

..

..

..

..

..

..

30,000

1,000

 

 

 

In planning

56

Dungarvan New Post Office

..

..

..

..

..

Not yet made

1,000

132.55

132.55

In planning

57

Killarney—Sorting Office

..

..

..

..

..

..

40,000

1,000

 

 

 

In planning

58

Listowel—New Post Office

..

..

..

..

..

..

Not yet made

1,000

50.16

50.16

In planning

59

Longford—New Post Office

..

..

..

..

..

Not yet made

5,000

 

 

 

In planning

60

Mullingar—New Post Office

..

..

..

..

..

50,000

2,000

658.20

658.20

In planning

61

Nenagh Post Office

..

..

..

..

..

..

..

54,000

6,000

1,281.15

812.30

2,093.45

In planning

62

Portlaoise—New Post Office

..

..

..

..

..

60,000

26,000

13,854.86

1,112.55

14,967.41

In progress

 

 

 

 

79,753.29

 

 

 

 

Department of Defence:

 

 

 

 

 

 

63A

Arbour Hill, Dublin, 1916 Memorial—Improvements

..

..

 

 

1,036.65

3,952.00

4,988.65

Completed

 

 

 

 

1,036.65

 

 

 

 

Department of Foreign Affairs:

 

 

 

 

 

 

62A

New York Consulate General—New Accommodation and

 

 

 

 

 

 

 

Adaptations

..

..

..

..

..

..

..

 

 

12,948.28

19,677.35

32,625.63

Completed

62B

Copenhagen—New Embassy Residence—Adaptations and

 

 

 

 

 

 

 

Furniture

..

..

..

..

..

..

..

..

 

 

1,585.22

7,860.67

9,445.89

Completed

 

 

 

 

14,533.50

 

 

 

 

Department of Social Welfare:

 

 

 

 

 

 

63

Dundrum, Co. Dublin—New Social Welfare Office

..

..

2,500

2,000

1,400.00

102.48

1,502.48

Virtually completed

 

 

 

 

1,400.00

 

 

 

 

General:

 

 

 

 

 

 

64

Minor New Works not exceeding £5,000 each

..

..

..

 

40,000

99,671.88

 

99,671.88

 

65

Urgent and Unforeseen Works

..

..

..

..

..

 

5,000

765.00

 

765.00

 

66

Balances of Expenditure on works of prior years which might not

 

 

 

 

 

 

 

have been completed on 1st April 1970

..

..

..

 

45,000

40,924.44

 

40,924.44

 

 

 

 

£5,004,000

£5,144,269.62

 

 

 

DETAILS OF MINOR NEW WORKS (E No. 64).

 

 

 

 

Expenditure

 

Work No.

Service and Description

Total Estimate

Vote 1970/71

1970/71

to 31/3/70

to 31/3/71

Observations

 

 

£

£

£

£

£

 

 

President’s Establishment:

 

 

 

 

 

 

80/120

Áras an Uachtaráin: Improvement to Boundaries

..

..

 

 

368.50

417.05

785.55

Completed

of 69/70

 

 

 

 

 

 

 

46

Aras an Uachtaráin Gardens: Provision of Cold Frames

..

 

 

549.00

549.00

Completed

94

Aras an Uachtaráin: Provision of waiting room

..

..

 

 

495.00

495.00

In progress

47

City Gate Lodge: Provision of toilet etc. facilities

..

..

 

 

270.00

270.00

Completed

80/49

East Gate Lodge: Improvements

..

..

..

..

..

 

 

160.37

2,781.73

2,942.10

Complet

of 69/70

 

 

 

 

 

 

 

80/50

West Gate Lodge: Improvements

..

..

..

..

 

 

93.37

2,846.80

2,940.17

Completed

of 69/70

 

 

 

 

 

 

 

 

Oireachtas:

 

 

 

 

 

 

80/86

Leinster House: Improvement of Toilet Facilities

..

..

 

 

91.05

1,175.55

1,266.60

Completed

of 69/70

 

 

 

 

 

 

 

80/126

Leinster House: Distinguished Strangers’ Gallery

..

..

 

 

366.63

120.97

487.60

Completed

of 69/70

 

 

 

 

 

 

 

80/168

Leinster House: Additional sanitary facilities (Room 10)

..

