Committee Reports::Report - Appropriation Accounts 1952 - 1953::30 March, 1955::Appendix

APPENDIX XII.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1952-53 (VOTE 9, SUBHEAD B.)

Work No.

Service and Description

Total Estimate

Vote 1952-53

Expenditure

Observations

1952-53

to 31/3/52

to 31/3/53

 

 

£

£

£

s.

d.

£

s.

d.

£

s.

d.

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

 

 

1

Áras an Uachtaráin—Improvements and furnishing

...

108,000

28,000

528

10

8

55,295

5

2

55,823

15

10

In Progress.

 

 

 

£28,000

£528

10

8

 

 

 

 

 

 

 

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

 

 

2

Electric Indicator System

...

...

...

...

3,000

3,000

Deferred.

3

Restaurant—Alteration and Improvement

...

...

1,500

1,500

£2,443

13

4

£2,443

13

4

In Progress.

 

 

 

£4,500

£2,443

13

4

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

 

4

2/3 Merrion Square—Central Heating

...

...

...

1,740

1,500

461

7

6

258

6

7

719

14

1

In Progress.

5

Ballyshannon Customs and Excise—Office accommodation

 

 

 

 

 

 

 

 

 

 

 

 

 

and Official Garage

...

...

...

...

...

2,500

2,500

Deferred.

6

Sligo Custom House—Thermal Storage Heating

...

600

600

In Progress.

7

Waterford Government Offices—Erection*

...

...

183,160

5,400

3,050

6

9

14,766

10

10

17,816

17

7

Project partly completed.

8

Office of Public Works—New Central Engineering

 

 

 

 

 

 

 

 

 

 

 

 

 

Workshop and Stores

...

...

...

...

...

30,500

3,500

861

1

3

1,784

13

6

2,645

14

9

In Progress.

9

Stationery Office—Storage

...

...

...

...

65,800

300

Deferred.

10

Valuation Office—Thermal Storage and Electric Water

 

 

 

 

 

 

 

 

 

 

 

 

 

Heaters

...

...

...

...

...

...

4,825

4,580

Postponed pending completion of legal formalities.

11

Ordnance Survey Office—Improved Ablution Facilities

950

950

461

7

6

461

7

6

Completed.

12

Ordnance Survey Office—Married Quarters—

 

 

 

 

 

 

 

 

 

 

 

 

 

Improvements

...

...

...

...

...

...

5,250

750

Deferred.

 

Parks:

 

 

 

 

 

 

 

 

 

 

 

 

13

Phoenix Park—Shelters for Relief Gatekeepers

...

2,100

175

994

7

10

1,430

19

9

2,425

7

7

Main work completed.

14

Rotunda Gardens—Garden of Remembrance

...

...

30,000

1,000

600

1

8

600

1

8

Postponed.

 

Harbours:

 

 

 

 

 

 

 

 

 

 

 

 

15

Buncrana Harbour—Improvements

...

...

...

1,050

750

175

0

0

300

0

0

475

0

0

In progress.

16

Dun Laoghaire Harbour—Additional Customs

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

35,000

20,000

28,153

12

1

7,955

5

1

36,108

17

2

Main work completed.

17

Dun Laoghaire Harbour—Public Lighting

...

...

2,300

1,000

Not commenced in 1952-53.

 

 

 

£43,005

£34,157

2

11

 

 

 

 

 

 

 

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

 

 

18

Botanic Gardens—Additional Glasshouse

...

...

7,000

3,000

4,035

13

2

4,003

1

10

8,038

15

0

Completed.

19

Botanic Gardens—New Fern House

...

...

...

Not yet made

500

Postponed.

20

Botanic Gardens—Improvement of Water Supply

...

 

1,000

395

3

11

395

3

11

Preliminary work completed; planning of main work in progress.

21

Athenry Agricultural School—Hard surfacing to Yards

 

 

 

 

 

 

 

 

 

 

 

 

 

and Avenues

...

...

...

...

...

...

2,800

2,800

1,268

16

3

1,268

16

3

In progress.

21A

Athenry Agricultural School—Reconstruction of “Laings

 

 

 

 

 

 

 

 

 

 

 

 

 

House”

...

...

...

...

...

...

480

0

0

480

0

0

Completed.

22

Athenry Agricultural School—New Grain, etc., Stores

...

4,500

4,250

 

4

8

 

4

8

Preliminary work.

23

Athenry Agricultural School—New Machinery Store

...

2,500

2,000

Tenders invited.

24

Athenry Agricultural School—Provision of Electric Power

1,750

500

1,075

0

0

387

9

9

1,462

9

9

In progress.

25

Ballyhaise Agricultural School—E.S.B. Supply

...

...

4,100

600

1,769

0

9

2,995

0

8

4,764

1

5

Completed.

25A

Ballyhaise Agricultural School—Artificial Insemination

 

 

 

 

 

 

 

 

 

 

 

 

 

Centre

...

...

...

...

...

...

23

0

0

23

0

0

In progress.

26

Clonakilty Agricultural School—New Buildings

...

75,000

500

439

6

4

286

11

9

725

18

1

Preliminary work completed. Main work not commenced in

26A

Clonakilty Agricultural School—Expenditure on

 

 

 

 

 

 

 

 

 

 

 

1952-53.

 

Insemination Centre

...

...

...

...

...

307

1

7

142

11

9

449

13

4

Completed.

27

Grange Stud and Dairy Farm—Adaptations

...

...

59,000

13,200

9,710

3

11

10,605

5

1

20,315

9

0

In progress.

28

Johnstown Castle—Adaptations and Renovations

...

142,000

15,400

17,886

3

8

106,176

9

8

124,062

13

4

Main adaptation works completed.

29

Munster Institute—Improved Accommodation

...

...

72,000

1,450

468

6

0

236

2

11

704

8

11

In progress.

30

Veterinary College—Improvements

...

...

...

127,000

10,000

200

1

6

76,831

6

5

77,031

7

11

Commencement of final section of work postponed pending settlement of legal dispute.

30A

Abbotstown Farm—Various overhaul and repair Works

..

634

9

3

634

9

3

In progress.

31

Fishery, etc. Harbours—Works of Economic Development

6,500

6,500

 

 

 

 

 

 

 

 

 

 

 

Ballymacw

...

