Qn. 177.
APPENDIX 4.
STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1966-67 (VOTE 8, SUBHEAD E).
Work No. |
Service and Description |
Total Estimate |
Vote 1966-67 |
Expenditure |
Observations |
1966-67 |
To 31/3/66 |
To 31/3/67 |
|
|
£ |
£ |
£ |
s. |
d. |
£ |
s. |
d. |
£ |
s. |
d. |
|
|
Oireachtas: |
|
|
|
|
|
|
|
|
|
|
|
|
1 |
Leinster House—Extension and Alterations |
660,000 |
150,000 |
148,678 |
7 |
5 |
465,570 |
12 |
3 |
614,248 |
19 |
8 |
Mainly completed |
|
Total: |
|
|
150,000 |
148,678 |
7 |
5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
Department of An Taoiseach: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Dublin Castle—State Apartments—Rebuilding of Drawing Room, |
|
|
|
|
|
|
|
|
|
|
|
|
|
Bedroom Block and main entrance. |
... |
... |
... |
375,000 |
165,000 |
82,289 |
13 |
11 |
196,660 |
3 |
7 |
278,949 |
17 |
6 |
In progress |
3 |
Central Statistics Office—Census of Population—Adaptations and |
|
|
|
|
|
|
|
|
|
|
|
|
|
Furnishing |
... |
... |
... |
... |
... |
... |
... |
... |
5,500 |
5,500 |
5,360 |
3 |
2 |
1 |
0 |
0 |
5,361 |
3 |
2 |
Completed |
|
Total: |
|
|
170,500 |
87,649 |
17 |
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Finance: |
|
|
|
|
|
|
|
|
|
|
|
|
4 |
Additional Accommodation (Dublin) |
... |
... |
... |
... |
... |
|
10,000 |
— |
|
|
|
|
|
|
Tenders under consideration. |
4a |
Additional Accommodation—O’Connell Bridge House, Dublin |
... |
4,500 |
— |
1,059 |
13 |
1 |
4,519 |
3 |
9 |
5,578 |
16 |
10 |
Completed. |
5 |
State Buildings—Kildare St. Merrion St.—New Electricity |
|
|
|
|
|
|
|
|
|
|
|
|
|
Distribution System |
... |
... |
... |
... |
... |
... |
... |
27,000 |
20,000 |
420 |
4 |
7 |
1,247 |
1 |
7 |
1,667 |
6 |
2 |
In planning. |
5a |
Central Heating Station—Renewal of plant |
... |
... |
... |
... |
63,000 |
— |
3,262 |
0 |
0 |
62,246 |
8 |
11 |
65,508 |
8 |
11 |
Completed. |
6 |
Revenue Commissioners—Dublin Castle—Stamping Branch, New |
|
|
|
|
|
|
|
|
|
|
|
|
|
Premises |
... |
... |
... |
... |
... |
... |
... |
... |
770,000 |
7,000 |
84 |
9 |
9 |
23,774 |
7 |
11 |
23,858 |
17 |
8 |
Planning completed. |
6a |
— |
do |
— |
Liberty Hall |
1,800 |
|
833 |
4 |
10 |
— |
833 |
4 |
10 |
Completed. |
7 |
Revenue Commissioners—New Customs Frontier Posts |
... |
... |
14,000 |
4,000 |
1,337 |
12 |
0 |
8,557 |
17 |
5 |
9,895 |
9 |
5 |
Partially completed. |
8 |
Revenue Commissioners—Dundalk—New Customs Road Station |
... |
27,500 |
2,000 |
1,814 |
4 |
0 |
24,743 |
16 |
9 |
26,558 |
0 |
9 |
Completed. |
9 |
Carlow New Government Offices |
... |
... |
... |
... |
... |
42,000 |
15,000 |
11,064 |
3 |
0 |
— |
11,064 |
3 |
0 |
In progress. |
10 |
Wexford New Government Offices & Telephone Exchange |
... |
49,500 |
2,250 |
245 |
5 |
11 |
50,147 |
13 |
2 |
50,392 |
19 |
1 |
Completed. |
|
Office of Public Works: |
|
|
|
|
|
|
|
|
|
|
|
|
11 |
Alterations |
... |
... |
... |
... |
... |
... |
... |
... |
20,000 |
1,500 |
3,515 |
10 |
7 |
7,162 |
9 |
10 |
10,678 |
0 |
5 |
Partially completed. |
11a |
10 Hume Street—National Monuments |
... |
... |
... |
... |
2,400 |
— |
1,738 |
12 |
4 |
900 |
0 |
0 |
2,638 |
12 |
4 |
Completed. |
12 |
Statue to Thomas Davis |
... |
... |
... |
... |
... |
... |
... |
15,000 |
1,500 |
3,727 |
12 |
8 |
15,736 |
19 |
8 |
19,464 |
12 |
4 |
Completed. |
13 |
State Memorial to the late President J. F. Kennedy |
... |
... |
... |
2,000,000 |
65,000 |
16,339 |
1 |
1 |
2,952 |
13 |
7 |
19,291 |
14 |
8 |
Planning in progress. |
14 |
Wolfe Tone Memorial |
... |
... |
... |
... |
... |
... |
... |
15,000 |
10,000 |
— |
— |
— |
In progress. |
15 |
Muckross House—Heating & Lighting Installations |
... |
... |
2,500 |
2,500 |
150 |
11 |
9 |
— |
150 |
11 |
9 |
In planning. |
16(1) |
Rotunda Gardens—Garden of Remembrance-Architectural Works |
166,000 |
14,000 |
9,444 |
6 |
6 |
159,316 |
4 |
6 |
168,760 |
11 |
0 |
Completed. |
16(2) |
Rotunda Gardens—Memorial Sculpture |
... |
... |
... |
... |
30,000 |
2,500 |
1,500 |
0 |
0 |
— |
1,500 |
0 |
0 |
In progress. |
17 |
Dún Laoghaire Harbour—Car Ferry Terminals |
... |
... |
... |
950,000 |
280,000 |
213,942 |
5 |
3 |
278,312 |
4 |
7 |
492,254 |
9 |
10 |
In progress. |
|
Total: |
|
|
437,250 |
270,478 |
17 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Justice |
|
|
|
|
|
|
|
|
|
|
|
|
18 |
Memorial to Gardai who lost their lives in the performance of duty |
13,900 |
900 |
1,998 |
9 |
11 |
11,985 |
0 |
0 |
13,983 |
9 |
11 |
Completed. |
19 |
Garda Síochána Depot—Extension of Garage and Workshop |
|
|
|
|
|
|
|
|
|
|
|
|
|
Accommodation |
... |
... |
... |
... |
... |
... |
... |
... |
71,000 |
40,000 |
31,450 |
0 |
0 |
17,103 |
17 |
2 |
48,553 |
17 |
2 |
In progress. |
20 |
New Garda Training Centre, Templemore—Adaptations, etc. |
... |
635,000 |
15,000 |
— |
617,634 |
12 |
0 |
617,634 |
12 |
0 |
Virtually completed. |
21 |
Erection of New Garda Síochána Station |
... |
... |
... |
... |
|
60,000 |
68,277 |
8 |
8 |
— |
|
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
|
|
|
|
Dublin Metropolitan Division: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Rathmines (Temporary Prefabricated building) |
... |
... |
... |
|
|
2,800 |
0 |
0 |
— |
2,800 |
0 |
0 |
Completed. |
|
Co. Cavan: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cootehill |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
422 |
0 |
0 |
8,022 |
0 |
3 |
8,444 |
0 |
3 |
Completed. |
|
Blacklion |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
806 |
13 |
0 |
6,251 |
0 |
0 |
7,057 |
13 |
0 |
Completed. |
|
Killeshandra |
... |
... |
... |
... |
... |
... |
... |
|
|
462 |
0 |
1 |
4,612 |
12 |
3 |
5,074 |
12 |
4 |
Completed. |
21 |
Co. Clare: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ardnacrusha |
... |
... |
... |
... |
... |
... |
... |
|
|
4,842 |
0 |
0 |
4,230 |
0 |
0 |
9,072 |
0 |
0 |
Completed. |
|
Kilrush |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,950 |
14 |
3 |
— |
1,950 |
14 |
3 |
In planning. |
|
Inagh |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
Cr. 442 |
8 |
8 |
6,609 |
12 |
6 |
6,167 |
3 |
10 |
Completed. |
|
Co. Cork: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Kinsale |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
420 |
0 |
0 |
7,898 |
16 |
9 |
8,318 |
16 |
9 |
Completed. |
|
Castletownroche |
... |
... |
... |
... |
... |
... |
... |
|
|
585 |
10 |
0 |
8,435 |
13 |
8 |
9,021 |
3 |
8 |
Completed. |
|
Co. Donegal: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ardara |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
410 |
1 |
8 |
5,985 |
0 |
0 |
6,395 |
1 |
8 |
