Committee Reports::Report - Appropriation Accounts 1965 - 1966::14 July, 1967::Appendix

Qn. 174.


APPENDIX XIII.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1965-66 (VOTE 8, SUBHEAD E).

Work
No.

Service and Description

Total
Estimate

Vote
1965-66

Expenditure

Observations

1965-66

To 31/3/65

To 31/3/66

 

 

£

£

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Oireachtas

 

 

 

 

 

 

 

 

 

 

 

 

1

Leinster House—Extension and Alterations

...

...

...

...

526,000

250,000

202,989

13

10

262,580

18

5

465,570

12

3

Partially completed.

 

Total:

 

 

250,000

202,989

13

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of the Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

 

2

Dublin Castle—State Apartments—Rebuilding of burnt-out Drawing

 

 

 

 

 

 

 

 

 

 

 

 

 

Room and former Bedroom Block

...

...

...

...

...

310,000

150,000

147,431

16

1

49,228

7

6

196,660

3

7

In progress.

 

Total:

 

 

150,000

147,431

16

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

 

3

Additional Accommodation—O’Connell Bridge House, Dublin

...

4,500

1,500

4,519

3

9

4,519

3

9

Completed.

4

Statue to Thomas Davis

...

...

...

...

...

...

...

15,000

10,000

13,772

11

3

1,964

8

5

15,736

19

8

Completed.

5

State Memorial to the late President J. F. Kennedy

...

...

...

2,000,000

50,000

2,747

8

1

205

5

6

2,952

13

7

In Planning.

6

Central Heating Station—Renewal of Plant

...

...

...

...

63,000

10,000

15,560

17

0

46,685

11

11

62,246

8

11

Virtually completed.

7

State Buildings—Kildare St., Merrion St. Upper—New Electricity

 

 

 

 

 

 

 

 

 

 

 

 

 

Distribution System

...

...

...

...

...

...

...

20,000

15,000

1,247

1

7

1,247

1

7

In planning.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

 

 

8

Additional Accommodation—Hawkins House, Dublin

...

...

18,000

8,000

14,928

13

7

14,928

13

7

Completed.

9

Dublin Castle—Rebuilding of Cross Block

...

...

...

...

143,000

11,000

13,219

16

1

130,571

15

11

143,791

12

0

Completed.

10

Dublin Castle—Stamping Branch—new premises

...

...

...

650,000

25,000

4,620

13

9

19,153

14

2

23,774

7

11

Deferred.

11

New Customs Frontier Posts

...

...

...

...

...

...

12,000

11,500

8,557

17

5

8,557

17

5

In progress.

12

Blacklion Customs Frontier Post—New Office, Road Station and

 

 

 

 

 

 

 

 

 

 

 

 

 

Residences

...

...

...

...

...

...

...

...

20,000

1,000

Deferred.

13

Dundalk—New Customs Road Station

...

...

...

...

27,500

15,000

17,677

0

0

7,066

16

9

24,743

16

9

Virtually completed.

14

Rosslare Harbour—Residence for Customs and Excise Surveyor

...

3,750

2,000

Deferred.

15

Waterford—New Government Offices

...

...

...

...

...

140,000

3,000

Deferred.

16

Wexford—New Government Offices and Telephone Exchange

...

48,000

4,500

12,087

2

4

38,060

10

10

50,147

13

2

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

 

 

17

Alterations

...

...

...

...

...

...

...

...

11,000

6,500

5,284

5

4

1,878

4

6

7,162

9

10

Part completed, Part deferred.

17a

10 Hume Street—National Monuments—Dark Room

...

...

2,400

900

0

0

900

0

0

In progress.

18

Dublin Central Building Maintenance Workshops—Adaptation and

 

 

 

 

 

 

 

 

 

 

 

 

 

Equipment

...

...

...

...

...

...

...

...

35,000

10,000

3,161

6

4

608

6

9

3,769

13

1

Part completed.

19

State Laboratory—College of Science—Renewal of Goods and

 

 

 

 

 

 

 

 

 

 

 

 

 

Passenger Lift

...

...

...

...

...

...

...

...

6,000

2,000

3,884

10

10

46

18

11

3,931

9

9

Completed.

20

Stationery Office—New Building

...

...

...

...

...

350,000

500

In planning.

21

Government Publications Sale Office—Additional Accommodation

5,000

4,500

Deferred.

22

Irish Red Cross Society—Accommodation 16 Merrion Square

...

5,800

5,500

5,668

11

7

5,668

11

7

Completed.

23

Phoenix Park—Erection of new glasshouse

...

...

...

...

4,500

700

4,164

4

10

730

0

0

4,894

4

10

Completed.

24 (1)

Rotunda Gardens—Garden of Remembrance—Architectural Works

166,000

15,000

14,270

9

6

145,045

15

0

159,316

4

6

Completed.

24 (2)

Garden of Remembrance—Memorial Sculpture

...

...

...

30,000

1,000

Under consideration.

25

Dun-Laoghaire Harbour—Car Ferry Terminal

...

...

...

850,000

270,000

206,729

16

4

71,582

8

3

278,312

4

7

In progress.

 

Total:

 

 

483,200

351,754

8

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

 

 

26

Additional Accommodation, Pembroke Street, (Dublin)

...

...

13,500

2,000

5,877

9

2

8,894

11

9

14,772

0

11

Part completed.

27

Memorial to Gárdaí who lost their lives in the performance of duty

13,900

2,000

4,411

0

0

7,574

0

0

11,985

0

0

Completed.

28

Gárda Siochana Depot—Extension of Garage and Workshop

 

 

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

...

...

71,000

50,000

15,750

0

0

1,353

17

2

17,103

17

2

In progress.

29

New Gárda Training Centre Templemore—Adaptations, etc.

...

634,000

60,000

20,742

0

0

596,892

12

0

617,634

12

0

Virtually completed.

30

Erection of New Gárda Síochána Stations

...

...

...

...

 

150,000

105,627

10

4

 

 

 

 

 

 

 

 

 

 

 

Detailed as follows:

 

 

 

 

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

 

 

 

 

 

 

Crumlin

...

...

...

...

...

...

...

...

 

 

2,824

4

0

55,812

8

8

58,636

12

8

Completed.

 

County Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballyconnell

...

...

...

...

...

...

...

...

 

 

1,604

14

7

13,678

2

11

15,282

17

6

Completed.

 

Blacklion

...

...

...

...

...

...

...

...

 

 

2,561

0

0

3,690

0

0

6,251

0

0

Completed.

 

Cootehill

...

...

...

...

...

...

...

...

 

 

1,135

0

3

6,887

0

0

8,022

0

3

Completed.

 

County Clare:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ardnacrusha

...

...

...

...

...

...

...

 

 

2,880

0

0

1,350

0

0

4,230

0

0

In progress.

 

Inagh

...

...

...

...

...

...

...

...

 

 

5,370

0

0

1,239

12

6

6,609

12

6

Completed.

 

Labasheeda

...

...

...

...

...

...

...

...

 

 

1,028

9

1

6,303

17

6

7,332

6

7

Completed.

 

County Cork:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bantry

...

...

...

...

...

...

...

...

 

 

1,011

16

11

10,077

10

3

11,089

7

2

Completed.

 

Castletownroche

...

...

...

...

...

...

...

 

 

1,082

13

8

7,353

0

0

8,435

13

8

Completed.

 

Donoughmore

...

...

...

...

...

...

...

 

 

841

1

4

5,035

0

0

5,876

1

4

Completed.

 

Kinsale

...

...

...

...

...

...

...

 

 

838

16

9

7,060

0

0

7,898

16

9

Completed.

 

Roscarbery

...

...

...

...

...

...

...

...

