Committee Reports::Report - Appropriation Accounts 1967 - 1968::23 July, 1969::Appendix

APPENDIX 8.

ARTERIAL DRAINAGE—CONSTRUCTION WORKS

Catchment Drainage Scheme

Original Estimate

Basic Labour Rate 30/11/68

Estimated Cost to Completion 30/11/68

Estimated Percentage Labour Content

Estimated Percentage Work Done

Estimated Materials Content

Estimated increase in price of materials

Date

Amount

Basic Labour Rate per hour

 

 

£

s.d.

s.d.

£

 

 

 

 

Inny

..

..

..

1960

1,840,000

2/5

4/8½

2,500,000

47%

100%

21%

25%

Deel

..

..

..

July 1962

920,000

2/11

4/8½

920,000

49%

100%

20%

20%

Killimor/Cappagh

..

April 1962

800,000

2/8½

4/8½

960,000

51%

100%

22%

20%

Corrib/Headford

..

1965

935,000

3/6¾

4/8½

1,075,000

50%

25%

21%

12½%

Moy

..

..

..

1960

3,260,000

2/5

4/8½

5,250,000

50%

90%

25%

25%