Completed. |
|
Burtonport |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
440 |
1 |
8 |
7,562 |
0 |
0 |
8,002 |
1 |
8 |
Completed. |
|
Carndonagh |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
16 |
17 |
7 |
8,654 |
13 |
11 |
8,671 |
11 |
6 |
Completed. |
|
Co. Dublin: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Clondalkin |
... |
... |
... |
... |
... |
... |
... |
|
|
1,900 |
0 |
0 |
14,842 |
3 |
2 |
16,742 |
3 |
2 |
Completed. |
|
Co. Galuay: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Killimor |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,335 |
0 |
0 |
3,915 |
0 |
0 |
5,250 |
0 |
0 |
Completed. |
|
Co. Kerry: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ballylongford |
... |
... |
... |
... |
... |
... |
... |
|
|
5,550 |
3 |
11 |
450 |
0 |
0 |
6,000 |
3 |
11 |
Completed. |
|
Kilgarvan |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,254 |
4 |
7 |
5,093 |
0 |
0 |
6,347 |
4 |
7 |
Completed. |
|
Co. Laois: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Abbeyleix |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
5,520 |
0 |
0 |
8,730 |
0 |
0 |
14,250 |
0 |
0 |
Completed. |
|
Co. Leitrim: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ballinamore |
... |
... |
... |
... |
... |
... |
... |
|
|
570 |
0 |
0 |
7,812 |
0 |
0 |
8,382 |
0 |
0 |
Completed. |
|
Co. longford: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Keenagh |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
2,599 |
14 |
7 |
2,430 |
0 |
0 |
5,029 |
14 |
7 |
Completed. |
|
Co. Meath: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ballivor |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
338 |
4 |
10 |
4,370 |
0 |
0 |
4,708 |
4 |
10 |
Completed. |
|
Crossakiel |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
4,225 |
0 |
0 |
2,217 |
0 |
0 |
6,442 |
0 |
0 |
Completed. |
|
Dunboyne |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
969 |
3 |
11 |
8,502 |
0 |
0 |
9,471 |
3 |
11 |
Completed. |
|
Slane |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,151 |
9 |
9 |
6,976 |
0 |
0 |
8,127 |
9 |
9 |
Completed. |
|
Co. Monaghan: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ballybay |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
802 |
3 |
2 |
7,410 |
0 |
0 |
8,212 |
3 |
2 |
Completed. |
|
Clones |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
6,737 |
10 |
0 |
5,850 |
0 |
0 |
12,587 |
10 |
0 |
Completed. |
|
Clontibret |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
134 |
12 |
0 |
6,907 |
3 |
3 |
7,041 |
15 |
3 |
Completed. |
|
Emyvale |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
2,338 |
7 |
2 |
7,110 |
0 |
0 |
9,448 |
7 |
2 |
Completed. |
|
Co. Offaly: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Shinrone |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,525 |
0 |
0 |
3,510 |
0 |
0 |
5,035 |
0 |
0 |
Completed. |
|
Co. Sligo: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Tubbercury |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
978 |
3 |
6 |
7,743 |
0 |
0 |
8,721 |
3 |
6 |
Completed. |
|
Co. Tipperarry: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Ballingarry North |
... |
... |
... |
... |
... |
... |
... |
|
|
745 |
1 |
2 |
5,360 |
0 |
0 |
6,105 |
1 |
2 |
Completed. |
|
Fethard |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
3,455 |
17 |
0 |
7,740 |
0 |
0 |
11,195 |
17 |
0 |
Completed. |
|
Co. Westmeath: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Rochford Bridge |
... |
... |
... |
... |
... |
... |
... |
|
|
539 |
4 |
5 |
4,165 |
2 |
6 |
4,704 |
6 |
11 |
Completed. |
|
Co. Wexford: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Courtown |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
2,463 |
0 |
0 |
5,850 |
0 |
0 |
8,313 |
0 |
0 |
Completed. |
|
Enniscorthy |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
9,000 |
0 |
0 |
4,950 |
0 |
0 |
13,950 |
0 |
0 |
Completed. |
|
Co. Wicklow: |
|
|
|
|
|
|
|
|
|
|
|
|
|
Rathdrum |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,431 |
10 |
1 |
11,178 |
0 |
0 |
12,609 |
19 |
1 |
Completed. |
22 |
Improvement Schemes at existing Garda Síochána Stations |
... |
|
35,000 |
24,809 |
4 |
4 |
|
|
|
|
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
|
|
|
|
Dublin Metropolitan Division: |
|
|
|
|
|
|
|
|
|
|
|
|
31/36 of 1965/66 |
Clontarf |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
25 |
0 |
0 |
2,347 |
15 |
0 |
2,372 |
15 |
0 |
Completed. |
64 |
Clontarf—(Flooring) |
... |
... |
... |
... |
... |
... |
|
|
208 |
9 |
9 |
— |
208 |
9 |
9 |
Completed. |
31 |
Special Detective Unit, Dublin Castle |
... |
... |
... |
... |
|
|
1,359 |
6 |
10 |
— |
1,359 |
6 |
10 |
Completed. |
26/58 of 64/65 |
Depot Hospital |
... |
... |
... |
... |
... |
... |
... |
|
|
8 |
18 |
9 |
904 |
8 |
6 |
913 |
7 |
3 |
Completed. |
49 |
Donnybrook |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
437 |
1 |
10 |
— |
437 |
1 |
10 |
Completed. |
31/18 of 65/66 |
Dún Laoghaire |
... |
... |
... |
... |
... |
... |
... |
|
|
87 |
10 |
0 |
36 |
7 |
6 |
123 |
17 |
6 |
Completed. |
26/15 of 1964-65 |
Kill O’Grange |
... |
... |
... |
... |
... |
... |
... |
|
|
342 |
2 |
10 |
1,612 |
8 |
6 |
1,954 |
11 |
4 |
Completed. |
44 |
Pearse St. |
... |
... |
... |
... |
... |
... |
... |
|
|
160 |
6 |
0 |
— |
160 |
6 |
0 |
Completed. |
|
Co. Carlow: |
|
|
|
|
|
|
|
|
|
|
|
|
33 |
Tullow |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
900 |
0 |
0 |
— |
900 |
0 |
0 |
In progress. |
|
Co. Cavan: |
|
|
|
|
|
|
|
|
|
|
|
|
50 |
Ballinagh |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
179 |
0 |
0 |
— |
179 |
0 |
0 |
Completed. |
|
Co. Clare: |
|
|
|
|
|
|
|
|
|
|
|
|
26 |
Doonbeg |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
945 |
0 |
0 |
— |
945 |
0 |
0 |
In progress. |
|
Co. Cork: |
|
|
|
|
|
|
|
|
|
|
|
|
55 |
Ballincollig |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
450 |
0 |
0 |
— |
450 |
0 |
0 |
Completed. |
31/66 of |
Castletownbere |
... |
... |
... |
... |
... |
... |
... |
|
|
179 |
15 |
0 |
884 |
0 |
0 |
1,063 |
15 |
0 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
22 |
Castletownsend |
... |
... |
... |
... |
... |
... |
... |
|
|
356 |
3 |
9 |
— |
356 |
3 |
9 |
Completed. |
31/42 of |
Clonakilty |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
742 |
12 |
7 |
2,100 |
0 |
0 |
2,842 |
12 |
7 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
26/73 of |
McCurtin St. Cork |
... |
... |
... |
... |
... |
... |
... |
|
|
243 |
2 |
10 |
513 |
2 |
6 |
756 |
5 |
4 |
Completed. |
1964-65 |
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