 

 

1,150

18

2

7,980

0

0

9,130

18

2

Completed.

 

Youghal

...

...

...

...

...

...

...

...

 

 

1,942

17

2

10,260

0

0

12,202

17

2

Completed.

 

County Donegal

 

 

 

 

 

 

 

 

 

 

 

 

 

Ardara

...

...

...

...

...

...

...

...

 

 

3,690

0

0

2,295

0

0

5,985

0

0

Completed.

 

Burtonport

...

...

...

...

...

...

...

...

 

 

1,197

0

0

6,365

0

0

7,562

0

0

Completed.

 

Carndonagh

...

...

...

...

...

...

...

...

 

 

2,194

13

11

6,460

0

0

8,654

13

11

Completed.

 

Castlefin

...

...

...

...

...

...

...

...

 

 

1,140

9

1

6,650

0

0

7,790

9

1

Completed.

 

County Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

 

Clondalkin

...

...

...

...

...

...

...

...

 

 

3,210

8

0

11,631

15

2

14,842

3

2

Completed.

 

County Galway

 

 

 

 

 

 

 

 

 

 

 

 

 

Ahascragh

...

...

...

...

...

...

...

...

 

 

149

19

0

6,751

13

3

6,901

12

3

Completed.

 

Killimor

...

...

...

...

...

...

...

...

 

 

3,915

0

0

3,915

0

0

In progress.

 

County Kerry:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballylongford

...

...

...

...

...

...

...

 

 

450

0

0

450

0

0

In progress.

 

Kilgarvan

...

...

...

...

...

...

...

...

 

 

4,040

0

0

1,053

0

0

5,093

0

0

Completed.

 

County Laois:

 

 

 

 

 

 

 

 

 

 

 

 

 

Abbeyleix

...

...

...

...

...

...

...

...

 

 

8,730

0

0

8,730

0

0

In progress.

 

Ballacolla

...

...

...

...

...

...

...

...

 

 

194

0

0

194

0

0

Deferred.

 

Ballickmoyler

...

...

...

...

...

...

...

 

 

194

2

6

194

2

6

Plans completed.

 

County Leitrim:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballinamore

...

...

...

...

...

...

...

 

 

22

0

0

7,790

0

0

7,812

0

0

Completed.

 

County Longford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Keenagh

...

...

...

...

...

...

...

 

 

2,430

0

0

2,430

0

0

In progress.

 

County Louth:

 

 

 

 

 

 

 

 

 

 

 

 

 

Castlebellingham

...

...

...

...

...

...

...

 

 

537

11

2

7,362

0

0

7,899

11

2

Completed.

 

County Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Laherdane

...

...

...

...

...

...

...

...

 

 

140

0

0

140

0

0

Deferred.

 

County Meath

 

 

 

 

 

 

 

 

 

 

 

 

 

Crossakiel

...

...

...

...

...

...

...

...

 

 

1,980

0

0

237

0

0

2,217

0

0

In progress.

 

Dunboyne

...

...

...

...

...

...

...

...

 

 

5,082

0

0

3,420

0

0

8,502

0

0

Completed.

 

Slane

...

...

...

...

...

...

...

...

...

 

 

270

0

0

6,706

0

0

6,976

0

0

Completed.

 

County Monaghan:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballybay

...

...

...

...

...

...

...

...

 

 

760

0

0

6,650

0

0

7,410

0

0

Completed.

 

Clones

...

...

...

...

...

...

...

...

 

 

5,850

0

0

5,850

0

0

In progress.

 

Emyvale

...

...

...

...

...

...

...

 

 

7,110

0

0

7,110

0

0

In progress.

 

County Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

 

Shinrone

...

...

...

...

...

...

...

...

 

 

3,510

0

0

3,510

0

0

In progress.

 

County Sligo

 

 

 

 

 

 

 

 

 

 

 

 

 

Collooney

...

...

...

...

...

...

...

...

 

 

434

0

0

8,252

17

6

8,686

17

6

Completed.

 

Tubercurry

...

...

...

...

...

...

...

...

 

 

618

0

0

7,125

0

0

7,743

0

0

Completed.

 

County Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballingarry North

...

...

...

...

...

...

...

 

 

3,060

0

0

2,300

6

0

5,360

6

0

Completed.

 

Fethard

...

...

...

...

...

...

...

...

 

 

6,480

0

0

1,260

0

0

7,740

0

0

In progress.

 

County Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Courtown

...

...

...

...

...

...

...

...

 

 

3,015

0

0

2,835

0

0

5,850

0

0

In progress.

 

Enniscorthy

...

...

...

...

...

...

...

...

 

 

4,950

0

0

4,950

0

0

In progress.

 

Glynn

...

...

...

...

...

...

...

...

...

 

 

223

14

9

8,915

16

4

9,139

11

1

Completed

 

County Wicklow

 

 

 

 

 

 

 

 

 

 

 

 

 

Rathdrum

...

...

...

...

...

...

...

...

 

 

5,778

0

0

5,400

0

0

11,178

0

0

Completed.

31

Improvement schemes at existing Gárda Síochána Stations

...

 

40,000

38,155

19

2

 

 

 

 

 

detailed as follows:

 

 

 

 

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

 

 

 

 

 

26/49 of 1964-5

Bridewell

...

...

...

...

...

...

...

...

 

 

507

2

11

137

1

10

644

4

9

Completed.

36

Clontarf

...

...

...

...

...

...

...

...

 

 

2,347

15

0

2,347

15

0

Completed.

26/58 of 1964-5

Depot Hospital

...

...

...

...

...

...

...

 

 

69

0

0

835

8

6

904

8

6

Completed.

18

Dun Laoghaire

...

...

...

...

...

...

...

...

 

 

36

7

6

36

7

6

In progress

39

Irishtown

...

...

...

...

...

...

...

...

...

 

 

258

11

 

258

11

8

Completed.

26/15 of 1964-5

Kill O’Grange

...

...

...

...

...

...

...

 

 

412

8

6

1,200

0

0

1,612

8

6

Completed.

26/22 of 1964-5

Sundrive Road

...

...

...

...

...

...

...

 

 

37

12

0

293

15

0

331

7

0

Completed.

 

County Carlow:

 

 

 

 

 

 

 

 

 

 

 

 

13

Rathvilly

...

...

...

...

...

...

...

...

...

 

 

1,215

0

0

1,215

0

0

Completed.

 

County Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

46

Dowra

...

...

...

...

...

...

...

...

 

 

1,129

15

6

1,129

15

6

Completed.

 

County Cork:

 

 

 

 

 

 

 

 

 

 

 

 

26/68 of 1964-5

Ballyvourney

...

...

...

...

...

...

...

 

 

243

8

0

700

0

0

943

8

0

Completed.

26/10 of 1964-5

Baltimore

...

...

...

...

...

...

...

...

 

 

142

16

1

300

0

0

442

16

1

Completed.

49

Castlemartyr

...

...

...

...

...

...

...

...

 

 

147

0

0

147

0

0

Completed.

66

Castletownbere

...

...

...

...

...

...

...

 

 

884

0

0

884

0

0

Completed.

42

Clonakilty

...

...

...

...

...

...

...

...

 

 

2,100

0

0

2,100

0

0

In progress.

65

Crosshaven

...

...

...

...

...

...

...

...

 

 

297

15

0

297

15

0

Completed.

26/73 of 1964-5

McCurtain St., Cork

...

...

...

...

...

...

 

 

501

9

1

11

13

5

513

2

6

In progress.

26

Schull

...

...

...

...

...

...

...

...

...

 

 

1,214

8

10

1,214

8

10

Completed.

26/72 of 1964-5

Union Quay, Cork

...

...

...

...

...

...