 

 

27.60

90.55

118.15

Completed

of 69/70

 

 

 

 

 

 

 

72

Leinster House: Annunciator System, C.C. Television

..

..

 

 

3,935.54

3,935.54

Completed

 

An Taoiseach:

 

 

 

 

 

 

80/66

Census of Population (Griffith Bks.)—Additional Storage

 

 

 

 

 

 

of 69/70

Accommodation

..

..

..

..

..

..

..

 

 

4.20

417.89

422.09

Completed

77

Do. Improvements

..

..

..

..

..

 

 

254.89

254.89

In progress

59

St. Patricks Hall, Dublin Castle. R.H.A. Exhibition (1970)

..

 

 

1,926.14

1,926.14

Completed

91

Government Buildings—Provision of Acoustical Panels

..

 

 

151.38

151.38

In progress

 

Department of Finance:

 

 

 

 

 

 

65

Revenue Commissioners, 26 Harcourt St.

..

..

..

 

 

2,129.31

2,129.31

In progress

81/104

Stamping Branch Dublin Castle: Site Clearance

..

..

 

 

18.54

365.52

384.06

Completed

of 68/69

 

 

 

 

 

 

 

76

Lansdowne House: Improvements

..

..

..

..

 

 

596.82

596.82

In progress

52

72/76 St. Stephen’s Green—Soundproofing of Committee Room

 

 

847.25

847.25

Completed

80/62

Athlone Government Offices—Accommodation

..

..

..

 

 

524.17

729.90

1,254.07

Completed

of 69/70

 

 

 

 

 

 

 

53

Bantry Customs & Excise

..

..

..

..

..

..

 

 

704.16

704.16

Completed

83/84

Cork Government Offices—Improvements

..

..

..

 

 

473.25

2,030.79

2,504.04

Completed

of 67/68

 

 

 

 

 

 

 

81/107

Customs and Excise (Irish Life House) Cork

..

..

..

 

 

74.13

303.87

378.00

Completed

of 68/69

 

 

 

 

 

 

 

80/160

Custom House Cork, Revenue—Accommodation

..

..

 

 

1,331.18

460.38

1,791.56

Completed

of 69/70

 

 

 

 

 

 

 

70

Dundalk Customs & Excise Office

..

..

..

..

 

 

1,891.50

1,891.50

In progress

71

Kilkenny Revenue Office

..

..

..

..

..

..

 

 

1,383.11

1,383.11

Completed

48

Lifford Customs and Excise Office

..

..

..

..

 

 

296.13

296.13

Completed

80/147

Thurles Income Tax Office—Improvements

..

..

..

 

 

421.95

244.00

665.95

Completed

of 69/70

 

 

 

 

 

 

 

98

Chief State Solicitor’s Office, Dublin Castle

..

..

..

 

 

1,074.65

1,074.65

In progress

80/82

Office of Public Works, 51 St. Stepehn’s Green—Adaptations

 

 

266.73

172.84

439.57

Completed

of 69/70

 

 

 

 

 

 

 

57

51 St. Stephen’s Green—Alterations, Engineers Branch

..

 

 

4,261.14

4,261.14

Virtually completed

80/25

Divisional Office, Old Blackrock Road, Cork—Improvements

 

 

580.07

9.88

589.95

Completed

of 69/70

 

 

 

 

 

 

 

80/182

Kilkenny National Monuments Depot—Improvements

..

 

 

113.63

66.00

179.63

Completed

of 69/70

 

 

 

 

 

 

 

83

Archaeological Survey Field H.Q’s. Mullingar

..

..

..

 

 

1,125.00

1,125.00

In progress

116

Rock of Cashel, Caretaker’s Cottage—Extension and

 

 

 

 

 

 

 

Improvements

..

..

..

..

..

..

..

..

 

 

630.00

630.00

In progress

 

Parks:

 

 

 

 

 

 

29

Phoenix Park—Provision of Gateman’s Hut

..

..

..

 

 

1,198.00

1,198.00

In progress

97

Bourn Vincent Memorial Park. Improvements to Drumrower Rd.

 

 

3,320.00

3,320.00

In progress

51

Arbour Hill Memorial Plot—Lighting

..

..

..

..

 

 

219.02

219.02

In progress

 

Shannon Navigation:

 

 

 

 

 

 

80/105

New Quay at Rooskey

..