...

...

...

9

7

0

In progress.

 

Bloodyforeland

...

...

...

77

8

8

Completed.

 

Carne

...

...

...

...

...

619

1

0

Completed.

 

Dingle

...

...

...

...

...

22

13

1

In progress.

 

Dooneen

...

...

...

...

1,869

12

1

Completed.

 

Greencastle

...

...

...

...

6,750

11

9

5,228

8

6

11,979

0

3

In progress.

 

Portaleen

...

...

...

...

89

16

7

In progress.

 

Sherkin Island

...

...

...

1,340

9

11

Completed.

 

Whiddy Island

...

...

...

566

11

2

Completed.

 

Tory Island

...

...

...

...

6

16

10

 

Malinmore

...

...

...

...

1

2

6

 

 

 

 

£11,353

10

7

 

 

 

 

 

 

 

 

 

 

£61,700

£49,650

17

8

 

 

 

 

 

 

 

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

 

 

32

Courts of Justice, Law Library—Improvement of

 

 

 

 

 

 

 

 

 

 

 

 

 

Ventilation

...

...

...

...

...

...

...

...

2,000

2,000

292

15

9

292

15

9

In progress.

32A

Government Buildings, North Block—Additional

 

 

 

 

 

 

 

 

 

 

 

 

 

Shelving

...

...

...

...

...

...

...

544

4

6

544

4

6

Completed.

32B

Land Registry—Improved Accommodation

...

...

1,508

2

10

1,508

2

10

In progress.

33

Garda Depot—Additional Accommodation

...

...

Not yet made

500

2,836

2

10

4,955

13

0

7,791

15

10

In progress.

34

Garda Depot—Additional Garage and Workshop

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

42,000

800

Postponed.

35

Garda Depot—Additional Storage

...

...

...

1,200

1,200

Planning virtually completed.

36

Garda Depot—Extension of Hospital

...

...

...

4,300

220

1,379

3

8

3,320

14

8

4,699

18

4

Completed.

37

Garda Depot—New Electrical Distribution System

...

1,250

1,250

53

12

0

53

12

0

In progress.

38

Garda Síochána Barracks (to be specified)—New Works,

 

 

 

 

 

 

 

 

 

 

 

 

 

Alterations and Additions

...

...

...

...

87,000

87,000

15,989

11

11

See details at back.

39

New Works, Alterations and Additions at other Garda

 

 

 

 

 

 

 

 

 

 

 

 

 

Síochána Barracks

...

...

...

...

...

5,000

5,000

60

19

7

See details at back.

40

Minor New Works at Garda Síochána Barracks

...

...

4,000

4,000

2,379

12

4

See details at back.

 

 

 

£101,970

£24,990

13

5

 

 

 

 

 

 

 

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

 

41

Tyrone House—Improvement of Lighting

...

...

1,000

1,000

Postponed.

42

Talbot House—Central Heating

...

...

...

3,500

3,300

In progress.

42A

National Education Office—Publications Branch

631

13

5

631

13

5

In progress.

43

Central Model Schools—Central Heating and Electric

 

 

 

 

 

 

 

 

 

 

 

 

 

Lighting

...

...

...

...

...

...

...

4,650

4,650

Postponed.

44

Central Model Schools—Erection of Italian Presentation

 

 

 

 

 

 

 

 

 

 

 

 

 

Statuary

...

...

...

...

...

...

...

1,300

1,300

Completed but not paid for.

45

Dunmanway Model School—Improvements

...

...

1,950

1,950

Commencement of work delayed pending settlement of way-leaves, etc.

46

National Schools—Grants for Building, Enlarging,

 

 

 

 

 

 

 

 

 

 

 

 

 

Enclosing, etc.

...

...

...

...

...

...

600,000

600,000

684,355

19

3

684,355

19

3

 

 

Preparatory Colleges:

 

 

 

 

 

 

 

 

 

 

 

 

47

Coláiste Móibhí—Adaptations

...

...

...

...

55,000

15,000

15,561

7

3

15,561

7

3

Next stage postponed.

 

Institutions of Science and Art:

 

 

 

 

 

 

 

 

 

 

 

 

48

National Library and National Museum—Renewal of

 

 

 

 

 

 

 

 

 

 

 

 

 

Defective Stonework

...

...

...

...

...

70,000

5,000

Postponed.

48A

National Library—Provision of Shelving

...

...

26

12

2

26

12

2

Tenders about to be invited.

49

National Museum—Internal Passage between Divisions

...

700

700

1,078

10

0

1,078

10

0

Virtually completed

 

Reformatory and Industrial Schools:

 

 

 

 

 

 

 

 

 

 

 

 

50

Reformatory School, Daingean—Adaptations

...

...

53,500

7,500

3,208

18

11

44,500

11

10

47,709

10

9

Four (of five) stages of work completed.

 

 

 

£640,400

£689,301

13

9

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

 

50A

Department of Lands—Luncheon Club Alterations

..

888

18

10

888

18

10

Completed.

 

Forestry Branch:

 

 

 

 

 

 

 

 

 

 

 

 

51

Forestry School, Shelton Abbey—Adaptations

37,000

10,000

536

4

7

536

4

7

In progress.

 

Gaeltacht Services Branch:

 

 

 

 

 

 

 

 

 

 

 

 

52

Ardara Tweed Mart—Improvements

...

...

...

3,000

2,000

171

18

1

171

18

1

In progress.

53

Cliffoney Lace Centre—New Premises

...

...

...

5,500

1,500

Project abandoned.

54

Crolly Toy Factory—Improvement of Heating

...

950

500

414

8

0

443

5

2

857

13

2

In progress.

55

Crolly Toy Factory—Water Supply, Cycle Shed, etc.

2,000

1,800

Tenders under consideration.

56

Elly Bay Toy Factory—Water Supply and Improved

 

 

 

 

 

 

 

 

 

 

 

 

 

Sanitary Accommodation, etc.

...

...

...

1,200

1,200

1,048

12

9

12

13

5

1,061

6

2

In progress.

57

Glencolumbkille—New Tweed Mart

...

...

...

6,000

1,000

Planning completed. Finance sanction awaited.