...

 

 

321

15

5

750

0

0

1,071

15

5

Completed.

40

Union Quay, Cork

...

...

...

...

...

...

...

 

 

293

0

0

293

0

0

In progress.

 

County Donegal

 

 

 

 

 

 

 

 

 

 

 

 

16

Falcarragh

...

...

...

...

...

...

...

...

 

 

1,686

5

0

1,686

5

0

Completed.

12

Mountcharles

...

...

...

...

...

...

...

 

 

823

9

1

823

9

1

Completed.

 

County Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

26/46 of 1964-5

Rathcoole

...

...

...

...

...

...

...

...

 

 

159

15

1

1,011

0

0

1,170

15

1

Completed.

64

Malahide

...

...

...

...

...

...

...

...

 

 

630

0

0

630

0

0

In progress.

 

County Galway:

 

 

 

 

 

 

 

 

 

 

 

 

22

Ardrahan

...

...

...

...

...

...

...

...

 

 

357

0

0

357

0

0

Completed.

68

Ballinasloe

...

...

...

...

...

...

...

...

 

 

241

14

0

241

14

0

Completed.

41

Corrandulla

...

...

...

...

...

...

...

...

 

 

900

0

0

900

0

0

Completed.

60

Gort

...

...

...

...

...

...

...

...

...

 

 

396

9

1

396

9

1

Completed.

54

Kiltullagh

...

...

...

...

...

...

...

...

 

 

128

7

6

128

7

6

Completed.

29

Kinvara

...

...

...

...

...

...

...

...

 

 

2,380

0

0

2,380

0

0

Completed.

26/63 of 1964-5

Loughrea

...

...

...

...

...

...

...

...

 

 

114

15

7

400

0

0

514

15

7

Completed.

26/57 of 1964-5

Maam

...

...

...

...

...

...

...

...

...

 

 

244

4

1

1,053

0

0

1,297

4

1

Completed.

37

Monivea

...

...

...

...

...

...

...

...

 

 

303

10

0

303

10

0

In progress.

26/45 of 1964-5

Tynagh

...

...

...

...

...

...

...

...

 

 

2,409

16

6

276

17

6

2,686

14

0

Completed.

67

Woodford

...

...

...

...

...

...

...

...

 

 

456

18

6

456

18

6

Completed.

 

County Kerry:

 

 

 

 

 

 

 

 

 

 

 

 

25/68 of 1963-4

Ballyduff

...

...

...

...

...

...

...

...

 

 

368

0

0

536

0

6

904

0

6

Completed.

75

Ballyferriter

...

...

...

...

...

...

...

 

 

126

10

0

126

10

0

Completed.

45

Lixnaw

...

...

...

...

...

...

...

...

 

 

298

0

0

298

0

0

Completed.

69

Kenmare

...

...

...

...

...

...

...

...

 

 

680

0

0

680

0

0

In progress.

48

Listowel

...

...

...

...

...

...

...

...

 

 

600

0

0

600

0

0

In progress.

 

County Kildare:

 

 

 

 

 

 

 

 

 

 

 

 

32

Kilcullen

...

...

...

...

...

...

...

...

 

 

360

0

0

360

0

0

Completed.

26/97 of 1964-5

Maynooth

...

...

...

...

...

...

...

...

 

 

1,491

0

0

1,316

0

0

2,807

0

0

Completed.

 

County Kilkenny:

 

 

 

 

 

 

 

 

 

 

 

 

8

Johnstown

...

...

...

...

...

...

...

...

 

 

148

10

0

148

10

0

Completed.

 

County Laois:

 

 

 

 

 

 

 

 

 

 

 

 

19

Rathdowney

...

...

...

...

...

...

...

 

 

1,628

4

6

1,628

4

6

Completed.

 

County Limerick

 

 

 

 

 

 

 

 

 

 

 

 

26/102 of 1964-5

Croom

...

...

...

...

...

...

...

...

 

 

121

17

2

170

0

0

291

17

2

Completed.

26/18 of 1964-5

Murroe

...

...

...

...

...

...

...

...

 

 

290

17

6

335

0

0

625

17

6

Completed.

26/5 of 1964-5

Newcastlewest

...

...

...

...

...

...

...

 

 

39

1

1

202

0

0

241

1

1

Completed.

 

County Longford:

 

 

 

 

 

 

 

 

 

 

 

 

74

Smear

...

...

...

...

...

...

...

...

 

 

160

0

0

160

0

0

Completed.

 

County Louth:

 

 

 

 

 

 

 

 

 

 

 

 

25

Drogheda

...

...

...

...

...

...

...

...

 

 

1,980

0

0

1,980

0

0

In progress.

14

Dundalk

...

...

...

...

...

...

...

...

 

 

540

0

0

540

0

0

Completed.

 

County Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

26/78 of 1964-5

Bellacorick

...

...

...

...

...

...

...

...

 

 

798

15

0

250

0

0

1,048

15

0

Completed.

57

Hollymount

...

...

...

...

...

...

...

 

 

855

0

0

855

0

0

In progress.

26/52 of 1964-5

Shrule

...

...

...

...

...

...

...

...

 

 

154

10

0

307

16

7

462

6

7

Completed.

 

County Meath:

 

 

 

 

 

 

 

 

 

 

 

 

73

Ashbourne

...

...

...

...

...

...

...

...

 

 

369

19

3

 

 

 

369

19

3

Completed.

20

Longwood

...

...

...

...

...

...

...

...

 

 

182

0

0

 

 

 

182

0

0

In progress.

30

Summerhill

...

...

...

...

...

...

...

...

 

 

152

10

6

 

 

 

152

10

6

Completed.

 

County Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

70

Birr

...

...

...

...

...

...

...

...

...

 

 

440

14

3

 

 

 

440

14

3

Completed.

28

Tullamore

...

...

...

...

...

...

...

...

 

 

357

5

6

 

 

 

357

5

6

Completed.

 

County Roscommon:

 

 

 

 

 

 

 

 

 

 

 

 

15

Ballyfarnon

...

...

...

...

...

...

...

...

 

 

811

15

0

 

 

 

811

15

0

Completed.

 

County Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

27

Buninadden

...

...

...

...

...

...

...

 

 

272

16

0

 

 

 

272

16

0

Completed.

76

Skreen

...

...

...

...

...

...

...

...

 

 

241

0

0

 

 

 

241

0

0

In progress.

 

County Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

52

Dundrum

...

...

...

...

...

...

...

...

 

 

140

0

0

 

 

 

140

0

0

Completed.

23

Kilsheelan

...

...

...

...

...

...

...

...

 

 

273

16

0

 

 

 

273

16

0

Completed.

26/66 of 1964-5

Templetouhy

...

...

...

...

...

...

 

 

267

15

0

500

0

0

767

15

0

Completed.

 

County Westmeath:

 

 

 

 

 

 

 

 

 

 

 

 

51

Castletown-Geoghegan

...

...

...

...

...

...

 

 

193

10

0

 

 

 

193

10

0

In progress.

 

County Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

21

Rosslare Strand

...

...

...

...

...

...

...

...

 

 

421

2

6

 

 

 

421

2

6

Completed.

32

Houses for Married Members of the Gárda Siochana

...

...

...

 

380,000

245,000

0

0

675,120

0

0

920,120

0

0

In progress.

33

Courts of Justice—Renewal of Defective Stonework

...

...

...

50,000

4,000

 

 

 

4,945

14

5

4,945

14

5

Stage 1 completed.

34

Land Registry—Additional Accommodation (Stage 11)

...

...

150,000

50,000

5,579

9

9

62

4

3

5,641

14

0

In progress.

 

Total:

 

 

738,000

441,143

8

5

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

 

 

35

Additional accommodation—O’Connell Bridge House, Dublin

...