..

..

..

..

..

 

 

45.63

1,506.00

1,551.63

Completed

of 69/70

 

 

 

 

 

 

 

82

New Quay at Battlebridge

..

..

..

..

..

..

 

 

1,643.07

1,643.07

In progress

81

New Quay at Lanesboro

..

..

..

..

..

..

 

 

314.63

314.63

In progress

 

Stationery Office:

 

 

 

 

 

 

80/91

Beggar’s Bush—Provision of Toilet Facilities (Block F)

..

 

 

81.97

785.64

867.61

Completed

of 69/70

 

 

 

 

 

 

 

81/97

Beggar’s Bush—Improvements

..

..

..

..

..

 

 

358.10

501.39

859.49

Completed

of 68/69

 

 

 

 

 

 

 

80/113

Beggar’s Bush—Provision of Toilet Facilities (Block D Rm. 6)

..

 

 

39.97

287.70

327.67

Completed

83/65

Valuation Office 5/6 Ely Place: Improvements

..

..

..

 

 

4.00

420.56

424.56

Completed

of 67/68

 

 

 

 

 

 

 

81/56

Valuation Office 5/6 Ely Place: Improvements

..

..

..

 

 

2.21

1,174.64

1,176.85

Completed

of 68/69

 

 

 

 

 

 

 

80/65

Ordnance Survey Office—Provision of toilets etc.

..

..

 

 

7.77

523.02

530.79

Completed

of 69/70

 

 

 

 

 

 

 

80/149

Ordnance Survey Office—Provision of new general stores office

 

 

2.60

9.64

12.24

In progress

of 69/70

 

 

 

 

 

 

 

 

Unappropriated General:

 

 

 

 

 

 

80/153

Law Library Four Courts—Improvement of lighting

..

..

 

 

781.85

679.84

1,461.69

Completed

of 69/70

 

 

 

 

 

 

 

80/80

R.D.S. Grounds, Ballsbridge—Scientific and Technical

 

 

 

 

 

 

of 69/70

Exhibition

..

..

..

..

..

..

..

..

..

 

 

238.49

1,356.36

1,594.85

Completed

 

Department of Justice:

 

 

 

 

 

 

80/144

Land Registry—Adaptations

..

..

..

..

..

 

 

616.10

295.53

911.63

Completed

of 69/70

 

 

 

 

 

 

 

74

Land Registry—Alterations etc.

..

..

..

..

..

 

 

2,728.40

2,728.40

In progress

80/158

State Paper Office—Accommodation in basement of State

 

 

 

 

 

 

of 69/70

Apartments

..

..

..

..

..

..

..

..

 

 

117.08

803.80

920.88

Completed

 

Department of Local Government:

 

 

 

 

 

 

24

Parkgate Hall—Tarmacadam

..

..

..

..

..

 

 

530.00

530.00

Completed

63

Custom House—Sub-division of rooms

..

..

..

..

 

 

197.98

197.98

In progress

88

Custom House—Additional Accommodation

..

..

..

 

 

283.26

283.26

Under review

 

Department of Education:

 

 

 

 

 

 

80/76

Talbot House—Provision of Interview Room

..

..

..

 

 

30.45

72.97

103.42

Completed

of 69/70

 

 

 

 

 

 

 

80/94

Tyrone House—Accommodation for Parliamentary Secretary

 

 

87.28

631.85

719.13

Completed

of 69/70

 

 

 

 

 

 

 

93

Training College Building, Marlboro St.

..

..

..

..

 

 

183.60

183.60

In progress

87

Hawkins House, Enlargement of Strongroom, Provision of

 

 

 

 

 

 

 

reception and registry

..

..

..

..

..

..

..

 

 

679.67

679.67

Completed

80/140

Language Institute, 31 Fitzwilliam Square—Adaptations

..

 

 

5,152.55

238.18

5,390.73

Completed

of 69/70

 

 

 

 

 

 

 

80/81

National Museum—Adaptations

..

..

..

..

..

 

 

24.08

18.82

42.90

Completed

of 69/70

 

 

 

 

 

 

 

80/174

National Museum—Provision of Humidifiers

..

..

..