Tarelton |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
428 |
0 |
0 |
— |
428 |
0 |
0 |
In progress. |
|
Co. Dublin: |
|
|
|
|
|
|
|
|
|
|
|
|
19 |
Balbriggan |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,811 |
6 |
9 |
— |
1,811 |
6 |
9 |
Completed. |
|
Co. Galway: |
|
|
|
|
|
|
|
|
|
|
|
|
15 |
Barnaderg |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
356 |
17 |
6 |
— |
356 |
17 |
6 |
Partly completed. |
32 |
Corofin |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
263 |
15 |
0 |
— |
263 |
15 |
0 |
Completed. |
31/41 of 1965-66 |
Corrandulla |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
150 |
0 |
0 |
900 |
0 |
0 |
1,050 |
0 |
0 |
In progress. |
42 |
Kilcolgan |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
276 |
15 |
0 |
— |
276 |
15 |
0 |
Partly completed. |
14 |
Kilconly |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
310 |
5 |
0 |
— |
310 |
5 |
0 |
Partly completed. |
31/29 of |
Kinvara |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
81 |
9 |
0 |
2,380 |
0 |
0 |
2,401 |
9 |
0 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
26/57 of |
Maam |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
7 |
3 |
11 |
1,297 |
4 |
1 |
1,304 |
8 |
0 |
Completed. |
1964-65 |
|
|
|
|
|
|
|
|
|
|
|
|
|
26/45 of |
Tynagh |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
366 |
2 |
5 |
2,686 |
14 |
0 |
3,052 |
16 |
5 |
Completed. |
1964-65 |
|
|
|
|
|
|
|
|
|
|
|
|
|
26/56 of |
Moylough |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
156 |
0 |
0 |
500 |
0 |
0 |
656 |
0 |
0 |
Completed. |
1964-65 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Co. Kerry: |
|
|
|
|
|
|
|
|
|
|
|
|
37 |
Castleisland |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,485 |
0 |
0 |
|
|
|
1,485 |
0 |
0 |
In progress. |
6 |
Castlemaine |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
115 |
15 |
0 |
|
|
|
115 |
15 |
0 |
|
31/69 of |
Kenmare |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
629 |
5 |
8 |
680 |
0 |
0 |
1,309 |
5 |
8 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
31/48 of |
Listowel |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
78 |
0 |
0 |
600 |
0 |
0 |
678 |
0 |
0 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Laois: |
|
|
|
|
|
|
|
|
|
|
|
|
36 |
Borris-in-Ossory |
... |
... |
... |
... |
... |
... |
... |
|
|
600 |
0 |
0 |
— |
600 |
0 |
0 |
In Progress. |
31/19 of |
Rathdowney |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
13 |
4 |
0 |
1,628 |
4 |
6 |
1,641 |
8 |
6 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Co. Leitrim: |
|
|
|
|
|
|
|
|
|
|
|
|
30 |
Keshcarrigan |
... |
... |
... |
... |
... |
... |
... |
|
|
145 |
0 |
0 |
— |
145 |
0 |
0 |
Completed. |
22 |
Co. Limerick: |
|
|
|
|
|
|
|
|
|
|
|
|
41 |
Doon |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
331 |
10 |
5 |
— |
331 |
10 |
5 |
Completed. |
14 |
Co. Louth: |
|
|
|
|
|
|
|
|
|
|
|
|
31/25 of |
Dundalk |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
270 |
0 |
0 |
540 |
0 |
0 |
810 |
0 |
0 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
31/25 of |
Drogheda |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
450 |
0 |
0 |
1,980 |
0 |
0 |
2,430 |
0 |
0 |
In progress. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Co. Mayo: |
|
|
|
|
|
|
|
|
|
|
|
|
24 |
Bonniconlon |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
310 |
0 |
0 |
— |
310 |
0 |
0 |
In progress. |
31/57 of |
Hollymount |
... |
... |
... |
... |
... |
... |
... |
|
|
351 |
19 |
4 |
855 |
0 |
0 |
1,206 |
19 |
4 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
17 |
Knock |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,000 |
0 |
0 |
— |
1,000 |
0 |
0 |
Completed. |
31/38 of |
Shrule |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
134 |
13 |
6 |
462 |
6 |
7 |
597 |
0 |
1 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Co. Meath: |
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Dunshaughlin |
... |
... |
... |
... |
... |
... |
... |
|
|
310 |
4 |
0 |
|
|
|
310 |
4 |
0 |
Completed. |
|
Co. Offaly: |
|
|
|
|
|
|
|
|
|
|
|
|
31/70 of |
Birr |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
12 |
10 |
0 |
440 |
14 |
3 |
453 |
4 |
3 |
Completed. |
1965-66 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Co. Roscommon: |
|
|
|
|
|
|
|
|
|
|
|
|
5 |
Clonark |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
119 |
10 |
0 |
— |
119 |
10 |
0 |
In progress. |
|
Co. Tipperary: |
|
|
|
|
|
|
|
|
|
|
|
|
26/48 of |
Carrick-on-Suir |
... |
... |
... |
... |
... |
... |
... |
|
|
39 |
1 |
9 |
220 |
0 |
0 |
259 |
0 |
9 |
Completed. |
1964-65 |
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
Golden |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,116 |
0 |
11 |
— |
1,116 |
0 |
11 |
Completed. |
38 |
Shevry |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
170 |
0 |
0 |
— |
170 |
0 |
0 |
In progress. |
|
Co. Waterford: |
|
|
|
|
|
|
|
|
|
|
|
|
29 |
Kill |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
2,340 |
0 |
0 |
— |
2,340 |
0 |
0 |
In progress. |
28 |
Leamybrien |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
3,600 |
0 |
0 |
— |
3,600 |
0 |
0 |
In progress. |
|
Co. Wexford: |
|
|
|
|
|
|
|
|
|
|
|
|
27 |
Ballywilliam |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
355 |
5 |
0 |
— |
355 |
5 |
0 |
Completed. |
23 |
Houses for Married Members of the Garda Síochána |
... |
... |
|
120,000 |
110,156 |
0 |
0 |
920,120 |
0 |
0 |
1,030,276 |
0 |
0 |
|
24 |
Courts of Justice—Renewal of Defective Stonework |
... |
... |
... |
68,000 |
500 |
1,689 |
2 |
8 |
4,945 |
14 |
5 |
6,034 |
17 |
1 |
Planning completed. |
24A |
Metropolitan District Courts—Improvements to Justices’ Rooms |
... |
2,400 |
|
159 |
13 |
2 |
— |
159 |
13 |
2 |
Completed. |
25 |
Land Registry—Additional Accommodation (Stage II) |
... |
... |
224,000 |
60,000 |
44,862 |
5 |
4 |
5,641 |
14 |
0 |
50,503 |
19 |
4 |
In progress. |
|
Total: |
|
|
331,400 |
283,402 |
4 |
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Local Government: |
|
|
|
|
|
|
|
|
|
|
|
|
25A |
Additional Accommodation—O’Connell Bridge House, Dublin |
... |
16,500 |
— |
3,831 |
19 |
9 |
22,069 |
1 |
11 |
25,901 |
1 |
8 |
Completed |
|
Total: |
|
|
|
3,831 |
19 |
9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Education: |
|
|
|
|
|
|
|
|
|
|
|
|
26 |
Additional Accommodation (Dublin)—Liberty Hall |
... |
... |
... |
6,000 |
3,500 |
2,552 |
5 |
11 |
2,933 |
4 |
10 |
5,485 |
10 |
9 |
Completed. |
27 |
National Schools—Grants for Building, Enlarging, Enclosing etc. |
... |
|
2,760,000 |
2,772,038 |