 

 

 

 

6

3

6

192

2

0

 

 

 

Hostel and main extension

58

Kilcar—New Spinning Factory

...

...

...

...

57,400

1,700

3,430

19

5

52,916

14

2

56,545

19

1

works completed. Supplementary works in progress.

59

Roundstone Knitting Centre—Extension

...

...

1,300

1,300

12

8

11

12

8

11

Tenders under consideration.

60

Tourmakeady Knitting Centre—Adaptations

...

...

3,200

2,900

3,092

3

11

272

19

2

3,365

3

1

Main works completed. Subsidiary works in progress.

61

Tourmakeady Knitting Centre—Residence for Technical

 

 

 

 

 

 

 

 

 

 

 

 

 

Staff

...

...

...

...

...

...

...

800

800

506

15

9

9

4

9

516

0

6

Completed.

62

Central Depot and Rural Centres—Improved

 

 

 

 

 

 

 

 

 

 

 

 

 

Fire-Fighting Facilities

...

...

...

...

...

10,425

6,000

Postponed.

 

 

 

£30,700

£10,108

13

9

 

 

 

 

 

 

 

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

 

 

63

Additional Telegraphic Weather Reporting Stations

...

16,100

5,000

1,829

4

4

1,829

4

4

Planning for one station in progress; sites for four others being acquired.

64

Rosslare, New Meteorological Observing Station and

 

 

 

 

 

 

 

 

 

 

 

 

 

Training Centre

...

...

...

...

...

...

15,500

3,000

 

9

3

 

9

3

Preliminary work.

65

Valentia Observatory—Adaptations and Additions

...

56,000

8,000

440

2

0

4,356

3

1

4,796

5

1

Preliminary works completed.

 

 

 

£16,000

£440

11

3

 

 

 

 

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

 

 

66

Dublin, General Post Office—Additional cycle

 

 

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

...

...

...

2,000

2,000

11

4

0

11

4

0

In progress.

67

Dublin, College Green Post Office—Alterations

...

1,000

1,000

Project being revised.

68

Dublin, New Post Office, St. Andrew Street*

...

...

34,000

8,000

6,801

2

0

26,896

16

3

33,697

18

3

Main works completed.

69

Dublin, Engineering Branch, Distillery Road—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations*

...

...

...

...

...

...

...

2,350

300

554

18

7

2,067

4

5

2,622

3

0

Main work completed. Supplementary works in progress.

70

Dublin, Post Office Factory—Improved Office

 

 

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

...

...

640

640

Planning completed.

71

Dublin, Post Office Factory—Rebuilding

...

...

52,000

25,000

17,310

15

11

32,121

13

11

49,432

9

10

Main works completed.

72

Dublin, Post Office Stores, Infirmary Road—Thermal

 

 

 

 

 

 

 

 

 

 

 

 

 

Storage Heating

...

...

...

...

...

3,500

3,500

866

7

6

866

7

6

In progress.

73

Dublin, Post Office Stores—Resurfacing Yard

...

...

560

560

500

11

0

11

4

0

511

15

0

Work virtually completed.

74

Ballina Post Office—Additional Accommodation*

...

10,400

5,000

Bill of Quantities awaited.

75

Ballyhaunis Post Office—Improvements

...

...

700

100

360

7

6

380

10

4

740

17

10

Completed.

76

Birr Post Office—Adaptations

...

...

...

...

1,350

1,320

893

4

0

29

15

11

922

19

11

Completed.

77

Cahir Post Office—Adaptations*

...

...

...

490

490

9

1

7

3

2

4

12

3

11

Negotiations with Contractor for revision of original scheme.

78

Clonmel Post Office—Extension

...

...

...

1,350

1,350

260

10

0

2

11

8

263

1

8

In progress.

79

Cork Head Post Office—Improvements

...

...

15,200

750

8,378

16

2

12,240

0

0

20,618

16

2

Completed.

80

Drogheda, New Post Office and Telephone Exchange*

...

39,000

17,000

9,426

19

10

616

13

0

10,043

12

10

In progress.

81

Enniscorthy Post Office—Improvements*

...

...

420

420

In progress.

82

Kilrush, New Post Office and Telephone Exchange*

...

14,400

4,000

240

0

0

240

0

0

Quantity Surveyor’s fees.

83

Limerick, New Telephone Exchange*

...

...

...

2,000

600

1

0

6

1

0

6

Tenders about to be invited.

84

Portlaoighise Post Office—Improvements

...

...

1,050

1,050

650

13

9

650

13

9

In progress.

85

Rathluirc, New Post Office and Telephone Exchange*

...

14,000

4,000

Planning, etc., completed.

86

Tralee Post Office—Extension

...

...

...

...

6,000

2,000

Bills of Quantities awaited.

87

Improved Sorting Equipment at Post Offices

...

...

11,500

3,800

554

16

2

7,208

14

9

7,763

10

11

In progress.

87A

Droichead Nua Post Office—Adaptation of Premises

...

618

1

1

618

1

1

Completed.

 

Wireless Broadcasting:

 

 

 

 

 

 

 

 

 

 

 

 

88

Dublin G.P.O.—Studio and Office Accommodation

...

18,000

6,500

2,332

9

7

13,995

0

5

16,327

10

0

Furnishing in progress.

89

Dublin, Phoenix Hall—Adaptations

...

...

...

5,000

500

39

7

3

4,533

0

3

4,572

7

6

First series of adaptations completed.

90

Cork, New Studios

...

...

...

...

...

16,000

500

Delayed by negotiations with Cork V.E.C. regarding associated School of Music.

 

 

 

£90,380

£49,810

6

5

 

 

 

 

 

 

 

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

 

91

Dublin, Coláiste Caoimhín—Improvement of heating

...

2,500

2,250

1,712

0

5

1,712

0

5

In progress.

92

Dublin, St. Bricin’s Hospital—Lift

...

...

...

1,750

200

1,259

9

0

1,220

8

6

2,479

17

6

Completed.

93

Dublin, Portobello Barracks—Laundry and Bathhouse

150

Project abandoned.

94

Baldonnel Camp—Hangar Gates

...

...

...

17,250

500

12

13

0

12

13

0

In progress.