 

 

150.68

1,932.50

2,083.18

In progress

of 69/70

 

 

 

 

 

 

 

83/69

Folk Museum—Royal Hospital, Kilmainham—Improvements

 

 

421.75

512.71

934.46

Completed

of 67/68

 

 

 

 

 

 

 

80/180

Limerick Model School—Improvements

..

..

..

 

 

1,439.58

2,032.75

3,472.33

In progress

of 69/70

 

 

 

 

 

 

 

81/42

Cork Model School—Sanitary and Heating Improvements

..

 

 

165.00

828.76

993.76

Completed

of 68/69

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

80/183

Cavan—Improvement to New Offices, 87 Main Street

..

..

 

 

41.05

58.04

99.09

Completed

of 69/70

 

 

 

 

 

 

 

80/127

Cork Land Commission Office—Improvements

..

..

 

 

307.51

1.40

308.91

In progress

of 69/70

 

 

 

 

 

 

 

80/84

Bray—Adaptations

..

..

..

..

..

..

..

 

 

320.00

1,433.07

1,753.07

Completed

of 69/70

 

 

 

 

 

 

 

95

Shelton Abbey—Forestry Fire Protection Works

..

..

 

 

2,319.79

2,319.79

In progress

 

Department of Agriculture and Fisheries:

 

 

 

 

 

 

22

14/17 Upper Merrion St.

..

..

..

..

..

..

 

 

595.03

595.03

Completed

81/94

National Dairy Publicity Council, 121 Lr. Baggot Street—

 

 

 

 

 

 

of 68/69

Accommodation

..

..

..

..

..

..

..

 

 

23.00

458.67

481.67

Completed

66

O’Connell Bridge House

..

..

..

..

..

..

 

 

890.50

890.50

Completed

13

Ennis District Veterinary Office

..

..

..

..

..

 

 

636.60

636.60

In progress

39

Mullingar Veterinary Office

..

..

..

..

..

 

 

1,299.43

1,299.43

In progress

60

Bridgend Egg Inspection Hut

..

..

..

..

..

 

 

737.73

737.73

Completed

80/117

Abbotstown Farm—Provision of Snail House

..

..

..

 

 

315.05

35.82

350.87

Completed

of 69/70

 

 

 

 

 

 

 

80/54

Abbotstown Farm—Well boring

..

..

..

..

..

 

 

226.50

864.10

1,090.60

Completed

of 69/70

 

 

 

 

 

 

 

61

Abbotstown Farm—Veterinary Field Station

..

..

..

 

 

107.40

107.40

In progress

55

Abbotstown Farm:Provision of Chicken Hut

..

..

..

 

 

980.50

980.50

In progress

80/36

Abbotstown Farm—Improvements to Cattle Court

..

..

 

 

12.29

1,235.59

1,247.88

Completed

of 69/70

 

 

 

 

 

 

 

68

Abbotstown Farm: Fitting Entrance Gates

..

..

..

 

 

1,777.58

1,777.58

In progress

80/161

Ballsbridge Vet. College—Improvements to Ventilation in

 

 

 

 

 

 

of 69/70

Lecture Theatre

..

..

..

..

..

..

..

 

 

1,994.08

160.95

2,155.03

Completed

83/105 of 67/68

Ballsbridge Vet. College—Adaptations

..

..

..

..

 

 

9.21

1,808.65

1,817.86

Completed

80/45

Ballsbridge Vet. College—Improvements to small animals

 

 

 

 

 

 

of 69/70

operating theatre

..

..

..

..

..

..

..

 

 

9.47

1,479.13

1,488.60

In progress

80/33

Ballsbridge Vet. College—Adaptations to lecture room and

 

 

 

 

 

 

of 69/70

laboratory

..

..

..

..

..

..

..

 

 

2.64

1,594.22

1,596.86

Completed

80/112 of 69/70

Botanic Gardens—Heating in Alpine House

..

..

..

 

 

18.19

32.14

50.33

Completed

80/109 of 69/70

Ballyhaise Agricultural School—Improvements at No. 1 Cottage

 

 

754.78

450.00

1,204.78

Completed

80/133 of 69/70

Ballyhaise Agricultural School—Water Supply to Residences

..

 

 

CR. 430.00

430.00

In progress

80/69 of 69/70

Ballyhaise Agricultural School—Provision of grain dryer

..