12 |
9 |
|
|
|
2,772,038 |
12 |
9 |
|
28 |
National Library—Fire Alarm System |
... |
... |
... |
6,750 |
6,750 |
4,860 |
0 |
0 |
— |
4,860 |
0 |
0 |
Nearing completion. |
29 |
National Museum—Fire Alarm System |
... |
... |
... |
... |
8,500 |
8,500 |
66 |
1 |
11 |
21 |
2 |
2 |
87 |
4 |
1 |
Contract placed. |
29A |
National Museum—Royal Hospital, Kilmainham, Improved |
|
|
|
|
|
|
|
|
|
|
|
|
|
Electrical System |
... |
... |
... |
... |
... |
... |
... |
... |
4,000 |
— |
1,035 |
17 |
2 |
2,275 |
0 |
0 |
3,310 |
17 |
2 |
Completed. |
30 |
Dublin Preventive Centre |
... |
... |
... |
... |
... |
... |
266,000 |
2,000 |
— |
3,587 |
10 |
4 |
3,587 |
10 |
4 |
Tenders invited. |
31 |
Dublin Institute for Advanced Studies—Accommodation |
... |
... |
72,000 |
1,000 |
1,149 |
6 |
0 |
3,588 |
6 |
0 |
4,737 |
12 |
0 |
Planning completed. |
32 |
National Gallery—Extension |
... |
... |
... |
... |
... |
... |
315,000 |
100,000 |
100,439 |
6 |
10 |
66,829 |
10 |
9 |
167,268 |
17 |
7 |
In progress. |
|
Total |
|
|
2,881,750 |
2,882,141 |
10 |
7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Lands: |
|
|
|
|
|
|
|
|
|
|
|
|
33 |
Avondale House—Adaptation as Forestry Training and Conference |
|
|
|
|
|
|
|
|
|
|
|
|
|
Centre |
... |
... |
... |
... |
... |
... |
... |
... |
... |
60,000 |
27,000 |
26,010 |
0 |
0 |
20,653 |
6 |
5 |
46,663 |
6 |
5 |
Nearing completion. |
34 |
Shelton Abbey Forestry School—Improvement of Sewage System |
4,000 |
4,000 |
— |
— |
— |
In Planning. |
|
Total: |
|
|
31,000 |
26,010 |
0 |
0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Agriculture and Fisheries: |
|
|
|
|
|
|
|
|
|
|
|
|
34A |
Additional Accommodation—O’Connell Bridge House, Dublin |
... |
8,500 |
— |
2,243 |
1 |
0 |
12,006 |
9 |
11 |
14,249 |
10 |
11 |
Completed |
35(1) |
Veterinary College Ballsbridge—New Radiography Unit Extension |
|
|
|
|
|
|
|
|
|
|
|
|
|
of Operating Theatre |
... |
... |
... |
... |
... |
... |
... |
14,500 |
12,750 |
5,416 |
17 |
2 |
— |
5,416 |
17 |
2 |
In progress. |
35(2) |
Veterinary College Ballsbridge—Extension |
... |
... |
... |
... |
150,000 |
20,000 |
7,251 |
5 |
6 |
3,278 |
7 |
0 |
10,529 |
12 |
6 |
In planning. |
35(3) |
Veterinary College, Ballsbridge Pathological Anatomy Unit |
... |
13,200 |
— |
3,397 |
11 |
8 |
12,821 |
19 |
8 |
16,219 |
11 |
4 |
Completed. |
36 |
Botanic Gardens—Accommodation for a Herbarium and Botanical |
|
|
|
|
|
|
|
|
|
|
|
|
|
Collection |
... |
... |
... |
... |
... |
... |
... |
... |
6,300 |
1,500 |
646 |
6 |
0 |
2,272 |
19 |
0 |
2,919 |
5 |
0 |
In progress. |
37 |
Butter Testing Station, Dublin—Extension |
... |
... |
... |
... |
7,000 |
5,000 |
— |
— |
|
|
|
In planning. |
38 |
Regional Veterinary and Dairy Produce Laboratories |
... |
... |
144,500 |
30,000 |
14,676 |
1 |
1 |
7,105 |
11 |
2 |
21,781 |
12 |
3 |
In progress. |
38A |
Ennis—Building for Veterinary Land Project Staff |
... |
... |
11,000 |
— |
5,670 |
0 |
0 |
— |
5,670 |
0 |
0 |
In progress. |
39(1) |
Abbotstown Farm—Experimental Animals Farmyard |
... |
... |
71,000 |
2,500 |
— |
57,144 |
7 |
3 |
57,144 |
7 |
3 |
Final Stage in planning. |
39(2) |
Abbotstown Farm—Experimental Animals Accommodation |
... |
120,000 |
3,500 |
1,500 |
0 |
0 |
3,500 |
0 |
0 |
5,000 |
0 |
0 |
Planning completed. |
39(3) |
Abbotstown Farm—Foundation Stock Farmyard |
... |
... |
... |
92,000 |
7,000 |
3,772 |
4 |
7 |
82,744 |
3 |
5 |
86,516 |
8 |
0 |
Mainly completed. |
39(4) |
Abbotstown Farm—Veterinary Field Station |
... |
... |
... |
... |
167,000 |
10,000 |
22,983 |
15 |
10 |
160,598 |
7 |
5 |
183,582 |
3 |
3 |
Completed. |
39(5) |
Abbotstown Farm—Field Station—Loose Boxes |
... |
... |
... |
6,500 |
|
3,330 |
0 |
0 |
— |
3,330 |
0 |
0 |
Completed. |
40(1) |
Athenry Agricultural School—Improvement of Water Supply |
... |
19,000 |
11,000 |
1,026 |
9 |
7 |
5,490 |
7 |
2 |
6,516 |
16 |
9 |
In progress. |
40(2) |
Athenry Agricultural School—Erection of new Building |
... |
... |
110,000 |
1,000 |
5,184 |
17 |
2 |
113,138 |
7 |
1 |
118,323 |
4 |
3 |
Completed. |
40(3) |
Athenry Agricultural School—Improvements to Turkey Hatchery |
37,500 |
1,400 |
1,366 |
0 |
0 |
36,477 |
10 |
7 |
37,843 |
10 |
7 |
Completed. |
41 |
Ballyhaise Agricultural School—Sewage Disposal Scheme |
... |
... |
12,000 |
8,000 |
— |
232 |
16 |
1 |
232 |
16 |
1 |
In planning. |
41A |
Ballyhaise Agricultural School—Fire Precaution Works and |
|
|
|
|
|
|
|
|
|
|
|
|
|
Improvements to Heating System |
... |
... |
... |
... |
... |
4,500 |
— |
2,412 |
15 |
0 |
3,323 |
3 |
6 |
5,735 |
18 |
6 |
Completed. |
42(1) |
Clonakilty Agricultural School—New Building |
... |
... |
... |
110,000 |
1,000 |
8,372 |
1 |
2 |
110,497 |
11 |
7 |
118,869 |
12 |
9 |
Completed. |
42(2) |
Clonakilty Agricultural School—Employees’ Cottages |
... |
... |
11,350 |
750 |
150 |
0 |
0 |
11,850 |
0 |
0 |
12,000 |
0 |
0 |
Completed. |
43 |
Kennedy Memorial Park, Co. Wexford—School of Horticulture etc. |
145,000 |
2,000 |
1,002 |
10 |
0 |
— |
1,002 |
10 |
0 |
In planning. |
44(1) |
Munster Institute—New Poultry Plant |
... |
... |
... |
... |
100,000 |
5,000 |
3,625 |
0 |
0 |
31,924 |
6 |
7 |
35,549 |
6 |
7 |
Partially completed. |
44(2) |
Munster Institute—Extension of Pig Progeny Testing Station |
... |
53,000 |
5,000 |
7,012 |
11 |
1 |
45,589 |
11 |
3 |
52,602 |
2 |
4 |
Completed. |
45 |
Quarantine Station for Imported Livestock (Spike Island) |
... |
39,000 |
4,000 |
2,974 |
0 |
0 |
36,979 |
16 |
4 |
39,953 |
16 |
4 |
Completed. |
45A |
Waterford B.T.E. Offices—Accommodation for Brucellosis |
|
|
|
|
|
|
|
|
|
|
|
|
|
Eradication Centre |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,620 |
0 |
0 |
— |
1,620 |
0 |
0 |
|
46 |
Major Fishery Harbours |
... |
... |
... |
... |
... |
... |
1,695,000 |
160,000 |
122,620 |
0 |
3 |
— |
|
|
|
|
|
|
|
|
Detailed as follows: |
|
|
|
|
|
|
|
|
Castletownbere |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
25,031 |
16 |
6 |
74,709 |
15 |
9 |
99,741 |
12 |
3 |
In progress. |
|
Dunmore East |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
74,319 |
9 |
3 |
170,964 |
11 |
4 |
245,284 |
0 |
7 |
In progress. |
|
Galway |
... |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
143 |
8 |
1 |
28,666 |
17 |
2 |
28,810 |
5 |
3 |
In planning. |
|
Howth |
... |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
130 |
6 |
11 |
20,471 |
0 |
11 |
20,601 |
7 |
10 |
In planning. |
|
Killybegs |
... |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
22,994 |
19 |
6 |
107,808 |
0 |
11 |
130,863 |
0 |
5 |
In progress. |
47 |
Works of Economic Development at other Fishery Harbours |