16,500

5,000

22,069

1

11

 

 

 

22,069

1

11

Completed.

 

Total:

 

 

5,000

22,069

1

11

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

 

36

Additional Accommodation—Hawkins House, Dublin

...

...

12,000

5,000

14,193

11

8

 

 

 

14,193

11

8

Completed.

37

National Schools—Grants for Building, Enlarging, Enclosing, etc.

 

3,000,000

3,122,469

16

7

 

 

 

3,122,469

16

7

 

38

National Library—Fire Alarm System

...

...

...

...

6,750

6,750

 

 

 

 

 

 

 

 

 

In planning.

39

National Museum—Fire Alarm System

...

...

...

...

8,500

8,500

21

2

2

 

 

 

21

2

2

In planning.

39a

Royal Hospital Kilmainham—Improved Electrical System

...

...

 

 

2,275

0

0

 

 

 

2,275

0

0

Completed.

40

National College of Art—Additional Accommodation

...

...

3,600

3,000

3,972

12

4

 

 

 

3,972

12

4

Completed.

41

Coláiste Moibhí—Fire Precaution Works

...

...

...

...

2,000

850

764

14

7

1,595

9

7

2,360

4

2

Completed.

42

Dublin Preventive Centre

...

...

...

...

...

...

200,000

Nil

3,508

19

10

78

10

6

3,587

10

4

Deferred.

43

Dublin Institute for Advanced Studies—Accommodation

...

...

72,000

35,000

3,588

6

0

 

 

 

3,558

6

0

Deferred.

44

National Gallery—Extension

...

...

...

...

...

...

315,000

95,000

53,122

9

4

13,707

1

5

66,829

10

9

In progress.

 

Total:

 

 

3,154,100

3,263,916

12

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

 

45

21-29   31-33 Upper Merrion Street, Dublin Improvement of

 

 

 

 

 

 

 

 

 

 

 

 

 

Electrical and Heating Installations

...

...

...

...

...

35,000

7,500

687

7

3

3,175

1

4

3,862

8

7

Part Completed.

46

22 Upper Merrion Street, Dublin—Formation of a Car Park

...

2,500

700

2,606

10

0

 

 

 

2,606

10

0

Completed.

47

Avondale House—Adaptation as Forestry Training and Conference

 

 

 

 

 

 

 

 

 

 

 

 

 

Centre

...

...

...

...

...

...

...

...

...

40,000

22,500

19,803

6

5

850

0

0

20,653

6

5

In progress.

48

Galway Fisheries Research Station—Erection

...

...

...

150,000

500

 

 

 

 

 

 

 

 

 

Site being acquired.

49

Major Fisheries Harbours

...

...

...

...

...

...

1,631,000

195,000

151,985

17

0

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

 

 

Castletownbere ...

47,013

7

6

27,696

8

3

74,709

15

9

In progress.

 

 

 

Dunmore East

71,283

4

11

99,681

6

5

170,964,

11

4

In progress.

 

 

 

Galway ...

131

4

6

28,535

12

8

28,666

17

2

Preliminary investigations completed.

 

 

 

Howth ...

119

19

0

20,351

1

11

20,471

0

11

Preliminary investigations completed.

 

 

 

Killybegs ...

33,420

1

7

74,447

19

4

107,868

0

11

In progress.

 

 

 

Other expenditure (general)

17

19

6

14,533

4

1

14,551

3

7

 

50

Works of Economic Development at other Fishery Harbours

...

147,470

37,000

16,632

18

6

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

Ballynacarta

 

 

 

 

 

 

 

 

 

 

 

 

 

Slip ...

CR. 97

13

9

3,590

16

8

3,493

2

11

Completed.

 

 

 

Burtonport

 

 

 

 

 

 

 

 

 

 

 

 

 

Beacons ...

 

10

6

4,936

10

10

4,937

1

4

Completed.

 

 

 

Cahirciveen

 

 

 

 

 

 

 

 

 

 

 

 

 

Harbour ...

3,210

12

3

 

 

 

3,210

12

3

In progress.

 

 

 

Greencastle

CR 2,890

15

5

71,282

0

3

68,391

4

10

Completed.

 

 

 

Passage East

CR. 464

2

11

3,506

10

7

3,042

7

8

In progress.

 

 

 

Renard Point

16,309

4

3

701

14

6

17,010

18

9

In progress.

 

 

 

Skerries

 

 

 

 

 

 

 

 

 

 

 

 

 

Harbour ...

17

12

3

 

 

 

17

12

3

In planning.

 

 

 

Wicklow Slip

508

5

0

89

7

10

597

12

10

Completed.

 

 

 

Westport ...

39

6

4

 

 

 

39

6

4

In planning.

 

Total:

 

 

263,200

191,715

19

2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

 

 

51

Additional Accommodation—O’Connell Bridge House, Dublin

...

8,500

2,500

12,006

9

11

 

 

 

12,006

9

11

Completed.

52 (1)

Veterinary College Ballsbridge—New Radiography Unit and

 

 

 

 

 

 

 

 

 

 

 

 

 

Extension of Operating Theatre

...

...

...

...

...

14,500

10,000

 

 

 

 

 

 

 

 

 

In planning.

52 (2)

Veterinary College Ballsbridge—Extension

...

...

...

...

150,000

1,000

2,539

4

11

739

2

1

3,278

7

0

In planning.

53 (1)

Botanic Gardens—New Farm House

...

...

...

...

...

14,000

1,000

4,075

16

11

11,747

8

0

15,823

4

11

Completed.

53 (2)

Botanic Gardens—Accommodation for a Herbarium and Botanical

 

 

 

 

 

 

 

 

 

 

 

 

 

Collection

...

...

...

...

...

...

...

...

6,300

1,000

2,272

19

0

 

 

 

2,272

19

0

In progress.

53 (3)

Botanic Gardens—Classroom Laboratory Accommodation

...

...

6,400

1,500

2,448

6

2

3,600

0

0

6,048

6

2

Completed.

54

Butter Testing Station, Dublin—Extension

...

...

...

...

7,000

2,000

 

 

 

 

 

 

 

 

 

In planning.

55

Regional Veterinary and Dairy Produce Laboratories

...

...

100,000

25,000

7,105

11

2

 

 

 

7,105

1

2

Sligo: In progress. Athlone: Co. Limerick: Planning.

55A

Spike Island—Quarantine Station

...

...

...

...

...

39,000

 

12,223

14

4

24,756

2

0

36,979

16

4

Part Completed.

56 (1)

Abbotstown Farm—Experimental Animals Farmyard

...

...

71,000

10,000

9

18

4

57,134

8

11

57,144

7

3

Final Stage in planning.

56 (2)

Abbotstown Farm—Experimental Animals Accommodation

...

80,000

35,000

3,500

0

0

 

 

 

3,500

0

0

In planning.

56 (3)

Abbotstown Farm—Foundation Stock Farmyard

...

...

...

92,000

3,000

5,454

19

3

77,289

4

2

82,744

3

5

Nearing Completion.

56 (4)

Abbotstown Farm—Residence for Director

...

...

...

...

5,800

500

 

 

 

4,728

3

6

4,728

3

6

Completed.

56 (5)

Abbotstown Farm—Veterinary Field Station

...

...

...

148,000

70,000

104,184

13

11

56,413

13

6

160,598

7

5

Almost Completed.

57 (1)

Athenry Agricultural School—Improvement of Water Supply

...

15,000

4,000

4,090

10

10

1,399

16

4

5,490

7

2

In progress.

57 (2)

Athenry Agricultural School—New Building

...

...

...

...

110,000

2,500

9,074

14

1

104,063

13

0

113,138

7

 

Completed.