95

Baldonnel—Hard Surface Runways

...

...

...

20,000

2,904

8

10

2,904

8

10

Preliminary work.

96

Curragh Camp—Catholic Church

...

...

...

...

125,000

1,000

Planning in progress.

97

Curragh—Connolly Barracks—Dining Hall and

 

 

 

 

 

 

 

 

 

 

 

 

 

Cookhouse

...

...

...

...

...

...

...

1,000

Planning in progress.

98

Curragh, Plunkett Barracks—Dining Hall and Cookhouse

1,000

Planning in progress.

99

Curragh, Extension of Magazines

...

...

...

98,000

8,000

24,215

14

2

78,678

7

8

102,894

1

10

Completed.

100

Curragh, Renewal of Electrical Installation

...

...

40,000

20,000

Planning in progress.

101

Haulbowline Dockyard—New Jetty

...

...

...

85,000

30,000

25,241

13

7

46,685

5

8

71,926

19

3

Virtually completed.

102

Kilworth Camp—Officers’ Mess

...

...

...

...

17,000

5,000

2,260

10

1

2,260

10

1

In progress.

 

 

 

£89,100

£57,606

9

1

 

 

 

 

 

 

 

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

 

 

103

Berne Legation—Adaptations and Furnishing

...

6,310

4,350

5,041

16

0

18

9

4

5,060

5

4

Furnishing in progress.

104

Bonn Legation—Adaptations and Furnishing

...

...

12,000

11,000

9,767

17

9

804

7

9

10,572

5

6

In progress.

105

Canberra Embassy—New Building

...

...

...

95,000

800

151

3

2

2,728

12

10

2,879

16

0

Furnishings, etc.

106

London Embassy—Adaptations

...

...

...

...

95,000

12,000

18,244

4

10

83,267

6

2

101,511

11

0

Completed.

 

 

 

£28,150

£33,205

1

9

 

 

 

 

 

 

 

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

 

 

107

Dublin, Victoria Street Employment Exchange—Thermal

 

 

 

 

 

 

 

 

 

 

 

 

 

Storage heating and improved lighting

...

...

850

850

617

11

10

617

11

10

Completed.

108

Waterford, New Employment Exchange

...

...

51,800

11,500

10,005

6

7

23,944

9

11

33,949

16

6

Completed.

 

 

 

£12,350

£10,622

18

5

 

 

 

 

 

 

 

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

 

 

109

Dublin, Head Office, Custom House—Improved Typing

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

1,280

600

1,078

0

9

70

18

6

1,148

19

3

Completed save for furnishing.

110

Dundrum Asylum—Alterations and Additions

...

...

18,440

14,070

12,171

11

1

898

8

0

13,069

19

1

In progress.

 

 

 

£14,670

£13,249

11

10

 

 

 

 

 

 

 

 

General:

 

 

 

 

 

 

 

 

 

 

 

 

111

Minor New Works not exceeding £400 each

...

...

10,000

10,000

11,507

12

7

See details at back.

112

Urgent and Unforeseen Works

...

...

...

...

30,000

30,000

11,693

12

3

See details at back.

113

Minor Balances of Expenditure on Works of Prior Years

...

15,000

15,000

26,099

1

1

See details at back.

 

 

 

£1,215,925

£1,025,416

10

2

 

 

 

 

 

 

 

 

Deduct for Works which may not be carried out during the

 

 

 

 

 

 

 

 

 

 

 

 

 

year

...

...

...

...

...

...

...

 

65,925

 

 

 

 

 

 

 

 

 

 

£1,150,000

£1,025,416

10

2

 

 

 

 

 

 

 

 


Work No.

Service and Description

Expenditure

Observations

1952-53

to 31/3/52

to 31/3/53

 

No. 38—GARDA SIOCHANA BARRACKS.

 

 

 

 

 

 

 

 

 

 

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Newmarket-on-Fergus, Co. Clare—New Barracks

...

...

11

16

1

11

16

1

Fresh tenders about to be invited.

 

Bundoran, Co. Donegal

...

...

...

...

...

...

5,912

14

10

5,912

14

10

In progress.

 

Harcourt Terrace, Dublin—Boundary wall and cycle shed

...

732

1

6

732

1

6

In progress.

 

Athenry, Co. Galway—New Barracks

...

...

...

...

 

4

8

3

19

7

4

4

3

Postponed.

 

Achill Sound, Co. Mayo

...

...

...

...

...

197

10

0

3,893

14

4

4,091

4

4

Completed.

 

Thurles, Co. Tipperary—New Barracks

...

...

...

 

5

11

 

5

11

Bills of Quantities awaited.

 

New Ross, Co. Wexford—New Barracks

...

...

...

9,134

18

11

8,199

11

10

17,334

10

9

Completed.

 

 

£15,989

11

11

 

 

 

 

 

 

 

 

No. 39—NEW WORKS ALTERATIONS AND ADDITIONS, AT OTHER GARDA SIOCHANA BARRACKS.

 

32 of 1950/51

Kilmainham, Dublin—Adaptations

...

...

...

...

21

9

6

413

18

11

435

8

5

Completed.

37 of 1951/52

Churchill, Co. Donegal—New Barracks

...

...

...

...

27

17

0

5,876

13

5

5,904

10

5

Completed.

 

Sligo Garda Barracks—Improvements

...

...

...

...

11

13

1

11

13

1

Tenders under examination

 

 

£60

19

7

 

 

 

 

 

 

 

No. 40—MINOR NEW WORKS AT GARDA SIOCHANA BARRACKS.

 

 

 

 

 

 

 

 

 

 

 

Dublin Metropolitan Area:

 

 

 

 

 

 

 

 

 

 

1

Terenure—Improvements

...

...

...

...

...

96

2

5

96

2

5

Completed.

2

Rathmines—Improvements

...

...

...

...

...

25

4

8

25

4

8

In progress.

3

Kill-o-Grange

...

...

...

...

...

...

...

58 59

12 15

11 0

118

7

11

Completed.

5(39/12 of 51/52)

Newmarket—Formation of Reserve Room

...

...

...

145

5

3

156

10

9

301

16

0

Completed.

6

Kilmainham—Alterations

...

...

...

...

...