... |
46,225 |
19,600 |
20,000 |
15 |
2 |
|
|
|
|
|
|
|
|
|
|
|
detailed as follows:— |
|
|
|
|
|
|
|
|
Bandon Estuary |
... |
... |
... |
... |
... |
... |
... |
|
|
23 |
11 |
3 |
— |
23 |
11 |
3 |
In planning. |
|
Burtonport Beacons |
... |
... |
... |
... |
... |
... |
... |
|
|
6 |
8 |
3 |
4,937 |
1 |
4 |
4,943 |
9 |
7 |
Completed. |
|
Cahirciveen |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
2,243 |
4 |
9 |
3,210 |
12 |
3 |
5,453 |
17 |
0 |
Completed. |
|
Darbys Point, Achill Island |
... |
... |
... |
... |
... |
... |
|
|
1,020 |
0 |
0 |
— |
1,020 |
0 |
0 |
In planning. |
|
Dingle |
... |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,680 |
0 |
0 |
— |
1,680 |
0 |
0 |
In planning. |
|
Enniscrone |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
|
18 |
0 |
2,940 |
5 |
8 |
2,941 |
3 |
8 |
Completed. |
|
Greencastle |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
50 |
13 |
5 |
68,391 |
4 |
10 |
68,441 |
18 |
3 |
Completed. |
|
Kilmore Quay |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
30 |
0 |
0 |
— |
30 |
0 |
0 |
Tenders invited. |
|
Passage East |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
977 |
8 |
5 |
3,042 |
7 |
8 |
4,019 |
16 |
1 |
Completed. |
|
Reen Pier |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
611 |
5 |
0 |
— |
611 |
5 |
0 |
In progress. |
|
Renard Point |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
12,195 |
4 |
1 |
17,010 |
18 |
9 |
29,206 |
2 |
10 |
Completed. |
|
Skerries |
... |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
1,159 |
10 |
0 |
17 |
12 |
3 |
1,177 |
2 |
3 |
In planning. |
|
Westport |
... |
... |
... |
... |
... |
... |
... |
... |
|
|
2 |
12 |
0 |
39 |
6 |
4 |
41 |
18 |
4 |
Completed. |
48 |
Galway, Fisheries Research Station—Erection |
... |
... |
... |
150,000 |
2,500 |
|
— |
— |
In planning. |
|
Total: |
|
|
313,500 |
248,254 |
2 |
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Labour: |
|
|
|
|
|
|
|
|
|
|
|
|
49 |
Additional Accommodation (Dublin)—Ansley House |
... |
... |
80,000 |
60,000 |
30,383 |
16 |
2 |
16,536 |
2 |
6 |
46,919 |
18 |
8 |
Partially completed. |
|
Total: |
|
|
60,000 |
30,383 |
16 |
2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Transport and Power: |
|
|
|
|
|
|
|
|
|
|
|
|
49A |
Additional Accommodation—O’Connell Bridge House, Dublin |
... |
3,000 |
— |
669 |
8 |
6 |
3,466 |
11 |
2 |
4,135 |
19 |
8 |
Completed. |
50 |
Clones Meteorological Station—Extension |
... |
... |
... |
... |
4,350 |
500 |
804 |
8 |
9 |
3,450 |
0 |
0 |
4,254 |
8 |
9 |
Completed. |
|
Total: |
|
|
500 |
1,473 |
17 |
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Posts and Telegraphs: |
|
|
|
|
|
|
|
|
|
|
|
|
51 |
Dublin—New Central Sorting Office |
... |
... |
... |
... |
... |
846,000 |
173,000 |
101,289 |
11 |
2 |
689,814 |
1 |
0 |
791,103 |
12 |
2 |
Nearing completion. |
51A |
Dublin—G.P.O. Dining Club—Improvements to Kitchen |
... |
... |
3,850 |
|
3,391 |
1 |
1 |
— |
3,391 |
1 |
1 |
|
52 |
Dublin—New District Sorting Office and Telephone Exchange at |
|
|
|
|
|
|
|
|
|
|
|
|
|
Coolock/Raheny |
... |
... |
... |
... |
... |
... |
... |
17,000 |
500 |
768 |
17 |
7 |
15,456 |
8 |
6 |
16,225 |
7 |
1 |
Completed. |
52A |
Dublin—G.P.O. Strong Room |
... |
... |
... |
... |
... |
... |
4,440 |
|
3,420 |
0 |
0 |
— |
3,420 |
0 |
0 |
Completed. |
53 |
Dublin—New Warehousing, etc. Accommodation |
... |
... |
... |
190,000 |
70,000 |
65,000 |
0 |
0 |
86,403 |
16 |
7 |
151,403 |
16 |
7 |
In progress. |
54 |
Blackrock, Co. Dublin, Post Office—Improvements |
... |
... |
... |
4,000 |
3,000 |
3,150 |
0 |
0 |
— |
3,150 |
0 |
0 |
Virtually completed. |
55 |
Dún Laoghaire Post Office—Improvements |
... |
... |
... |
... |
55,500 |
2,500 |
— |
357 |
10 |
9 |
357 |
10 |
9 |
Suspended. |
56 |
Carlow Post Office and Telephone Exchange |
... |
... |
... |
... |
114,000 |
27,000 |
16,989 |
0 |
0 |
2,474 |
6 |
6 |
19,463 |
6 |
6 |
In progress. |
57 |
Greystones Post Office—Improvements |
... |
... |
... |
... |
4,500 |
1,500 |
2,453 |
0 |
0 |
2,280 |
0 |
0 |
4,733 |
0 |
0 |
Completed. |
58 |
Killarney—New Telephone Exchange and Additional Sorting Office, |
|
|
|
|
|
|
|
|
|
|
|
|
|
etc. accommodation |
... |
... |
... |
... |
... |
... |
... |
35,000 |
500 |
— |
— |
— |
In progress. |
58A |
Limerick Post Office—Improvements |
... |
... |
... |
... |
... |
|
— |
2,460 |
8 |
11 |
24,380 |
17 |
8 |
26,841 |
6 |
7 |
Completed. |
59 |
Youghal—New Post Office and Telephone Exchange |
... |
... |
18,000 |
2,000 |
2,292 |
16 |
11 |
15,768 |
13 |
5 |
18,061 |
10 |
4 |
Completed. |
|
Total: |
|
|
280,000 |
201,214 |
16 |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of External Affairs: |
|
|
|
|
|
|
|
|
|
|
|
|
60 |
Irish Embassy in Washington—Ambassador’s Residence— |
|
|
|
|
|
|
|
|
|
|
|
|
|
Adaptation and Furnishing |
... |
... |
... |
... |
... |
... |
... |
55,000 |
22,000 |
20,385 |
4 |
7 |
32,257 |
9 |
5 |
52,642 |
14 |
0 |
Virtually completed. |
|
Total: |
|
|
22,000 |
20,385 |
4 |
7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Social Welfare: |
|
|
|
|
|
|
|
|
|
|
|
|
61 |
Longford New Employment Exchange |
... |
... |
... |
... |
23,000 |
10,000 |
6,753 |
3 |
1 |
10,268 |
6 |
0 |
17,021 |
9 |
1 |
Completed. |
|
Total: |
|
|
10,000 |
6,753 |
3 |
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Department of Health: |
|
|
|
|
|
|
|
|
|
|
|
|
62 |
Liberty Hall—Accommodation |
... |
... |
... |
... |
... |
... |
2,200 |
1,500 |
1,559 |
19 |
8 |
2,164 |
14 |
2 |
3,724 |
13 |
10 |
Completed. |
63(1) |
Central Mental Hospital, Dundrum—New Entrance Gates |
... |
... |
2,200 |
1,300 |
— |
360 |
0 |
0 |
360 |
0 |
0 |
Nearing completion. |
63(2) |
Central Mental Hospital, Dundrum—Rebuilding Boiler House |
... |
6,850 |
1,000 |
2,108 |
7 |
8 |
5,400 |
0 |
0 |
7,508 |
7 |
8 |
Completed. |
|
Total: |
|
|
3,800 |
3,668 |
7 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1966-67 (VOTE 8, SUBHEAD E).
Work No. |
Service and Description |
Total Estimate |
Vote 1966-67 |
1966-67 |
|
|
|
£ |
£ |
£ |
s. |
d. |
|
|
General: |
|
|
|
|
|
|
64 |
Minor New Works not exceeding £2,000 each |
... |
... |
... |
... |
|
30,000 |
27,340 |
8 |
9 |
|
65 |
Urgent and Unforeseen Works |
... |
... |
... |
... |
... |
... |
|
5,000 |
12,540 |
4 |
8 |
|
66 |
Minor Balances of Expenditure (not provided for above) on works of prior years which might not have been completed on 1st April, 1966 |
|
15,000 |
16,301 |
1 |
4 |
|
|
Total: |
|
4,741,700 |
4,270,516 |
18 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
DETAILS OF No. 64—MINOR NEW WORKS.