 

 

681.50

672.46

1,353.96

Completed

38

Clonakilty Agricultural School—Provision of Grain Dryer

..

 

 

1,268.00

1,268.00

In progress

80/99 of 69/70

Munster Institute—Provision of Partitions in Pig Progeny Station

 

 

2,114.11

328.69

2,442.80

In progress

19

Munster Institute—Improvements

..

..

..

..

 

 

945.00

945.00

In progress

69

Munster Institute—Alterations

..

..

..

..

..

 

 

900.00

900.00

In progress

27

Thorndale Laboratory—Petrol Storage Tank

..

..

..

 

 

651.22

651.22

In progress

80/110 of 69/70

Thorndale Laboratory—Adaptations

..

..

..

..

 

 

24.87

151.96

176.83

Completed

26

Fisheries, 3 Cathal Brugha St.—Gas Central Heating System

..

 

 

958.13

958.13

In progress

100

Fisheries, 3 Cathal Brugha St.—Adaptations

..

..

..

 

 

374.20

374.20

In progress

80/106 of 69/70

Butter Testing Station—Electrical adaptations

..

..

..

 

 

29.15

86.83

115.98

Completed

 

Department of Transport and Power:

 

 

 

 

 

 

80/77 of 69/70

Malin Head Wireless Station—Improvements

..

..

..

 

 

552.00

1,710.00

2,262.00

Completed

64

Eden Quay-Mercantile Marine Office

..

..

..

..

 

 

357.57

357.57

In progress

 

Department of Industry and Commerce:

 

 

 

 

 

 

80/157

Companies Registration Office, 13/14 Earlsfort Tce.—

 

 

 

 

 

 

of 69/70

Accommodation

..

..

..

..

..

..

..

..

 

 

2,764.58

1,784.14

4,548.72

Completed

80/32 of 69/70

Head Office, Kildare St.—New Waiting Room

..

..

..

 

 

31.19

865.70

896.89

Completed

80/148

Griffith Barracks—Provision of accommodation for An Coimis-

 

 

 

 

 

 

of 69/70

iún Dumpála

..

..

..

..

..

..

..

 

 

103.71

2.48

106.19

Completed

81/92 of 68/69

Patents Office—Griffith Barracks—Additions

..

..

..

 

 

77.15

514.40

591.55

Completed

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

41

G.P.O.—Improvements to Water Supply

..

..

..

 

 

1,394.00

1,394.00

In progress

56

G.P.O.—Formation of Pay Room

..

..

..

..

 

 

575.38

575.38

In progress

80/130 of 69/70

Leitrim House—Demolition of sheds

..

..

..

..

 

 

8.23

471.00

479.23

Completed

80/89 of 69/70

Distillery Rd., Garage—Improvements

..

..

..

..

 

 

28.34

115.30

143.64

Completed

67

Dunlaoghaire P.O.—Extension of Sorting Office

..

..

 

 

1,972.95

1,972.95

In progress

99

Sherriff St., Central Sorting Office—Enclosure for Oil Tank

..

 

 

3,600.00

3,600.00

Completed

80/143 of 69/70

10/12 Trinity St.—Adaptations etc.

..

..

..

..

 

 

96.11

305.17

401.28

Completed

80/114 of 69/70

Cork Post Office—Improvements to dining club

..

..

 

 

65.47

4.13

69.60

Completed

81/61 of 68/69

Cork Head Post Office—Improvements

..

..

..

..

 

 

27.92

1,731.85

1,759.77

Completed

20

Gorey Post Office—Improvements

..

..

..

..

 

 

2,385.00

2,385.00

In progress

81/24 of 68/69

Kinsale Post Office—Improvements

..

..

..

..

 

 

1,896.00

2,011.85

3,907.85

Completed

120

Monaghan Post Office—Provision of Canteen

..

..

..

 

 

990.00

990.00

In progress

80/44 of 69/70

Thurles Post Office—Garage Accommodation

..

..

..

 

 

1,264.18

180.00

1,444.18

Completed

43

Tipperary Post Office—Improvements

..

..

..

..

 

 

572.20

572.20

Completed

83/12 of 67/68

Tuam Post Office—Improvements

..

..

..

..

 

 

100.00

1,612.56

1,712.56

Completed

64/39 of 66/67

Westport Post Office—Improvements

..