57 (3)

Athenry Agricultural School—Improvements to Turkey Hatchery

...

32,500

2,500

6,947

3

11

29,530

6

8

36,477

10

7

Completed.

57 (4)

Athenry Agricultural School—Erection of Employees’ Cottages

...

6,000

3,000

 

 

 

 

 

 

 

 

 

Deferred.

58

Backweston Farm—New Farm Buildings

...

...

...

...

72,000

37,500

1,280

1

8

1,002

3

6

2,282

5

2

Deferred.

59 (1)

Ballyhaise Agricultural School—Pig Progeny Testing Station

...

48,500

4,000

 

 

 

 

 

 

 

 

 

In planning.

59 (2)

Ballyhaise Agricultural School—Erection of new Brooder House

...

11,000

500

 

 

 

 

 

 

 

 

 

Deferred.

59 (3)

Ballyhaise Agricultural School—Fire Precaution Works and

 

 

 

 

 

 

 

 

 

 

 

 

 

Improvements to Heating System

...

...

...

...

...

4,500

2,600

1,434

13

6

1,888

10

0

3,323

3

6

In progress.

59 (4)

Ballyhaise Agricultural School—Sewage Disposal Scheme

...

...

6,000

5,000

232

16

1

 

 

 

232

16

1

In planning.

60 (1)

Clonakilty Agricultural School—New Building

...

...

...

110,000

2,500

10,953

10

9

99,544

0

10

110,497

11

7

Completed.

60 (2)

Clonakilty Agricultural School—Employees’ Cottages

...

...

11,340

4,000

2,217

0

0

9,633

0

0

11,850

0

0

Completed.

16

Kennedy Memorial Park, Co. Wexford—School of Horticulture, etc.

145,000

2,000

 

 

 

 

 

 

 

 

 

In planning.

62 (1)

Munster Institute—New Poultry Plant

...

...

...

...

100,000

16,000

14,758

0

0

17,166

6

7

31,924

6

7

Part Completed.

62 (2)

Munster Institute—Extension of Pig Progeny Testing Station

...

46,000

20,000

19,570

5

0

26,019

6

3

45,589

11

3

Virtually Completed.

63

Thorndale—Detention Station for Imported Livestock

...

...

16,100

1,000

1,146

18

11

16,234

15

6

17,381

14

5

Completed.

 

Total:

 

 

269,600

227,527

8

8

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

 

 

64

Additional Accommodation: Ansley House, Dublin

...

...

...

35,000

20,000

16,536

2

6

 

 

 

16,536

2

6

In progress.

 

Total:

 

 

20,000

16,536

2

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

 

 

65

Additional Accommodation—O’Connell Bridge House Dublin

...

3,000

1,000

3,466

11

2

 

 

 

3,466

11

2

Completed.

66

Clones Meteorological Station—Extension

...

...

...

...

4,350

500

800

0

0

3,150

0

0

3,150

0

0

Completed.

67

Mullingar—Erection of New Meteorological Station

...

...

...

4,000

3,000

 

 

 

 

 

 

 

 

 

Deferred.

68

Rosslare Harbour Meteorological Station—Residence for Officer in

 

 

 

 

 

 

 

 

 

 

 

 

 

Charge

...

...

...

...

...

...

...

...

...

3,750

2,000

 

 

 

 

 

 

 

 

 

Deferred.

69

Valentia Observatory—Improvement of Entrance Roadway

...

3,000

3,000

 

 

 

 

 

 

 

 

 

Deferred.

 

Total:

 

 

9,500

3,766

11

2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

 

 

70

Dublin—New Central Sorting Office

...

...

...

...

...

770,000

230 000

369,711

4

7

320,102

16

5

689,814

1

0

Nearing Completion.

71

Dublin—New District Sorting Office and Telephone Exchange— Coolock/Raheny

...

...

...

...

...

...

...

14,340

3,800

5,358

12

4

10,097

16

2

15,456

8

6

Completed.

72

Dublin—New Warehousing etc. Accommodation

...

...

...

190,000

50,000

60,500

0

0

25,903

16

7

86,403

16

7

In progress.

73

Blackrock, Co. Dublin, Post Office—Improvements

...

...

...

2,500

2,000

 

 

 

 

 

 

 

 

 

Deferred.

74

Dun Laoghaire—New Engineering Headquarters and Garage

...

2,150

1,100

1,316

18

9

778

15

7

2,095

14

4

Completed.

75

Dun Laoghaire Post Office—Improvements

...

...

...

...

55,500

4,000

357

10

9

 

 

 

357

10

9

In planning.

76

Carlow Post Office, Telephone Exchange and Government Buildings

95,000

30,000

1,088

6

6

1,386

0

0

2,474

6

6

In progress.

77

Clonmel—New Telephone Exchange, Engineering Stores, Office and

 

 

 

 

 

 

 

 

 

 

 

 

 

Garage, etc. Accommodation

...

...

...

...

...

2,000

400

 

 

 

 

 

 

 

 

 

Demolition work in progress.

78

Enniscorthy Post Office—Improvements

...

...

...

...

9,000

5,000

 

 

 

 

 

 

 

 

 

Deferred.

79

Greystones Post Office—Improvements

...

...

...

...

7,200

4,000

2,280

0

0

 

 

 

2,280

0

0

In progress.

80

Kilkenny New Telephone Exchange and Area Engineering

 

 

 

 

 

 

 

 

 

 

 

 

 

Head-quarters

...

...

...

...

...

...

...

...

1,250

400

669

0

0

377

19

8

1,046

19

8

Completed.

81

Killarney—New Telephone Exchange and additional Sorting Office,

 

 

 

 

 

 

 

 

 

 

 

 

 

etc., accommodation

...

...

...

...

...

...

...

35,000

200

 

 

 

 

 

 

 

 

 

Telephone Exchange in Planning, Sorting Office accommodation deferred

82

Youghal—New Post Office and Telephone Exchange

...

...

18,000

3,000

2,727

1

8

13,041

11

9

15,768

13

5

Completed.

 

Total:

 

 

333,900

444,008

14

7

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

 

83 (1)

School of Civil Defence—Improved Accommodation

...

...

26,500

1,000

1,484

0

0

28,246

15

5

29,730

15

5

Completed.

83 (2)

School of Civil Defence—Additional Accommodation

...

...

3,000

2,000

 

 

 

 

 

 

 

 

 

Under consideration.

84

Coláiste Caoimhín—Additional Accommodation for Civil Defence

 

 

 

 

 

 

 

 

 

 

 

 

 

Staff

...

...

...

...

...

...

...

...

...

2,600

1,500

 

 

 

 

 

 

 

 

 

Deferred.

 

Total:

 

 

4,500

1,484

0

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of External Affairs

 

 

 

 

 

 

 

 

 

 

 

 

85

Apostolic Nunciature—Improved accommodation

...

...

...

33,000

16,000

257

10

0

 

 

 

257

10

0

In planning.

86

Irish Embassy to Federation of Nigeria—Erection of

...

...

100,000

20,000

346

0

2

12,419

17

8

12,765

17

10

In planning.

 

(a) Residence for Ambassador and Secretary

 

 

 

 

 

 

 

 

 

 

 

 

 

(b) Offices.

 

 

 

 

 

 

 

 

 

 

 

 

87

Irish Embassy in Washington—Ambassador’s Residence—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptation and furnishing

...

...

...

...

...

...

33,000

31,000

32,257

9

5

 

 

 

32,257

9

5

In progress.

 

Total:

 

 

67,000

32,860

19

7

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Social Welfare

 

 

 

 

 

 

 

 

 

 

 

 

88

Longford—New Employment Exchange

...

...