183

16

5

183

16

5

Completed.

7

Dalkey—Electrical Installation

...

...

...

...

82

13

0

82

13

0

Completed.

14

Irishtown—Improvements

...

...

...

...

57

14

6

57

14

6

In progress.

17

Dublin Castle Detective Branch—Improvements

...

...

233

15

1

233

15

1

Nearing completion.

22

Bridewell—Improvements

...

...

...

...

...

147

16

8

147

16

8

Virtually completed.

Provincial Barracks:

 

 

 

 

 

 

 

 

 

 

39/2 of 1951/52

Arva, Co. Cavan—Provision of Baths, etc.

...

...

...

42

15

10

100

0

0

142

15

10

Completed.

39/14 of 1951/52

Stradone, Co. Cavan—Alterations

...

...

...

...

37

11

0

60

0

0

97

11

0

Completed.

19

Castledermot, Co. Kildare—Installation of Electricity

...

97

5

0

97

5

0

In progress.

4

Mullinavat, Co. Kilkenny—Electrical Installation

...

...

98

7

3

98

7

3

Completed.

15

Kinlough, Co. Leitrim—Sanitary works, etc.

...

...

235

0

0

235

0

0

In progress.

11

Pallasgreen, Co. Limerick—Electrical Installations

...

...

226

0

0

226

0

0

Completed.

39/6 of 1951/52

Patrickswell, Co. Limerick—New Sanitary Appliances, etc.

...

10

0

0

167

8

0

177

8

0

Completed.

23

Keel, Co. Mayo—Electrical Installation

...

...

...

172

16

8

172

16

8

Completed.

16

Tullamore, Co. Offaly—Improvement of Drainage system

...

181

9

6

181

9

6

Completed.

9

Ballymote, Co. Sligo—Concreting yard, etc.

...

...

156

0

0

156

0

0

Completed.

12

Barnderrig, Co. Wicklow—Sinking of well and erection of

 

 

 

 

 

 

 

 

 

 

 

pump

...

...

...

...

...

...

...

...

1

10

0

1

10

0

Tender under consideration.

29

Rochfortbridge, Co. Westmeath—Electrical Installation

...

30

1

2

30

1

2

Completed.

 

 

£2,379

12

4

 

 

 

 

 

 

 

 

No. 111—MINOR NEW WORKS.

 

 

 

 

 

 

 

 

 

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

52

Áras an Uachtaráin—Improvements at Butler’s House

...

218

2

2

218

2

2

Virtually complete.

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

45

Library—Improvement of lighting

...

...

...

...

2

2

5

2

2

5

Tender accepted.

48

Entrance—Provision of seats

...

...

...

...

...

30

15

0

30

15

0

In progress.

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

92/2 of 1951/52

Statistics Office, 3 Cathal Brugha Street, Dublin—

26

6

9

42

6

8

311

5

5

Completed.

5

Improvement of heating

...

...

...

...

...

...

242

12

0

 

 

 

 

 

 

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Civil Service Commission:

 

 

 

 

 

 

 

 

 

 

91/51 of 1951/52

45 Upper O’Connell Street, Dublin—Improvement of

 

 

 

 

 

 

 

 

 

 

 

heating

...

...

...

...

...

...

...

127

13

0

2

0

5

129

13

5

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

91/43 of 1951/52

Headquarters: Finance Solicitor’s Office—Sub-division of

 

 

 

 

 

 

 

 

 

 

 

room

...

...

...

...

...

...

...

56

8

0

147

11

11

203

19

11

Completed.

91/67 of 1951/52

Headquarters: Secretariat—Improved lighting

...

...

245

10

7

10

17

0

256

7

7

Completed.

32

Headquarters: Provision of plugs for Dictating Machines

66

14

0

66

14

0

In progress.

59

Headquarters: Sub-division of room

...

...

...

63

0

10

63

0

10

In progress.

91/61 of 1951/52

Dún Laoghaire, Harbour Master’s Office—Improvements

...

209

14

3

121

0

11

330

15

2

In progress.

 

Pay-Master General’s Office:

 

 

 

 

 

 

 

 

 

 

91/44 of 1951/52

3 Lr. Ormond Quay—Improvement of lighting

...

...

93

0

0

92

16

4

185

16

4

Completed.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

91/31 of 1951/52

Dublin Castle, Clock Tower Building—Improved Heating

...

106

0

0

13

9

5

119

9

5

Completed.

91/76 of 1951/52

Dublin Castle, Legislation Section—Provision of Stoves

...

285

10

7

68

8

8

353

19

3

Completed.

18

Dublin Castle, Companies Branch—Improvements

...

142

17

6

142

17

6

Completed.

28

Dublin Castle, Adjudication Branch—Erection of Partitions

113

2

2

113

2

2

Virtually complete.

38

Dublin Castle, Block 10—Provision of shelving

...

...

149

7

8

149

7

8

Completed.

50

Dublin Castle, Public Departments Branch—Extension of

 

 

 

 

 

 

 

 

 

 

 

H.W. System

...

...

...

...

...

...

125

10

0

125

10

0

Completed.

91/56 of 1951/52

Bridgend Frontier Post—Improvements

...

...

...

24

7

0

150

0

0

174

7

0

Completed.

20

Dundalk Taxes Office—Provision of shelving, etc.

...

...

214

10

0

214

10

0

Completed.

14

Estate Duty Office, 21 St. Stephen’s Green—Supply of

 

 

 

 

 

 

 

 

 

 

 

Filing Units

...

...

...

...

...

...

135

15

3

135

15

3

Completed.

51

Tralee Custom House—Provision of Thermal Storage

 

 

 

 

 

 

 

 

 

 

 

Heaters

...

...

...

...

...

...

...

143

12

0

143

12

0

Completed.

 

Valuation Office:

 

 

 

 

 

 

 

 

 

 

91/47 of 1951/52

Headquarters—Improvements to Drawing Office

...

...

404

6

7

8

2

8

412

9

3

Completed.

 

General:

 

 

 

 

 

 

 

 

 

 

26

State Apartments, Dublin Castle—Provision of Presidential

 

 

 

 

 

 

 

 

 

 

 

Arms, etc.

...

...

...

...

...

...

...