..

..

..

 

 

164.00

2,114.98

2,278.98

Completed

25

Amiens St. Parcel Office—Improvements

..

..

..

 

 

499.32

499.32

In progress

 

Department of Defence:

 

 

 

 

 

 

80/103 of 69/70

Parkgate St.—Adaptations

..

..

..

..

..

..

 

 

68.49

2,458.93

2,527.42

Completed

81/103 of 68/69

Parkgate St.—Library Improvements

..

..

..

..

 

 

25.37

2,587.75

2,613.12

Completed

80/83 of 69/70

Coláiste Caoimhín—Adaptations

..

..

..

..

..

 

 

302.03

638.80

940.83

In progress

33

Coláiste Caoimhín—Improvements to Heating

..

..

..

 

 

2,296.92

2,296.92

Completed

86

Parkgate St.—Adaptations

..

..

..

..

..

..

 

 

173.93

173.93

In progress

32

Parkgate St.—Central Heating in Red House

..

..

..

 

 

1,257.05

1,257.05

In progress

 

Department of foreign Affairs:

 

 

 

 

 

 

84

Iveagh House—Adaptations

..

..

..

..

..

 

 

929.87

 

929.87

In progress

 

Department of Labour:

 

 

 

 

 

 

 

Employment Exchanges

 

 

 

 

 

 

31

Athlone—Office for Placement Section

..

..

..

..

 

 

695.00

695.00

In progress

11

Cork—Improvements

..

..

..

..

..

..

 

 

333.82

333.82

In progress

44

Drogheda—Electrical Works

..

..

..

..

..

 

 

672.50

672.50

Completed

54

Gardiner St.—Improvements in Security

..

..

..

..

 

 

1,168.00

1,168.00

In progress

18

Tralee—Alterations

..

..

..

..

..

..

 

 

1,080.00

1,080.00

In progress

50

Werburgh St.—Improvements in Heating

..

..

..

 

 

208.73

208.73

In progress

78

Ansley House—Adaptations

..

..

..

..

..

 

 

663.60

663.60

In progress

 

Department of Health:

 

 

 

 

 

 

80/115 of 69/70

Custom House—Adaptations to Public Office

..

..

..

 

 

10.81

264.39

275.20

Completed

80/138 of 69/70

Central Mental Hospital Dundrum—Improvements

..

..

 

 

206.07

173.10

379.17

Completed

45

Central Mental Hospital Security Improvements

..

..

 

 

242.00

242.00

Completed

80/151

Central Mental Hospital Gate Lodge—Provision of prefabricated

 

 

 

 

 

 

of 69/70

extension

..

..

..

..

..

..

..

..

 

 

406.35

1,200.00

1,606.35

Completed

80/92 of 69/70

Custom House—Improvement to lighting

..

..

..

 

 

10.37

477.48

487.85

Completed

DETAILS OF URGENT AND UNFORESEEN WORKS (E No. 65).

 

 

 

 

Expenditure

 

Work No.

Service and Description

Total Estimate

Vote 1970-71

1970-71

to 31/3/70

to 31/3/71

Observations

 

 

£

£

£

£

£

 

 

Department of Finance:

 

 

 

 

 

 

1

Lifford Frontier Post—Temporary Office

..

..

..

 

 

765.00

765.00

Completed

DETAILS OF URGENT AND UNFORESEEN WORKS (E No. 65).

 

 

 

 

Expenditure

 

Work No.

Service and Description

Total Estimate

Vote 1970/71

1970/71

to 31/3/70

to 31/3/71

Observations

 

 

£

£

£

£

£

 

 

Department of an Taoiseach:

 

 

 

 

 

 

2A

Government Buildings, North Block—Improvements to

 

 

 

 

 

 

of 68/69

Taoiseach’s Accommodation

..

..

..

..

..

..

 

 

42.37

2,512.88

2,555.25

Completed

4 of 64/65

Statistics—St. Stepehen’s Green House

..

..

..

..

 

 

3,500.00

39,934.55

43,434.55

Completed

 

Department of Finance:

 

 

 

 

 

 

3A of 68/69

72/76 St. Stepehn’s Green—Additional Accommodation

..

 

 

463.52

66,909.53

67,373.05

Completed

10B of 68/69

18 Lansdowne Rd.—Adaptations

..