Work No. |
Service and Description |
Expenditure |
Observations |
1966-67 |
To 31/3/66 |
To 31/3/67 |
|
|
£ |
s. |
d. |
£ |
s. |
d. |
£ |
s. |
d. |
|
|
President’s Establishment: |
|
|
|
|
|
|
|
|
|
|
27 |
State Apartments, Dublin Castle—Preparation for Inauguration |
... |
... |
... |
1,122 |
16 |
11 |
— |
1,122 |
16 |
11 |
Completed. |
|
Oireachtas: |
|
|
|
|
|
|
|
|
|
|
34 |
Leinster House—Improve toilet facilities for military fire picquet |
... |
... |
... |
318 |
0 |
0 |
— |
318 |
0 |
0 |
Completed. |
|
Department of Finance: |
|
|
|
|
|
|
|
|
|
|
|
Revenue Commissioners |
|
|
|
|
|
|
|
|
|
|
76/98 of 1964/65 |
Dublin Castle, Stamping Branch—Adaptations |
... |
... |
... |
... |
... |
22 |
15 |
1 |
1,683 |
18 |
0 |
1,706 |
13 |
1 |
Completed. |
18 |
14-15 Upr. O’Connell St.—Adaptations |
... |
... |
... |
... |
... |
... |
562 |
10 |
7 |
— |
562 |
10 |
7 |
Completed. |
66 |
14-15 Upr. O’Connell St.—Shelving |
... |
... |
... |
... |
... |
... |
... |
445 |
7 |
8 |
— |
445 |
7 |
8 |
Completed. |
90/31 of 1965/66 |
Bridgend Customs Frontier Post—Improved sanitary facilities |
... |
... |
... |
396 |
14 |
1 |
1,460 |
0 |
0 |
1,856 |
14 |
1 |
Completed. |
32 |
Cork Government Buildings—Electrical Improvements |
... |
... |
... |
... |
145 |
7 |
7 |
— |
145 |
7 |
7 |
Completed. |
77 |
Tullynagrow Customs Frontier Post—Sanitary Improvements |
... |
... |
... |
239 |
0 |
6 |
— |
239 |
0 |
6 |
Completed. |
81 |
Cork Government Buildings—Adaptations |
... |
... |
... |
... |
... |
... |
56 |
15 |
0 |
— |
56 |
15 |
0 |
In progress. |
|
Office of Public Works: |
|
|
|
|
|
|
|
|
|
|
72/74 of 1963/64 |
Phoenix Park—Improvements at White Gates |
... |
... |
... |
... |
... |
117 |
4 |
7 |
128 |
5 |
11 |
245 |
10 |
6 |
Completed. |
90/21 of 1965/66 |
St. Stephens Green Park—Improvements to Playground |
... |
... |
... |
... |
17 |
0 |
4 |
813 |
1 |
1 |
830 |
1 |
5 |
Completed. |
90/44 of 1965/66 |
13/14 Earlsfort Terrace—Security Alterations |
... |
... |
... |
... |
... |
... |
3 |
17 |
0 |
232 |
1 |
8 |
235 |
18 |
8 |
Completed. |
90/66 of 1965/66 |
51 St. Stephen’s Green—Drawing Office—Alterations |
... |
... |
... |
... |
199 |
19 |
7 |
414 |
18 |
1 |
614 |
17 |
8 |
Completed. |
31 |
St. Stephen’s Green Park—Site for Fianna Memorial |
... |
... |
... |
... |
349 |
0 |
0 |
— |
349 |
0 |
0 |
Completed. |
52 |
Griffith Barracks—Electrical Improvements |
... |
... |
... |
... |
... |
... |
539 |
2 |
8 |
— |
539 |
2 |
8 |
Completed. |
75 |
51 St. Stephen’s Green—Electrical Lighting Improvements |
... |
... |
... |
... |
46 |
0 |
0 |
— |
46 |
0 |
0 |
In progress. |
90/65 of 1965/66 |
Garnish Island—Improved Water Supply, etc. |
... |
... |
... |
... |
... |
162 |
2 |
6 |
102 |
1 |
11 |
264 |
4 |
5 |
Completed. |
90/74 of 1965/66 |
Ardee—Accommodation for Archaeological Survey |
... |
... |
... |
... |
... |
715 |
12 |
2 |
278 |
14 |
6 |
994 |
6 |
8 |
Completed. |
|
Valuation Office: |
|
|
|
|
|
|
|
|
|
|
76/72 of 1964/65 |
5/6 Ely Place—Improved heating, etc. |
... |
... |
... |
... |
... |
... |
... |
1 |
3 |
9 |
679 |
17 |
1 |
681 |
0 |
10 |
Completed. |
90/87 of 1965/66 |
Ordnance Survey Office—Fundamental Bench Marks |
... |
... |
... |
... |
289 |
2 |
0 |
35 |
11 |
3 |
324 |
13 |
3 |
Completed. |
21 |
Ordnance Survey Office—Storage Racks |
... |
... |
... |
... |
... |
... |
206 |
1 |
8 |
— |
206 |
1 |
8 |
Completed. |
|
State Laboratory: |
|
|
|
|
|
|
|
|
|
|
55 |
College of Science—Shelving |
... |
... |
... |
... |
... |
... |
... |
... |
70 |
4 |
1 |
— |
70 |
4 |
1 |
Completed. |
|
General: |
|
|
|
|
|
|
|
|
|
|
17 |
Castlebar Government Offices—Adaptations |
... |
... |
... |
... |
... |
... |
495 |
0 |
0 |
— |
495 |
0 |
0 |
In progress. |
67 |
Letterkenny Government Offices—Equipping |
... |
... |
... |
... |
... |
... |
66 |
3 |
0 |
— |
66 |
3 |
0 |
In progress. |
70 |
Cork Government Buildings—Improvements |
... |
... |
... |
... |
... |
... |
161 |
7 |
5 |
— |
161 |
7 |
5 |
In progress. |
|
Department of Justice: |
|
|
|
|
|
|
|
|
|
|
22 |
High Court, Official Assignees Office—Adaptations |
... |
... |
... |
... |
... |
188 |
16 |
3 |
— |
188 |
16 |
3 |
In progress. |
30 |
Metropolitan District Courts—Provision of sound amplification |
... |
... |
... |
254 |
10 |
1 |
— |
254 |
10 |
1 |
Completed. |
|
Department of Local Government: |
|
|
|
|
|
|
|
|
|
|
76 |
Dublin Custom House—Adaptations |
... |
... |
... |
... |
... |
... |
... |
237 |
19 |
7 |
— |
237 |
19 |
7 |
In progress. |
|
Department of Education: |
|
|
|
|
|
|
|
|
|
|
65 |
Marlboro Street—Improved lighting |
... |
... |
... |
... |
... |
... |
... |
47 |
11 |
7 |
— |
47 |
11 |
7 |
In progress. |
37 |
Marlboro Street—Adaptations |
... |
... |
... |
... |
... |
... |
... |
... |
767 |
7 |
4 |
— |
767 |
7 |
4 |
In progress. |
7 |
Tyrone House—Sanitary Improvements |
... |
... |
... |
... |
... |
... |
617 |
19 |
4 |
— |
617 |
19 |
4 |
Completed. |
26 |
Tyrone House—Improvements |
... |
... |
... |
... |
... |
... |
... |
... |
80 |
5 |
7 |
— |
80 |
5 |
7 |
In progress. |
46 |
Tyrone House—Tea Room for Minister’s Staff |
... |
... |
... |
... |
... |
197 |
12 |
4 |
— |
197 |
12 |
4 |
Completed. |
63 |
Tyrone House—Reception Office |
... |
... |
... |
... |
... |
... |
... |
198 |
1 |
7 |
— |
198 |
1 |
7 |
Completed. |
90/77 of 1965/66 |
Limerick Model School—Electrical Improvements |
... |
... |
... |
... |
... |
53 |
0 |
0 |
500 |
0 |
0 |
553 |
0 |
0 |
Completed. |
29 |
National Gallery—Conservation Laboratory—Adaptations |
... |
... |
... |
... |
482 |
7 |
0 |
— |
482 |
7 |
0 |
Completed. |
57 |
Bailieboro Model School—Improvements |
... |
... |
... |
... |
... |
... |
540 |
0 |
0 |
— |
540 |
0 |
0 |
Completed. |
95 |
St. Conleth’s Reformatory, Daingean—Improvements |
... |
... |
... |
... |
60 |
0 |
0 |
— |
60 |
0 |
0 |
Completed. |
|
Department of Lands: |
|
|
|
|
|
|
|
|
|
|
90/47 of 1965/66 |
2/3 Merrion Square—Rewire Electrical Installation |
... |
... |
... |
... |
... |
77 |
0 |
0 |
1,663 |
2 |
2 |
1,740 |
2 |
2 |
Completed. |
50 |
25/26 Upper Merrion St.—Accommodation for Scientific officer |
... |
... |
... |
964 |
19 |
0 |
— |
964 |
19 |
0 |
Completed. |
88 |
24 Upper Merrion St.—Adaptations |
... |
... |
... |
... |
... |
... |
... |
88 |
16 |
9 |
— |
88 |
16 |
9 |
In progress. |
90/84 of 1965/66 |
Forestry Branch, Mallow—Provision of Accommodation |
... |
... |
... |
... |
74 |
0 |
0 |
40 |
0 |
0 |
114 |
0 |
0 |
Completed. |
|
Department of Agriculture and Fisheries: |
|
|
|
|
|
|
|
|
|
|
90/80 of 1965/66 |
Veterinary College, Ballsbridge—Adaptations |
... |
... |
... |
... |
... |
... |
378 |
8 |
2 |
189 |
17 |
4 |
568 |
5 |
6 |
Completed. |
20 |
Veterinary College, Ballsbridge—Classroom Accommodation |
... |
... |
... |
193 |
1 |
0 |
— |
193 |
1 |
0 |
Completed. |
44 |