187

1

11

187

1

11

Completed.

65

State Apartments, Dublin Castle—Inauguration of the

 

 

 

 

 

 

 

 

 

 

 

third President

...

...

...

...

...

...

370

5

9

370

5

9

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

139/28 of 1950/51

Headquarters—Provision of Enquiry Office

...

...

...

6

5

0

385

10

8

391

15

8

Completed.

91/50 of 1951/52

Headquarters—Facilities for serving morning tea

...

...

71

10

0

137

15

11

209

5

11

Completed.

42

Athenry Agricultural College—Improvement of Entrance

...

207

0

0

207

0

0

Completed.

6

Ballyhaise Agricultural College—Improvements to Dairy

...

236

17

0

236

17

0

Completed.

23

Ballyhaise Agricultural College—Tarmacadam surfacing

...

173

7

0

173

7

0

Completed.

22

Botanic Gardens—Alterations to Hayshed

...

...

...

298

19

6

298

19

6

Completed.

12

Munster Institute—Improvements at Gardener’s Cottage

...

352

5

6

352

5

6

Completed.

9

Fisheries Branch—Provision of Shelving

...

...

...

102

14

0

102

14

0

Completed.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

24

Juvenile Court, Dublin Castle—Improvement of Heating

...

170

15

8

170

15

8

Completed.

55

District Courts—Adaptation of room for Court Clerk

...

161

8

4

161

8

4

Completed.

39/7 of 1951/52

Garda Depot—Alterations to heating in Sergeants’ Mess

...

74

1

10

60

6

4

134

8

2

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

21

National Library—Provision of Shelving

...

...

...

233

0

0

233

0

0

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

Land Commission:

 

 

 

 

 

 

 

 

 

 

11

7/8 Hume Street—Partitioning, Improvement of Lighting,

 

 

 

 

 

 

 

 

 

 

 

etc.

...

...

...

...

...

...

...

...

419

4

7

419

4

7

Completed.

25

Merrion Street—Provision of Additional Sanitary

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

210

7

10

210

7

10

Completed.

33

61 Merrion Square—Partitioning, etc., of store at rere

...

223

13

9

223

13

9

Completed.

43

61 Merrion Square—Alterations etc., to rooms on 1st and

 

 

 

 

 

 

 

 

 

 

 

3rd floors

...

...

...

...

...

...

...

209

16

5

209

16

5

In progress.

 

Gaeltacht Services Branch:

 

 

 

 

 

 

 

 

 

 

91/46 of 1951/52

Carraroe Knitting Centre—Adaptations, etc.

...

...

25

14

0

365

14

7

391

8

7

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

139/39 of 1950/51

Kildare Street—Sound-proofing “copy room” and erection

 

 

 

 

 

 

 

 

 

 

 

of porch

...

...

...

...

...

...

1

14

6

162

7

7

164

2

1

Completed.

91/32 of 1951/52

Kildare Street—Sound proofing four rooms

...

...

...

 

15

0

212

16

10

213

11

10

Completed.

91/65 of 1951/52

Kildare Street—Alterations in room No. 12

...

...

...

260

4

3

20

13

7

280

17

10

Completed.

40

Kildare Street—Improvement of heating of Registry

...

112

5

7

112

5

7

Completed.

58

Kildare Street—Provision of Shelving

...

...

...

4

11

10

4

11

10

In progress.

62

Gas, Weights and Measures Office—Dublin Castle—Electrical

 

 

 

 

 

 

 

 

 

 

 

Installation

...

...

...

...

...

...

...

356

4

5

356

4

5

Completed.

53

Industrial and Commercial Property Registration Office, 44

 

 

 

 

 

 

 

 

 

 

 

Merrion Square—Provision of Shelving

...

...

...

99

12

3

 

 

 

99

12

3

In progress.

139/42 of 1950/51

Mercantile Marine Office—Alterations

...

...

...

51

17

0

155

13

0

207

10

0

Completed.

 

Department of Posts and Telegraphs:*

 

 

 

 

 

 

 

 

 

 

91/41 of 1951/52

Aldboro House—Structural work in connection with heating

17

0

2

495

12

6

512

12

8

Completed.

13

Four Courts, Dublin—Provision of Storage Accommodation

238

0

3

238

0

3

Completed.

91/54 of 1951/52

St. Mary’s Abbey Stores—Adaptations, etc.

...

...

147

19

6

59

18

10

207

18

4

In progress.

30

Pearse Street Sorting Office—Provision of Cycle

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

...

201

2

2

201

2

2

Completed.

39

Pearse Street Sorting Office—Provision of Enclosure Porch

 

 

 

 

 

 

 

 

 

 

 

and Strong-room

...

...

...

...

...

...

192

3

4

192

3

4

In progress.

31

Clifden Post Office—Improvements

...

...

...

...

120

0

0

120

0

0

In progress.

10

Cork Sorting Office—Adaptation of room

...

...

...

105

18

3

105

18

3

Completed.

2

Galway Post Office—Adaptations

...

...

...

...

58

4

2

58

4

2

Completed.

8

Valentia Island Wireless Station—Provision of Fuel Storage

 

 

 

 

 

 

 

 

 

 

 

Accommodation, etc.

...

...

...

...

...

285

17

6

285

17

6

Completed.

91/78 of 1951/52

Post Office Savings Bank—Sound-proofing machine room

...

152

3

0

134

19

2

287

2

2

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

91/42 of 1951/52

Parkgate Street—Provision of Extract Fans

...

...

33

6

6

74

7

1

107

13

7

Completed.

36

Parkgate Street—Partitioning of room, etc.

...

...

...

183

5

4

183

5

4

Completed.

35

Marlboro’ Hall—Alterations at Luncheon Club

...

...

116

4

0

116

4

0

Completed.

47

Army Pensions Board—St. Bricin’s Hospital—Provision of

 

 

 

 

 

 

 

 

 

 

 

doors and curtains for pigeon holes

...

...

...

349

1

0

349

1

0

Completed.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

91/33 of 1951/52

Iveagh House—Improved Lighting in Library, etc.

...

29

19

5

119

7

3

149

6

8

Completed.

3

Iveagh House—Provision of additional kitchen equipment

164

15

6

164

15

6

Completed.