..

..

..

..

 

 

21.13

2,834.61

2,855.74

Completed

4 of 69/70

St Martins House—Additional Accommodation

..

..

 

 

379.47

14,108.22

14,487.69

Completed

 

Revenue Commissioners

 

 

 

 

 

 

8 of 69/70

Blacklion Customs Frontier Post

..

..

..

..

..

 

 

55.75

4,320.00

4,375.75

Completed

14 of 68/69

Carlow Government Office

..

..

..

..

..

 

 

9.65

39,776.98

39,786.63

Completed

15 of 68/69

Cork—Additional Accommodation

..

..

..

..

 

 

31.53

12,453.10

12,484.63

Completed

7 of 68/69

Drumbilla Frontier Post

..

..

..

..

..

..

 

 

1,010.89

3,899.53

4,910.42

Completed

8 of 66/67

Dundalk—New Customs Road Station

..

..

..

..

 

 

4,120.13

27,320.87

31,441.00

Completed

9 of 67/68

Revenue Commissioners—New Customs Frontier Posts

..

 

 

400.64

11,034.05

11,434.69

Completed

16 of 69/70

Waterford Government Offices

..

..

..

..

..

 

 

355.90

381.36

737.26

In planning

11A

Civil Service Commission, 45 Upper O’Connell St.—

 

 

 

 

 

 

of 68/69

Improvements

..

..

..

..

..

..

..

..

 

 

1,300.68

8,422.50

9,723.18

Completed

11B of 68/69

Civil Service Commission, 10 Parnell Square—Adaptations

..

 

 

1,734.48

17,453.17

19,187.65

Completed

4A of 69/70

Civil Service Dining Club

..

..

..

..

..

..

 

 

1,445.00

18,975.00

20,420.00

Completed

20/5 of 69/70

Bourn Vincent Memorial Park—Provision of visitors’ centre

..

 

 

114.18

9.00

123.18

In planning

17/1 of 69/70

Garden of Remembrance—Architectural Works

..

..

 

 

800.00

180,490.37

181,290.37

Completed

8 of 67/68

Dublin Castle—Rebuilding of Cross Block

..

..

..

 

 

189.19

145,671.24

145,860.43

Completed

23 of 67/68

Wolfe Tone Memorial—Dublin

..

..

..

..

..

 

 

930.00

14,734.31

15,664.31

Completed

 

Department of Justice:

 

 

 

 

 

 

26A of 68/69

Department of Justice 72/76 St. Stephen’s Green

..

..

 

 

277.53

51,045.32

51,322.85

Completed

33A of 68/69

High Courts—Improved Accommodation

..

..

..

 

 

9.93

2,664.50

2,674.43

Completed

29,1 of 64/65

Land Registry—Additional accommodation (Stage 1)

..

..

 

 

472.83

22,828.01

23,300.84

Completed

28

Garda Depot—Extension of Garage and Workshop

 

 

 

 

 

 

of 68/69

Accommodation

..

..

..

..

..

..

..

..

 

 

37.75

76,809.08

76,846.83

Completed

 

Department of Education:

 

 

 

 

 

 

36

Department of Education—Additional Accommodation,

 

 

 

 

 

 

of 68/69

Marlboro St.

..

..

..

..

..

..

..

..

 

 

1,285.94

22,730.01

24,015.95

Completed

37 of 69/70

National Gallery—Extension

..

..

..

..

..

 

 

5,119.84

443,606.52

448,726.36

Completed

 

Department of Lands:

 

 

 

 

 

 

38 of 69/70

St. Martin’s House—Additional Accommodation

..

..

 

 

453.17

6,531.91

6,985.08

Completed

44B of 68/69

24 Upper Merrion St.—Adaptations

..

..

..

..

 

 

51.74

5,150.53

5,202.27

Completed

 

Department of Agriculture and Fisheries:

 

 

 

 

 

 

43 of 69/70

St. Martin’s House—Additional Accommodation

..

..

 

 

880.91

3,550.56

4,431.47

Completed

47 of 67/68

Ansley House—Additional Accommodation

..

..

..

 

 

12.65

7,219.33

7,231.98

Completed

43A of 69/70

Cavan District Veterinary Office—Adaptations

..

..

..