...

...

23,000

15,000

10,268

6

0

 

 

 

10,268

6

0

Nearing completion.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total:

 

 

15,000

10,268

6

0

 

 

 

 

 

 

 

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

 

 

89 (1)

Central Mental Hospital Dundrum—New Entrance

...

...

2,200

2,200

360

0

0

 

 

 

360

0

0

In progress.

89 (2)

Central Mental Hospital—Rebuilding Boiler House

...

...

...

10,000

10,000

5,400

0

0

 

 

 

5,400

0

0

In progress.

 

Total:

 

 

12,200

5,760

0

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

General:

 

 

 

 

 

 

 

 

 

 

 

 

90

Minor New Works not exceeding £2,000 each

...

...

...

 

35,000

30,204

13

1

 

 

 

 

 

 

 

91

Urgent and Unforeseen Works

...

...

...

...

...

...

 

5,000

5,098

19

0

 

 

 

 

 

 

 

92

Minor Balances of Expenditure (not provided for above) on works

 

 

 

 

 

 

 

 

 

 

 

 

 

of prior years which may not be completed on 1st April, 1965

...

 

15,000

43,032

17

7

 

 

 

 

 

 

 

 

Total:

 

 

5,830,200

5,381,569

12

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Deduct for works which may not be carried out during the year—

 

260,200

 

 

 

 

 

 

 

 

 

 

 

Net Total:

 

 

5,570,000

5,381,569

12

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF No. 90—MINOR NEW WORKS.

Service and Description

Expenditure

Observations

1965-66

To 31/3/65

To 31/3/66

 

£

s.

d.

£

s.

d.

£

s.

d.

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

Árus an Uachtaraín—Electrical Adaptations

...

...

...

...

...

...

...

...

...

...

239

18

7

239

18

7

Completed.

Department of Finance

 

 

 

 

 

 

 

 

 

 

18 Lansdowne Road—Adaptations

...

...

...

...

...

...

...

...

...

...

...

11

10

10

524

17

4

536

8

2

Completed.

64/65 Merrion Square—Adaptations

...

...

...

...

...

...

...

...

...

...

...

14

11

1

613

5

6

627

16

7

Completed.

64/65 Merrion Square—Erecting partition

...

...

...

...

...

...

...

...

...

...

146

10

0

146

0

10

Completed.

Revenue Commissioners

 

 

 

 

 

 

 

 

 

 

Dublin Castle, Stamping Branch—Adaptations

...

...

...

...

...

...

...

...

...

1,049

12

2

634

5

10

1,683

18

0

Completed.

21 Parliament Street—Fire Precaution Works

...

...

...

...

...

...

...

...

...

1,544

11

0

815

0

10

2,359

11

10

Completed.

9-15 Upr. O’Connell St.—Electrical Adaptations

...

...

...

...

...

...

...

...

...

55

11

0

683

17

3

739

8

3

Completed.

9-15 Upr. O’Connell St.—Provision of Incinerators

...

...

...

...

...

...

...

...

...

298

0

0

271

5

2

569

5

2

Completed.

11-13 Upr O’Connell St.—Improved Lighting

...

...

...

...

...

...

...

...

...

193

7

7

193

7

7

Completed.

21 St. Stephen’s Green—Adaptations

...

...

...

...

...

...

...

...

...

...

564

5

11

7

3

11

571

9

10

Completed.

Limerick Government Offices—Improvements, etc.

...

...

...

...

...

...

...

...

1,248

6

1

1,418

11

8

2,666

17

9

Completed.

Bridgend Customs Frontier Post—Improvements

...

...

...

...

...

...

...

...

...

1,460

0

0

1,460

0

0

Completed.

Customs & Excise Offices—Cork—Improved Heating

...

...

...

...

...

...

...

...

124

10

0

124

10

0

Completed.

Office of Public Works

 

 

 

 

 

 

 

 

 

 

51 St. Stephen’s Green—Alterations Room 5

...

...

...

...

...

...

...

...

...

155

2

6

155

2

6

Completed.

51 St. Stephen’s Green—Drawing Office—Alterations

...

...

...

...

...

...

...

...

414

18

1

414

18

1

Completed.

51 St. Stephen’s Green—Dining Club—Provision of Kitchen Equipment

...

...

...

...

...

106

17

11

106

17

11

Completed.

13/14 Earlsfort Terrace—Security alterations

...

...

...

...

...

...

...

...

...

232

1

8

232

1

8

Completed.

St. Stephen’s Green Park—Improvements

...

...

...

...

...

...

...

...

...

...

813

1

1

813

1

1

Completed.

Dun Laoghaire Harbour—Improvements at No. 3 Coastguard Cottages

...

...

...

...

...

...

66

12

0

73

6

3

139

18

3

Completed.

Memorial Park, Islandbridge—New tool shed & breakfast room

...

...

...

...

...

...

...

456

8

6

456

8

6

Completed.

Garnish Island—Improved toilet facilities

...

...

...

...

...

...

...

...

...

102

1

11

102

1

11

In progress.

Ardee—Accommodation for Archacological Survey

...

...

...

...

...

...

...

...

...

278

14

6

278

14

6

In progress.

Cork Divisional Office—Adaptations

...

...

...

...

...

...

...

...

...

...

...

458

15

6

1,718

4

5

2,177

0

11

Completed.

Thurles District Office—New Structure

...

...

...

...

...

...

...

...

...

...

73

19

6

1,764

16

6

1,838

16

0

Completed.

Valuation Office

 

 

 

 

 

 

 

 

 

 

5/6 Ely Place—Improved heating, etc.

...

...

...

...

...

...

...

...

...

...

372

15

7

307

1

6

679

17

1

Completed

Ordnance Survey Office—Fundamental Bench Marks

...

...

...

...

...

...

...

...

35

11

3

35

11

3

In progress.

State Laboratory—Improvements

...

...

...

...

...

...

...

...

...

...

...

36

8

8

36

8

8

In progress

General

 

 

 

 

 

 

 

 

 

 

Government Buildings, West Block—Fire Precaution Works

...

...

...

...

...

...

...

130

5

8

11

15

8

142

1

4

Completed

Cork Government Buildings—Adaptations

...

...

...

...

...

...

...

...

...

...

274

18

11

61

4

6

336

3

5

Completed.

Department of Justice

 

 

 

 

 

 

 

 

 

 

High Court—Lifts

...

...

...

...

...

...

...

...

...

...

...

...

...

80

0

0

1,305

10

9

1,385

10

9

Completed.

Metropolitan District Courts—Improved Heating

...

...

...

...

...

...

...

...

...

84

19

7

1,010

5

4

1,095

4

11

Completed.

Circuit Court—Improvements

...

...

...

...

...

...

...

...

...

...

...

...

520

12

11

520

12

11

Completed.

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

Custom House—Adaptations

...

...

...

...

...

...

...

...

...

...

...

...

147

10

0

147

10

0

Completed.

Department of Education:

 

 

 

 

 

 

 

 

 

 

National Gallery—Improvements

...

...

...

...

...

...

...

...

...

...

...

302

0

0

302

0

0

Completed.

Central Model Schools—Partitioning

...

...

...

...

...

...

...

...

...

...

...

169

18

9

169

18

9

Completed.

Cork Model School—Improvements to Caretaker’s Quarters

...

...

...

...

...

...

...

186

0

0

186

0

0

Completed.

Limerick Model School—Electrical Improvements

...

...

...

...

...

...

...

...

...

500

0

0

500

0

0

Completed.

Department of Lands:

 

 

 

 

 

 

 

 

 

 

23/24 Upper Merrion St—Improvements

...

...

...

...

...

...

...

...

...

...

55

17

1

87

7

0

143

4

1

Completed.