27

Iveagh House—Partitioning room

...

...

...

...

111

12

8

111

12

8

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

139/54 of 1950/51

Belmullet Employment Exchange—Provision of Shelving, etc.

3

1

2

9

14

3

12

15

5

In progress.

17

Cork Employment Exchange—Transfer of Staff

...

...

167

6

9

167

6

9

Completed.

56

Victoria Street, Dublin, Employment Exchange—

 

 

 

 

 

 

 

 

 

 

 

Improvements

...

...

...

...

...

...

...

...

97

6

5

97

6

5

In progress.

66

Ship Street Barracks—Alterations, etc., and Transfer of Staff

377

5

9

377

5

9

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

46

Dublin Custom House—Alterations to Annexe

...

184

16

8

184

16

8

Completed.

91/21 of 1951/52

Dundrum Asylum—Extension of Shed at Ball-Alley

...

89

0

0

295

18

8

384

18

8

Completed.

91/63 of 1951/52

Dundrum Asylum—New Washing Machine

...

...

...

233

7

5

27

13

10

261

1

3

Completed.

139/66 of 1950/51

Dundrum Asylum—Improvements to Sleeping Quarters

...

 

5

0

312

5

8

312

10

8

Completed.

 

 

£11,507

12

7

 

 

 

 

 

 

 

 

No. 112—URGENT AND UNFORESEEN WORKS.

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

12

Earlsfort Terrace Workshop—Adaptation of former stable

1,477

17

7

1,477

17

7

In progress.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

2

C. & E. Dublin Castle—Adaptations, etc.

...

...

572

6

7

572

6

7

In progress.

22

Accountant General’s Office—Structural and electrical work

184

7

2

184

7

2

In progress.

 

Stationery Office:

 

 

 

 

 

 

 

 

 

 

21

Beggars Bush Barracks—Provision of Canteen

...

...

49

13

1

49

13

1

In progress.

 

Valuation Office:

 

 

 

 

 

 

 

 

 

 

20

Ordnance Survey Office—Installation of Machines, etc.

...

192

19

2

192

19

2

In progress.

 

General:

 

 

 

 

 

 

 

 

 

 

1

Removal and re-erection of ceilings from Mespil House

...

2,743

6

8

2,743

6

8

Completed.

24

State Apartments—Provision of Catering Facilities

...

561

12

10

561

12

10

In progress.

25

An Tóstal—Floodlighting of Government Buildings

...

3

14

9

3

14

9

In progress.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

16

Ballyhaise Agricultural College—Electrical Installations, etc.

179

16

4

179

16

4

In progress.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

23

Adoption Board, 45 St. Stephen’s Green—Structural

 

 

 

 

 

 

 

 

 

 

 

Alterations, etc.

...

...

...

...

...

...

...

218

5

2

218

5

2

In progress.

 

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

15

Housing Section—Provision of Filing Cabinets, and structural

 

 

 

 

 

 

 

 

 

 

 

work, etc.

...

...

...

...

...

...

711

10

10

711

10

10

In progress.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

19

Kildare Street—Installation of Germicidal Apparatus

...

536

16

11

536

16

11

Completed.

6

Labour Court, Griffith Barracks—Installation of Storage

 

 

 

 

 

 

 

 

 

 

 

Heaters

...

...

...

...

...

...

...

1,119

16

7

1,119

16

7

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

8

Marlboro’ Hall—Improvement of lighting

...

...

...

1,135

9

5

1,135

 

 

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

11

Árus Brugha—Adaptations, etc.

...

...

...

...

465

1

8

465

1

8

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

10 (91/70 of 1951/2)

General Register Office—Improvements, etc.

...

...

767

11

11

44

16

0

812

7

11

Completed.

4

Dundrum Asylum—New Lavatories

...

...

...

...

773

5

7

773

5

7

Completed.

 

 

£11,693

12

3

 

 

 

 

 

 

 

 

No. 113—MINOR BALANCES OF EXPENDITURE.

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

2 of 1951/52

Improvement of Entrance

...

...

...

...

...

1

6

4

7,602

0

2

7,602

6

6

Completed.

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

92/6 of 1951/52

Central Statistics Office, Dublin Castle—Improvements

...

746

13

4

393

19

4

1,140

12

8

Completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

92/13 of 1951/52

10 Hume Street—Electric Storage Heating

...

...

167

8

4

515

11

7

682

19

11

Completed

92/15 of 1951/52

51 St. Stephen’s Green—Engineers Branch New Office

...

155

0

0

455

16

6

610

16

6

Completed.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

4 of 1951/52

Dublin Castle—Renovations

...

...

...

...

523

6

7

4,500

18

0

5,024

4

7

Completed.

 

General:

 

 

 

 

 

 

 

 

 

 

3 of 1950/51 3 of 1951/52

Iveagh House—Office Accommodation and Staff Restaurant

13,221

13

4

82,231

4

10

95,452

18

2

Completed.

5 of 1951/52

Dublin Custom House—Improvement of lay-out of Grounds

273

10

1

8,291

4

1

8,564

14

2

Completed.

91/73 of 1950/51 6/73 of 1951/52

Dublin Custom House—Staff Restaurant

...

...

...

1,436

0

1

7,279

18

7

8,715

18

8

In progress.

92/22 of 1951/52

Papal Nunciature—Extension of Accommodation

...

...

542

17

9

693

6

0

1,236

3

9

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

140/4 of 1950/51

Government Buildings—Provision of improved

 

 

 

 

 

 

 

 

 

 

93 of 1951/52

accommodation for typing staff, etc.

...

...

...

...

...

1,163

9

10

1,621

15

9

2,785

5

7

Completed.

92/8 of 1951/52

Botanic Gardens—Electriclighting sheds and boiler house

...

52

10

9

487

12

2

540

2

11

Completed.

23 of 1951/52

Ballyhaise Agricultural College—New Piggeries

...

...

55

15

0

7,635

17

7

7,691

12

7

Completed.

25 of 1951/52

Clonakilty Agricultural College—Poultry Hatchery

...

163

14

2

2,361

1

4

2,524

15

6

Completed.

92/14 of 1951/52

Fisheries Branch—Accommodation for Parliamentary

 

 

 

 

 

 

 

 

 

 

 

Secretary

...