Veterinary College, Ballsbridge—Improvements |
... |
... |
... |
... |
... |
674 |
17 |
1 |
— |
674 |
17 |
1 |
In progress. |
62 |
Veterinary College, Ballsbridge—Consulting Room |
... |
... |
... |
... |
... |
331 |
7 |
4 |
— |
331 |
7 |
4 |
In progress. |
64 |
Veterinary College, Ballsbridge—Library Accommodation (Hume House) |
... |
... |
1,588 |
19 |
6 |
— |
1,588 |
19 |
6 |
Completed. |
85 |
Veterinary College, Ballsbridge—Canteen |
... |
... |
... |
... |
... |
... |
3 |
11 |
9 |
— |
3 |
11 |
9 |
In progress. |
90/56 of 1965/66 |
Chantilly Stud Farm—New Laboratory |
... |
... |
... |
... |
... |
... |
578 |
3 |
11 |
270 |
16 |
3 |
849 |
0 |
2 |
Completed. |
59 |
Chantilly Stud Farm—Provision of stalls |
... |
... |
... |
... |
... |
... |
152 |
9 |
0 |
— |
152 |
9 |
0 |
Completed. |
90/54 of 1965/66 |
Athenry Agricultural School—Adaptation |
... |
... |
... |
... |
... |
... |
47 |
0 |
0 |
954 |
3 |
4 |
1,001 |
3 |
4 |
Completed. |
41 |
Thorndale Pig Progeny Station—Improvements |
... |
... |
... |
... |
... |
571 |
18 |
0 |
— |
571 |
18 |
0 |
Completed. |
43 |
Athenry Agricultural School—Accommodation for Western Regional Officer |
... |
130 |
18 |
9 |
— |
130 |
18 |
9 |
In progress. |
90/50 of 1965/66 |
District Veterinary Office, Cork—Adaptations etc. |
... |
... |
... |
... |
... |
64 |
1 |
2 |
358 |
5 |
6 |
422 |
6 |
8 |
Completed. |
8 |
District Veterinary Office, Tralee—Improvements |
... |
... |
... |
... |
... |
231 |
0 |
4 |
— |
231 |
0 |
4 |
Completed. |
76/73 of 1964/65 |
Bovine T.B. Office, Sligo—Improvements |
... |
... |
... |
... |
... |
... |
573 |
1 |
3 |
385 |
8 |
4 |
957 |
9 |
7 |
Completed. |
|
Department of Industry and Commerce: |
|
|
|
|
|
|
|
|
|
|
60 |
Foras Tionscail—Improved Accommodation |
... |
... |
... |
... |
... |
... |
1,012 |
14 |
7 |
— |
1,012 |
14 |
7 |
In progress. |
|
Department of Transport and Power: |
|
|
|
|
|
|
|
|
|
|
76/30 of 1964/65 |
Valentia Observatory—Improvements |
... |
... |
... |
... |
... |
... |
... |
51 |
5 |
10 |
904 |
14 |
10 |
956 |
0 |
8 |
Completed. |
90/88 of 1965/66 |
Valentia Observatory—Fencing |
... |
... |
... |
... |
... |
... |
... |
... |
979 |
16 |
9 |
405 |
5 |
0 |
1,385 |
1 |
9 |
In progress. |
90/51 of 1965/66 |
Meteorological Station, Malin Head—New Building and Mast |
... |
... |
... |
256 |
14 |
2 |
600 |
0 |
0 |
856 |
14 |
2 |
In progress. |
|
Department of Posts and Telegraphs: |
|
|
|
|
|
|
|
|
|
|
90/43 of 1965/66 |
General Post Office, Dublin—Alterations to Telex Room |
... |
... |
... |
... |
491 |
10 |
0 |
863 |
15 |
0 |
1,355 |
5 |
0 |
Completed. |
9 |
General Post Office, Dublin—Kitchen Equipment |
... |
... |
... |
... |
... |
149 |
2 |
6 |
— |
149 |
2 |
6 |
In progress. |
90/63 of 1965/66 |
Aldboro House—Improved Canteen facilities |
... |
... |
... |
... |
... |
... |
41 |
13 |
7 |
53 |
0 |
11 |
94 |
14 |
6 |
Completed. |
90/81 of 1965/66 |
Aldboro House—Additional Accommodation |
... |
... |
... |
... |
... |
... |
121 |
11 |
7 |
57 |
13 |
5 |
179 |
5 |
0 |
Completed. |
90/49 of 1965/66 |
Castlebar Post Office—Sanitary Accommodation |
... |
... |
... |
... |
... |
66 |
16 |
5 |
961 |
10 |
8 |
1,028 |
7 |
1 |
Completed. |
12 |
Sligo Post Office—Installation of petrol tank |
... |
... |
... |
... |
... |
... |
660 |
17 |
0 |
— |
660 |
17 |
0 |
Completed. |
38 |
Tipperary Post Office—Provision of oil store |
... |
... |
... |
... |
... |
... |
297 |
15 |
0 |
— |
297 |
15 |
0 |
Completed. |
39 |
Westport Post Office—Improvements |
... |
... |
... |
... |
... |
... |
... |
630 |
0 |
0 |
— |
630 |
0 |
0 |
In progress. |
56 |
Tralee Post Office—Installation of electric petrol pump |
... |
... |
... |
... |
196 |
0 |
0 |
— |
196 |
0 |
0 |
Completed. |
|
Department of Defence: |
|
|
|
|
|
|
|
|
|
|
90/75 of 1965/66 |
Arbour Hill—Memorial Tablet |
... |
... |
... |
... |
... |
... |
... |
... |
379 |
19 |
0 |
125 |
0 |
0 |
504 |
19 |
0 |
Completed. |
|
Department of External Affairs: |
|
|
|
|
|
|
|
|
|
|
90/83 of 1965/66 |
30 Earlsfort Terrace—Adaptations |
... |
... |
... |
... |
... |
... |
... |
626 |
6 |
11 |
249 |
4 |
5 |
875 |
11 |
4 |
Completed. |
|
Department of Social Welfare: |
|
|
|
|
|
|
|
|
|
|
90/71 of 1965/66 |
Aras Mhic Dhiarmada—Partitions |
... |
... |
... |
... |
... |
... |
... |
1 |
17 |
4 |
180 |
15 |
11 |
182 |
13 |
3 |
Completed. |
16 |
Aras Mhic Dhiarmada—Sanitary Improvements |
... |
... |
... |
... |
... |
138 |
2 |
9 |
— |
138 |
2 |
9 |
Completed. |
|
Employment Exchanges: |
|
|
|
|
|
|
|
|
|
|
33 |
Cork—Improvements |
... |
... |
... |
... |
... |
... |
... |
... |
... |
428 |
12 |
0 |
— |
428 |
12 |
0 |
Completed. |
13 |
Dublin, Beresford Place—Heating Improvements |
... |
... |
... |
... |
... |
588 |
16 |
5 |
— |
588 |
16 |
5 |
Completed. |
28 |
Dublin, Beresford Place—Sanitary Improvements |
... |
... |
... |
... |
... |
927 |
12 |
9 |
— |
927 |
12 |
9 |
Completed. |
24 |
Dublin, Gardiner St.—Adaptations |
... |
... |
... |
... |
... |
... |
... |
471 |
6 |
3 |
— |
471 |
6 |
3 |
Completed. |
48 |
Dublin, Gardiner St.—Improvements |
... |
... |
... |
... |
... |
... |
... |
293 |
16 |
9 |
— |
293 |
16 |
9 |
Completed. |
23 |
Dublin, Victoria St.—Improvements |
... |
... |
... |
... |
... |
... |
... |
114 |
17 |
6 |
— |
114 |
17 |
6 |
Completed. |
36 |
Dublin, Werburgh St.—Improvements |
... |
... |
... |
... |
... |
... |
... |
493 |
12 |
9 |
— |
493 |
12 |
9 |
Completed. |
42 |
Galway—Improvements |
... |
... |
... |
... |
... |
... |
... |
... |
... |
46 |
10 |
8 |
— |
46 |
10 |
8 |
Practically completed. |
90/68 of 1965/66 |
Waterford—Heating Improvements |
... |
... |
... |
... |
... |
... |
... |
56 |
0 |
0 |
1,253 |
17 |
5 |
1,309 |
17 |
5 |
Completed. |
|
Department of Health: |
|
|
|
|
|
|
|
|
|
|
35 |
Custom House, Dublin—Adaptations |
... |
... |
... |
... |
... |
... |
... |
451 |
6 |
1 |
— |
451 |
6 |
1 |
Completed. |
47 |
Custom House, Dublin—Partitioning |
... |
... |
... |
... |
... |
... |
... |
178 |
2 |
4 |
— |
178 |
2 |
4 |
Completed. |
|
|
27,349 |
8 |
9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DETAILS OF No. 65—URGENT AND UNFORESEEN WORKS.
Work No. |
Service and Description |
Expenditure |
Observations |
1966-67 |
To 31/3/66 |
To 31/3/67 |
|
|
£ |
s. |
d. |
£ |
s. |
d. |
£ |
s. |
d. |
|
|
Department of Finance: |
|
|
|
|
|
|
|
|
|
|
|
Revenue Commissioners: |
|
|
|
|
|
|
|
|
|
|
2 |
Arus Brugha—Installation of Computer |
... |
... |
... |
... |
... |
... |
3,314 |
7 |
5 |
— |
3,314 |
7 |
5 |
In progress. |
|
Department of Lands: |
|
|
|
|
|
|
|
|
|
|
1 |
23/24 Upr. Merrion St.—Installation of Computer |
... |
... |
... |
... |
... |
9,225 |
17 |
3 |
— |
9,225 |
17 |
3 |
In progress. |
|
|
£12,540 |
4 |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DETAILS OF No. 66—MINOR BALANCES OF EXPENDITURE.