2/3 Merrion Square—Rewiring

...

...

...

...

...

...

...

...

...

...

...

...

1,663

2

2

1,663

2

2

In progress.

Land Commission, Castlebar—Improvements

...

...

...

...

...

...

...

...

...

550

14

7

550

14

7

In progress.

Forestry Branch, Mallow—Provision of Accommodation

...

...

...

...

...

...

...

...

40

0

0

40

0

0

In progress,

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

Government Buildings—Improvements

...

...

...

...

...

...

...

...

...

...

29

3

7

258

1

1

287

4

8

Completed.

Veterinary College, Ballsbridge—Improvements

...

...

...

...

...

...

...

...

...

81

10

0

238

14

8

320

4

8

Completed.

Veterinary College, Ballsbridge—Adaptations

...

...

...

...

...

...

...

...

...

189

17

4

189

17

4

In progress.

Abbotstown Farm—Sundry minor improvements

...

...

...

...

...

...

...

...

...

2

17

6

244

7

3

247

4

9

Completed.

Chantilly Stud Farm—New Laboratory

...

...

...

...

...

...

...

...

...

270

16

3

270

16

3

In progress.

Fisheries Branch, Fenit—Alteration and redecoration

...

...

...

...

...

...

...

...

290

0

0

290

0

0

Completed.

Munster Institute, Cork—Improvements

...

...

...

...

...

...

...

...

...

...

1,202

9

3

1,202

9

3

In progress.

Athenry Agricultural School—Adaptation

...

...

...

...

...

...

...

...

...

...

954

3

4

954

3

4

Completed.

Athenry Agricultural School—Improved toilet facilities

...

...

...

...

...

...

...

...

145

0

0

145

0

0

Completed.

Ballyhaise Agricultural School—Alterations

...

...

...

...

...

...

...

...

...

...

21

4

0

21

4

0

In progress.

Clonakilty Agricultural School—Improved heating

...

...

...

...

...

...

...

...

200

0

0

200

0

0

Completed.

Bovine T B. Office, Carlow—Improved Lighting

...

...

...

...

...

...

...

...

...

225

4

0

225

4

0

Completed.

Bovine T.B. Office, Cork—Improvements

...

...

...

...

...

...

...

...

...

...

358

5

6

358

5

6

In progress

Bovine T.B. Office—Sligo—Improvements

...

...

...

...

...

...

...

...

...

...

12

14

5

372

13

11

384

8

4

Completed.

Bovine T.B. Office, Tipperary—Alterations

...

...

...

...

...

...

...

...

...

...

140

12

6

1,189

7

8

1,330

0

2

Completed.

Bovine T.B. Office, Tralee—Electrical Installation

...

...

...

...

...

...

...

...

...

664

6

8

664

6

8

Completed.

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

Meteorological Station, Malin Head—Provide new buildings and mast

...

...

...

...

...

...

600

0

0

600

0

0

In progress

Valentia Observatory—Improvements

...

...

...

...

...

...

...

...

...

...

...

375

9

1

529

5

9

904

14

10

Completed.

Valentia Observatory—Erect new fencing

...

...

...

...

...

...

...

...

...

...

405

5

0

405

5

0

Completed.

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

44/5 Merrion Square—Improved toilet facilities

...

...

...

...

...

...

...

...

...

268

5

2

268

5

2

Completed.

Labour Court—Conference Rooms

...

...

...

...

...

...

...

...

...

...

...

22

17

1

1,151

18

6

1,174

15

7

Completed.

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

General Post Office, Dublin—Alterations

...

...

...

...

...

...

...

...

...

...

863

15

0

863

15

0

In progress.

General Post Office, Dublin—Dining Club—Equipment

...

...

...

...

...

...

...

...

113

5

0

690

0

0

803

5

0

Completed.

College Green—Adaptations

...

...

...

...

...

...

...

...

...

...

...

...

186

13

8

526

4

6

712

18

2

Completed.

Aldboro’ House—Improved Canteen facilities

...

...

...

...

...

...

...

...

...

53

10

11

53

10

11

In progress.

Aldboro’ House—Additional accommodation

...

...

...

...

...

...

...

...

...

57

13

5

57

13

5

In progress.

Post Office Factory, St. John’s Road.—Shelving

...

...

...

...

...

...

...

...

...

146

4

1

146

4

1

Completed.

James’ Street P.O.—Improvements

...

...

...

...

...

...

...

...

...

...

...

183

0

0

183

0

0

Completed.

Arklow P.O.—Additional accommodation

...

...

...

...

...

...

...

...

...

...

418

18

0

418

18

0

Completed.

Bantry P.O.—Additional Security arrangements

...

...

...

...

...

...

...

...

...

141

0

0

141

0

0

Completed.

Castlebar P.O.—Sanitary accommodation

...

...

...

...

...

...

...

...

...

...

961

10

8

961

10

8

Completed.

Drogheda P.O.—Additional toilet facilties

...

...

...

...

...

...

...

...

...

248

10

0

248

10

0

Completed.

Kells P.O.—Improvements

...

...

...

...

...

...

...

...

...

...

...

...

...

450

0

0

450

0

0

Completed.

Kildare P.O. and Residence—Improvements

...

...

...

...

...

...

...

...

...

...

184

0

0

1,562

16

8

1,746

16

8

Completed.

Letterkenny Engineering Branch—Improvements

...

...

...

...

...

...

...

...

...

178

0

10

450

4

5

628

5

3

Completed.

Limerick P.O.—Alterations

...

...

...

...

...

...

...

...

...

...

...

...

242

15

7

242

15

7

Completed.

Westport P.O.—Instal petrol tank and pump

...

...

...

...

...

...

...

...

...

135

0

0

411

15

0

546

15

0

Completed.

Department of Defence:

 

 

 

 

 

 

 

 

 

 

Arbour Hill—Provision of Memorial Tablet

...

...

...

...

...

...

...

...

...

...

125

0

0

125

0

0

Completed.

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

Iveagh House—Improvement of Lighting

...

...

...

...

...

...

...

...

...

...

45

5

9

78

7

0

123

12

9

Completed.

Iveagh House—Improvements

...

...

...

...

...

...

...

...

...

...

...

...

249

4

5

249

4

5

In progress.

Embassy to Holy See—Alterations

...

...

...

...

...

...

...

...

...

...

...

298

16

0

111

0

0

409

16

0

Completed.

London Embassy—Structural alterations

...

...

...

...

...

...

...

...

...

...

5

5

0

5

5

0

In progress.

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

Áras Mhic Dhiarmada—Dining Club—Water Heater

...

...

...

...

...

...

...

...

...

9

12

6

245

15

7

255

8

1

Completed.

Áras Mhic Dhiarmada—Dining Club—Improvements

...

...

...

...

...

...

...

...

310

0

11

310

0

11

Completed.

Áras Mhic Dhiarmada—Dining Club—Kitchen Equipment

...

...

...

...

...

...

...

...

481

15

0

481

15

0

Completed.

Áras Mhic Dhiarmada—Steel Partition

...

...

...

...

...

...

...

...

...

...

180

15

11

180

15

11

Completed.

Employment Exchanges:

 

 

 

 

 

 

 

 

 

 

Galway (Claddagh)—Partitions

...

...

...

...

...

...

...

...

...

...

...

226

15

0

226

15

0

Completed.

Limerick—Improved Lighting

...

...

...

...

...

...

...

...

...

...

...

51

0

0

1,058

17

6

1,109

17

6

Completed.

Newcastlewest—Improved heating and lighting

...

...

...

...

...

...

...

...

...

359

5

4

359

5

4

Completed.

Waterford—Instal new heating

...

...

...

...

...