 

 

2,380.08

4,770.00

7,150.08

Completed

50/3 of 68/69

Abbotstown Farm Foundation Stock Farmyard

..

..

 

 

973.60

89,941.08

90,914.68

Completed

39/4 of 66/67

Abbotstown Farm—Veterinary Field Station

..

..

..

 

 

119.99

185,322.13

185,442.12

Completed

55/3

Mellowes Agricultural College Athenry—Erection of Employees’

 

 

 

 

 

 

of 68/69

Cottages

..

..

..

..

..

..

..

..

 

 

699.57

4,709.35

5,408.92

Completed

53A (2) of 67/68

Backweston Farm—New Laboratories

..

..

..

..

 

 

191.35

1,557.21

1,748.56

Completed

47/2

Backweston Farm—Temperature and Light Control

 

 

 

 

 

 

of 69/70

Installations in Glasshouses

..

..

..

..

..

..

 

 

307.50

3,321.05

3,628.55

Completed

53/3 of 65/66

Botanic Gardens—Classroom Laboratory Accommodation

..

 

 

5.63

6,627.77

6,633.40

Completed

49

Botanic Gardens—Accommodation for a Herbarium and

 

 

 

 

 

 

of 67/68

Botanical collection

..

..

..

..

..

..

 

 

170.33

5,573.27

5,743.60

Completed

47

Ballsbridge Veterinary College New Radiography Unit and

 

 

 

 

 

 

of 68/69

Extension of Operating Theatre

..

..

..

..

 

 

1,000.23

23,382.62

24,382.85

Completed

54 of 67/68

Clonakilty Agricultural School—New Building

..

..

..

 

 

677.33

123,986.00

124,663.33

Completed

51 of 69/70

Munster Institute—New Laboratories

..

..

..

..

 

 

1,416.22

23,151.67

24,567.89

Completed

49 of 69/70

John F. Kennedy Memorial Park School of Horticulture etc.

 

 

32.56

30,710.83

30,743.39

In progress

48A

Ballyhaise Agricultural School Conversion of Haysheds to Silo

 

 

 

 

 

 

of 69/70

Pits

..

..

..

..

..

..

..

..

..

 

 

604.70

3,135.00

3,739.70

Completed

 

Department of Industry and Commerce:

 

 

 

 

 

 

63 of 68/69

I.D.A. Lansdowne House—Additional Accommodation

..

 

 

148.09

53,808.55

53,956.64

Completed

 

Department of Transport and Power:

 

 

 

 

 

 

58 of 69/70

Valentia Observatory—Improvement of Access

..

..

..

 

 

843.66

3,825.00

4,668.66

Completed

 

Department of Labour:

 

 

 

 

 

 

63 of 67/68

Ansley House

..

..

..

..

..

..

..

 

 

1,215.63

69,112.73

70,328.36

Completed

 

Department of posts and Telegraphs:

 

 

 

 

 

 

59 of 69/70

Dublin G.P.O.—Dining Club, Improvements

..

..

..

 

 

1,048.04

9,523.04

10,571.08

Completed

60 of 69/70

Dublin, New Central Sorting Office

..

..

..

..

 

 

1,777.53

908,908.92

910,686.45

Completed

72 of 68/69

Carlow New Post Office

..

..

..

..

..

..

 

 

102.94

75,213.25

75,316.19

Completed

68 of 69/70

Cork Post Office—Provision of Strong Room

..

..

..

 

 

83.85

45.00

128.85

In progress

65 of 64/65

Ennis Post Office—Improvements and new Telephone Exchange

 

 

46.00

11,074.15

11,120.15

Completed

75

Enniscorthy Post Office—Improvements to Sorting and Public

 

 

 

 

 

 

of 68/69

Offices

..

..

..

..

..

..

..

..

 

 

1,338.72

7,220.00

8,558.72

Completed

72 of 69/70

Macroom New Post Office

..

..

..

..

..

..

 

 

12.54

15,397.94

15,410.48

Completed

74 of 69/70

Waterford Post Office—Extension

..

..

..

..

 

 

178.00

191.00

369.00

In planning

 

Department of social Welfare:

 

 

 

 

 

 

79 of 69/70

Listowel Social Welfare Office

..

..

..

..

..

 

 

43.55

2,788.70

2,832.25

Completed