Work No. |
Service and Description |
Expenditure |
Observations |
1966-67 |
To 31/3/66 |
To 31/3/67 |
|
|
£ |
s. |
d. |
£ |
s. |
d. |
£ |
s. |
d. |
|
|
Department of An Taoiseach: |
|
|
|
|
|
|
|
|
|
|
4 of 1964/65 |
Central Statistics Office—New Accommodation |
... |
... |
... |
... |
... |
456 |
15 |
0 |
39,477 |
16 |
0 |
39,934 |
11 |
0 |
Completed. |
|
Department of Finance: |
|
|
|
|
|
|
|
|
|
|
4A of 1963/64 |
Transfer of staff to 64/65 Merrion Square |
... |
... |
... |
... |
... |
... |
15 |
7 |
6 |
4,201 |
18 |
6 |
4,217 |
6 |
0 |
Completed. |
17 of 1964/65 |
Ordnance Survey Office—Extension and Adaptation |
... |
... |
... |
... |
... |
129 |
5 |
6 |
5,637 |
0 |
9 |
5,766 |
6 |
3 |
Completed. |
18 (1) of 1964/65 |
Phoenix Park—Improvement of Water Supply |
... |
... |
... |
... |
... |
676 |
1 |
6 |
34,477 |
0 |
1 |
35,153 |
1 |
7 |
Completed. |
8 of 1965/66 |
Revenue Commissioners, Additional Accommodation—Hawkins House, Dublin |
... |
1,135 |
10 |
3 |
14,928 |
13 |
7 |
16,064 |
3 |
10 |
Completed. |
9 of 1965/66 |
Revenue Commissioners, Dublin Castle—Rebuilding of Cross Block |
... |
... |
1,892 |
2 |
7 |
143,791 |
12 |
0 |
145,683 |
14 |
7 |
Completed. |
90 (77/70 of 1962/63) |
Revenue Commissioners, Limerick—Improvements, etc. |
... |
... |
... |
... |
13 |
7 |
6 |
2,666 |
17 |
9 |
2,680 |
5 |
3 |
Completed. |
90 (76/41 of 1964/65) |
Office of Public Works: Thurles District Office—New Structure |
... |
... |
... |
310 |
13 |
0 |
1,838 |
16 |
0 |
2,149 |
9 |
0 |
Completed. |
18 of 1965/66 |
Office of Public Works, Dublin Central Building Maintenance Workshops— |
|
|
|
|
|
|
|
|
|
|
|
Adaptation and Equipment |
... |
... |
... |
... |
... |
... |
... |
... |
... |
933 |
13 |
5 |
3,769 |
13 |
1 |
4,703 |
6 |
6 |
Stage I completed. |
19 of 1965/66 |
State Laboratory—College of Science—Renewal of Goods and Passenger Lift |
... |
1,213 |
3 |
5 |
3,031 |
9 |
9 |
5,144 |
13 |
2 |
Completed. |
22 of 1965/66 |
Irish Red Cross Society—Accommodation, 16 Merrion Square |
... |
... |
... |
384 |
17 |
11 |
5,668 |
11 |
7 |
6,053 |
9 |
6 |
Practically completed. |
23 of 1965/66 |
Phoenix Park—Erection of new Glasshouse |
... |
... |
... |
... |
... |
... |
100 |
0 |
0 |
4,894 |
4 |
10 |
4,994 |
4 |
10 |
Completed. |
|
Department of Justice: |
|
|
|
|
|
|
|
|
|
|
26 of 1965/66 |
Additional Accommodation, Pembroke Street, (Dublin) |
... |
... |
... |
... |
95 |
1 |
9 |
14,772 |
0 |
11 |
14,867 |
2 |
8 |
|
|
Department of Education: |
|
|
|
|
|
|
|
|
|
|
78/2 of 1963/64 |
Central Model Schools, Marlboro Street—Adaptations, etc. |
... |
... |
... |
... |
564 |
8 |
7 |
7,470 |
14 |
5 |
8,035 |
3 |
0 |
Completed. |
36 of 1965/66 |
Additional Accommodation—Hawkins House, Dublin |
... |
... |
... |
... |
256 |
0 |
2 |
14,193 |
11 |
8 |
14,449 |
11 |
10 |
Completed. |
40 of 1965/66 |
National College of Art—Additional Accommodation |
... |
... |
... |
... |
... |
18 |
1 |
4 |
3,972 |
12 |
4 |
3,990 |
13 |
8 |
Completed. |
|
Department of Lands: |
|
|
|
|
|
|
|
|
|
|
46 of 1965/66 |
22 Upper Merrion Street, Dublin—Formation of a Car Park |
... |
... |
... |
... |
289 |
0 |
0 |
2,606 |
10 |
0 |
2,895 |
10 |
0 |
Completed. |
|
Department of Agriculture |
|
|
|
|
|
|
|
|
|
|
40 (1) of 1962/63 |
Abbotstown Farm—Artificial Insemination Experimental Station |
... |
... |
... |
1,929 |
16 |
10 |
21,717 |
2 |
6 |
23,646 |
19 |
4 |
Completed. |
40 (5) of 1962/63 |
Abbotstown Farm—Residence for Farm Manager |
... |
... |
... |
... |
... |
414 |
11 |
2 |
3,364 |
0 |
8 |
3,778 |
11 |
10 |
Completed. |
40/2 of 1963/64 |
Veterinary College, Ballsbridge—Improvements |
... |
... |
... |
... |
... |
19 |
13 |
1 |
19,800 |
0 |
1 |
19,819 |
13 |
2 |
Completed. |
47 (1) of 1963/64 |
Munster Institute—Fire Precaution Works |
... |
... |
... |
... |
... |
... |
445 |
6 |
4 |
2,238 |
15 |
11 |
2,684 |
2 |
3 |
Completed. |
73/1 of 1963/64 |
Bovine T.B. Office, Limerick—Improvements and Adaptations |
... |
... |
... |
54 |
18 |
8 |
2,288 |
9 |
5 |
2,343 |
8 |
1 |
Completed. |
77/3 of 1964/65 |
Thorndale Veterinary Laboratory—Adaptations |
... |
... |
... |
... |
... |
923 |
6 |
5 |
4,653 |
2 |
2 |
5,576 |
8 |
7 |
|
53 (3) of 1965/66 |
Botanic Gardens—Classroom/Laboratory Accommodation |
... |
... |
... |
... |
397 |
5 |
3 |
6,048 |
6 |
2 |
6,445 |
11 |
5 |
Completed. |
56 (4) of 1965/66 |
Abbotstown Farm—Residence for Director |
... |
... |
... |
... |
... |
... |
928 |
6 |
4 |
4,728 |
3 |
6 |
5,656 |
9 |
10 |
Completed. |
58 of 1965/66 |
Backweston Farm—New Farm Buildings |
... |
... |
... |
... |
... |
... |
8 |
2 |
0 |
2,282 |
5 |
2 |
2,290 |
7 |
2 |
Deferred. |
63 of 1965/66 |
Thorndale—Detention Station for Imported Livestock |
... |
... |
... |
... |
152 |
17 |
1 |
17,381 |
14 |
5 |
17,534 |
11 |
6 |
Completed. |
|
Department of Posts and Telegraphs: |
|
|
|
|
|
|
|
|
|
|
57 OF 1964/65 |
Dublin (Finglas) New District Sorting Office and Telephone Exchange |
... |
... |
25 |
19 |
3 |
16,789 |
4 |
5 |
16,815 |
3 |
8 |
Virtually completed. |
61 of 1964/65 |
Arklow Post Office—Improvements and new Telephone Exchange |
... |
... |
... |
418 |
9 |
7 |
18,534 |
7 |
1 |
18,952 |
16 |
8 |
Completed. |
62 of 1964/65 |
Ballinasloe—New Post Office and Telephone Exchange |
... |
... |
... |
... |
135 |
6 |
1 |
25,682 |
14 |
8 |
25,818 |
0 |
9 |
Completed. |
65 of 1964/65 |
Ennis Post Office—Improvements and New Telephone Exchange |
... |
... |
... |
902 |
10 |
2 |
10,852 |
3 |
2 |
11,754 |
13 |
4 |
Completed. |
69 of 1964/65 |
Wicklow—New Post Office and Telephone Exchange |
... |
... |
... |
... |
5 |
1 |
0 |
31,782 |
9 |
6 |
31,787 |
10 |
6 |
Completed. |
74 of 1965/66 |
Dún Laoghaire—New Engineering Headquarters and Garage |
... |
... |
... |
409 |
0 |
0 |
2,095 |
14 |
4 |
2,504 |
14 |
4 |
Completed. |
80 of 1965/66 |
Kilkenny New Telephone Exchange and Area Engineering Headquarters |
... |
... |
163 |
0 |
0 |
1,046 |
19 |
8 |
1,209 |
19 |
8 |
Completed. |
|
Department of Defence: |
|
|
|
|
|
|
|
|
|
|
83 (1) of 1965/66 |
School of Civil Defence—Improved Accommodation |
... |
... |
... |
... |
... |
451 |
11 |
7 |
29,730 |
15 |
5 |
30,182 |
7 |
0 |
Completed. |
|
Department of Health: |
|
|
|
|
|
|
|
|
|
|
71 of 1963/64 |
Central Mental Hospital, Dundrum—New Residence for Governor |
... |
... |
... |
32 |
11 |
1 |
7,580 |
8 |
10 |
7,612 |
19 |
11 |
Completed. |
|
Total for Minor Balances |
... |
£16,301 |
1 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|