...

...

...

...

...

...

1,253

17

5

1,253

17

5

Completed.

Department of Health:

 

 

 

 

 

 

 

 

 

 

Central Mental Hospital—Improved water supply

...

...

...

...

...

...

...

...

...

234

8

5

206

7

1

440

15

6

Completed.

Total for Minor New Works

...

£30,204

13

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 91—URGENT AND UNFORESEEN WORKS.

Service and Description

Expenditure

Observations

1965-66

To 31/3/65

To 31/3/66

 

£

s.

d.

£

s.

d.

£

s.

d.

 

Department of the Taoiseach:

 

 

 

 

 

 

 

 

 

 

Central Statistics Office, Griffith Barracks: Adaptation of computer room and supply of furniture

...

...

1

0

0

1

0

0

In progress.

Department of Education:

 

 

 

 

 

 

 

 

 

 

Liberty Hall—Partitions, furniture, etc.

...

...

...

...

...

...

...

...

...

...

2,933

4

10

2,933

4

10

In progress.

Department of Health:

 

 

 

 

 

 

 

 

 

 

Liberty Hall—Partitions, furniture, etc.

...

...

...

...

...

...

...

...

...

...

2,164

14

2

2,164

14

2

In progress.

Total for Urgent and Unforeseen Works

...

£5,098

19

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 92—MINOR BALANCES OF EXPENDITURE.

Service and Description

Expenditure

Observations

1965-66

To 31/3/65

To 31/3/66

 

£

s.

d.

£

s.

d.

£

s.

d.

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

Áras an Uachtaráin—Improvement of Planthouse accommodation

...

...

...

...

...

...

361

19

11

9,193

6

2

9,555

6

1

Completed.

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

Leinster House—Dáil Chamber: Improved Acoustics

...

...

...

...

...

...

...

...

72

1

3

6,746

0

0

6,818

1

3

Completed.

Department of the Taoiseach:

 

 

 

 

 

 

 

 

 

 

Central Statistics Office—New accommodation

...

...

...

...

...

...

...

...

...

3,781

5

5

35,696

10

7

39,477

16

0

Completed.

Department of Finance:

 

 

 

 

 

 

 

 

 

 

Transfer of Staff to 64/65 Merrion Square

...

...

...

...

...

...

...

...

...

...

36

18

0

4,165

0

6

4,201

18

6

Completed.

Civil Service Dining Club—Provision of Kitchen equipment and alterations to service section

...

...

...

728

10

6

5,654

13

9

6,383

4

3

Completed.

Carrickcarnan Customs Frontier Post—Office and Residence

...

...

...

...

...

...

...

1,469

19

5

14,697

15

6

16,167

14

11

Completed.

Lifford Customs Post—Erection

...

...

...

...

...

...

...

...

...

...

...

190

0

0

11,424

10

7

11,614

10

7

Completed.

Clondergole Customs Frontier Post—Erection

...

...

...

...

...

...

...

...

...

138

0

0

2,850

9

8

2,988

9

8

Completed.

Ordnance Survey Office—Extension and Adaptation

...

...

...

...

...

...

...

...

329

16

11

5,307

3

10

5,637

0

9

Completed.

Phoenix Park—Improvement of Water Supply

...

...

...

...

...

...

...

...

...

7,671

2

3

26,805

17

10

34,477

0

1

Completed.

Dun Laoghaire Harbour—Mail Boat Pier improvements

...

...

...

...

...

...

...

...

747

1

11

199,877

11

6

200,624

13

5

Completed.

Department of Justice:

 

 

 

 

 

 

 

 

 

 

Land Registry—Additional accommodation (Stage 1)

...

...

...

...

...

...

...

...

2,422

0

0

20,818

0

3

23,240

0

3

Completed.

Land Registry—Fire Escape Staircase

...

...

...

...

...

...

...

...

...

...

...

606

0

0

7,174

14

3

7,780

14

3

Completed.

Department of Education:

 

 

 

 

 

 

 

 

 

 

Central Model Schools, Marlboro Street—Adaptations, etc.

...

...

...

...

...

...

...

...

520

13

8

6,950

0

9

7,470

14

5

Completed.

National Museum—Intruder Alarm System

...

...

...

...

...

...

...

...

...

...

47

6

4

2,200

6

7

2,247

12

11

Completed.

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

69 Fitzwilliam Square, Dublin—Adaptations, etc.

...

...

...

...

...

...

...

...

...

1

8

3

3,568

17

8

3,570

5

11

Completed.

Veterinary College, Ballsbridge—Improvements

...

...

...

...

...

...

...

...

...

7

5

11

19,792

14

2

19,800

0

1

Completed.

Veterinary College, Ballsbridge—Pathological Anatomy Unit

...

...

...

...

...

...

...

1,301

6

5

11,520

13

3

12,821

19

8

Completed.

Thorndale Veterinary Laboratory—Adaptations

...

...

...

...

...

...

...

...

...

2,299

5

1

2,353

17

1

4,653

2

2

In progress.

Bovine T.B. Office, Limerick—Improvements and Adaptations

...

...

...

...

...

...

...

768

16

3

1,519

13

2

2,288

9

5

Completed.

Abbotstown Farm—Artificial Insemination Experimental Station

...

...

...

...

...

...

...

986

0

0

20,731

2

6

21,717

2

6

Completed.

Abbotstown Farm—Residence for Farm Manager

...

...

...

...

...

...

...

...

...

52

13

6

3,311

7

2

3,364

0

8

Completed.

Clonakilty Agricultural School—Fire precaution works

...

...

...

...

...

...

...

...

57

5

0

633

9

11

690

14

11

In progress.

Clonakilty Agricultural School—Improvement of Water Supply

...

...

...

...

...

...

...

1,895

16

7

16,647

0

11

18,542

17

6

Completed.

Munster Institute—Fire precaution works

...

...

...

...

...

...

...

...

...

...

435

13

2

1,803

2

9

2,238

15

11

Completed.

Munster Institute—Reconstruction of Cattle Court and Calf Sheds

...

...

...

...

...

...

855

6

2

2,440

14

6

3,296

0

8

Completed.

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

Arklow Post Office—Improvements and new Telephone Exchange

...

...

...

...

...

...

1,981

19

2

16,552

7

11

18,534

7

1

Completed.

Ballinasloe—New Post Office and Telephone Exchange

...

...

...

...

...

...

...

...

4,062

8

9

21,620

5

11

25,682

14

8

Completed.

Carrick-on-Shannon Post Office—Improvements

...

...

...

...

...

...

...

...

...

274

2

0

21,904

13

10

22,178

15

10

Completed.

Ennis Post Office—Improvements and new Telephone Exchange

...

...

...

...

...

...

...

190

2

8

10,662

0

6

10,852

3

2

Completed.

Finglas—New District Sorting Office and Telephone Exchange

...

...

...

...

...

...

...

846

14

9

15,942

9

8

16,789

4

5

Completed.

Limerick Post Office—Improvements

...

...

...

...

...

...

...

...

...

...

2,850

0

0

21,530

17

8

24,380

17

8

Completed.

Wicklow—New Post Office and Telephone Exchange

...

...

...

...

...

...

...

...

3,762

11

9

28,019

17

9

31,782

9

6

Completed.

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

Dublin—New Headquarters, Haddington Road

...

...

...

...

...

...

...

...

...

15

9

11

79,707

14

3

79,723

4

2

Deferred

Department of Health:

 

 

 

 

 

 

 

 

 

 

Central Mental Hospital, Dundrum—Improvements in Kitchen

...

...

...

...

...

...

...

1,265

16

8

1,298

12

3

2,564

8

11

Completed.

Total for Minor Balances

...

£43,032

17

7