...

...

...

...

...

...

...

56

6

6

562

4

10

618

11

4

Completed.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

47 of 1949/50

Public Record Office—Restoration of Air-raid shelter as Record

 

 

 

 

 

 

 

 

 

 

141 of 1950/51

Repository

...

...

...

...

...

...

...

209

19

10

121

17

7

331

17

5

Completed.

 


Work No.

Service and Description

Expenditure

Observations

1952-53

to 31/3/52

to 31/3/53

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Courts of Justice:

 

 

 

 

 

 

 

 

 

 

233/10 of 1949/50

Adaptation of rooms

...

...

...

...

...

37

10

0

1,083

11

2

1,121

1

2

Completed.

39a of 1951/52

Audibility Improvements at Metropolitan District Courts

...

511

8

7

21

7

3

532

15

10

In progress.

92/11 of 1951/52

Structural Alterations etc., at Restaurant

...

...

467

10

8

1,981

9

7

2,449

0

3

Completed.

 

Garda Síochána:

 

 

 

 

 

 

 

 

 

 

233/1 of 1949/50

Headquarters—Transfer to Depot

...

...

...

...

19

0

7

18,801

3

2

18,820

3

9

Completed.

36 of 1951/52

Dublin Castle—Garage Accommodation

...

...

...

697

6

2

268

2

5

965

8

7

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

40a of 1951/52

Headquarters Office—Adaptations

...

...

...

...

1,958

19

0

376

4

3

2,335

3

3

Completed.

44 of 1951/52

National Gallery—Electric Installation

...

...

...

212

10

10

6,263

16

7

6,476

7

5

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

105 of 1950/51

Headquarters Buildings—Adaptations

...

...

...

104

4

1

10,869

14

2

10,973

18

3

Completed.

 

Gaeltacht Services Branch:

 

 

 

 

 

 

 

 

 

 

141 of 1949/50

Bruckless Lace Centre—Renovation and extension

...

76

15

0

1,554

18

5

1,631

13

5

Completed.

107 of 1950/51

Geesala Knitting Centre—Improvements

...

...

...

 

14

10

1,570

5

5

1,571

0

3

Completed.

46 of 1951/52

Elly Bay Toy Factory—Rebuilding

...

...

...

75

14

10

5,602

14

10

5,678

9

8

Completed.

48 of 1951/52

Falcarragh Knitting Centre—Adaptations

...

...

...

150

4

11

1,331

15

9

1,482

0

8

Completed.

92/16 of 1951/52

Carratigue Knitting Centre—Improvements

...

...

108

16

3

250

0

0

358

16

3

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

111 of 1950/51

Kildare Street—New Headquarters

...

...

...

...

33

0

0

255,748

4

3

255,781

4

3

Completed.

140/1 of 1950/51

Kildare Street—Provision of water storage tank

...

...

152

3

7

1,593

4

3

1,745

7

10

Completed.

140/12 of 1950/51

Griffith Barracks—Adaptations, etc., for Prices Advisory Body

1

1

0

4,176

12

6

4,177

13

6

Completed.

234 of 1949/50

Meteorological Services—Fencing, etc., of Rainfall Gauges

...

8

0

0

689

18

8

697

18

8

Completed.

 

Department of Posts and Telegraphs:*

 

 

 

 

 

 

 

 

 

 

119 of 1950/51

Dundalk Post Office—Improvements

...

...

...

...

51

6

9

4,278

6

4

4,329

13

1

Completed.

121 of 1950/51

Loughrea Post Office—Adaptations

...

...

...

...

1

17

11

1,164

3

1

1,166

1

0

Completed.

122 of 1950/51

Nenagh Post Office—Improvements

...

...

...

...

80

0

0

1,132

11

11

1,212

11

11

Completed.

63 of 1951/52

Boyle Post Office—Adaptations

...

...

...

...

19

15

9

340

0

0

359

15

9

Completed.

71 of 1951/52

Wexford Post Office—Adaptations

...

...

...

...

115

18

0

354

3

3

470

1

3

Completed.

92/1 of 1951/52

Newbridge Military Barracks—Adaptations for Stores

...

55

9

5

841

14

7

897

4

0

Completed.

92/18 of 1951/52

Caherciveen Post Office—Adaptations

...

...

...

300

0

0

452

10

0

752

10

0

Completed.

92/19 of 1951/52

Glencree former Reformatory—Adaptations for Stores

...

276

6

0

450

0

0

726

6

0

In progress.

186/10 of 1947/48

Wireless Broadcasting—Adaptation of Portobello former Post

 

 

 

 

 

 

 

 

 

 

 

Office

...

...

...

...

...

...

...

24

6

3

870

5

0

894

11

3

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

140/16 of 1950/51

School of Defence—Adaptations, etc.

...

...

...

233

14

10

1,543

19

1

1,777

13

11

Completed.

77 of 1951/52

Collins Barracks, Cork—Married Quarters

...

...

...

7

10

0

26,710

12

10

26,718

2

10

Completed.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

233/180 of 1949/50

Lisbon Legation—Improvements, etc.

...

...

...

7

6

4

3,871

9

9

3,878

16

1

Completed.

92/24 of 1951/52

Stockholm Legation—Works and Furniture

...

...

465

9

0

817

4

5

1,282

13

5

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

134 of 1950/51 84 of 1951/52

Kilkenny Employment Exchange—Adaptations

...

...

378

16

8

712

10

0

1,091

6

8

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

89 of 1951/52

Dundrum Asylum—Improved Cooking Facilities

...

...

627

19

11

1,296

7

11

1,924

7

10

Completed.

92/25 of 1951/52

Dundrum Asylum—Recreation Room for Attendants

...

68

12

0

33

19

9

102

11

9

Completed.

 

 

£26,099

1

1

 

 

 

 

 

 

 

*Excluding amount chargeable to Telephone Capital.


†Excluding amount chargeable to Telephone Capital and Vote for Posts and Telegraphs.


‡Excluding amount chargeable to Vote for Posts and Telegraphs.


*Excluding amounts, if any, chargeable to Telephone Capital Account.


*Excluding amount chargeable to Telephone Capital Account.