Committee Reports::Report - Appropriation Accounts 1962 - 1963::12 November, 1964::Appendix

Qn. 277.


APPENDIX XXII.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1962-63 (VOTE 9, SUBHEAD B).

Work
No.

Service and Description

Total
Estimate

Vote
1962-63

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

£

£

s.

d.

£

s.

d.

£

s.

d.

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

 

 

1

Árus an Uachtaráin—Improvement of Planthouse Accommodation

8,250

5,000

2,924

3

7

262

5

11

3,186

9

6

In progress.

 

Total:

 

 

5,000

2,924

3

7

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

 

 

2

Leinster House—Extension

...

...

...

...

...

...

300,000

90,000

49,034

8

4

59 6,549

14 18

2 4

55,644

0

10

In progress.

 

Total:

 

 

90,000

49,034

8

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

 

3

State Apartments—Restoration of burnt-out Drawing Rooms

...

104,000

1,000

103

18

6

6,092

11

2

6,196

9

8

In planning.

 

Total:

 

 

1,000

103

18

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

 

4

Statue of Thomas Davis

...

...

...

...

...

...

...

6,500

1,000

214

1

8

150

0

0

364

1

8

Commissioned.

5

Central Heating Station—Renewal of Plant

...

...

...

...

50,000

25,000

88

10

0

—

88

10

0

In progress.

6

State Buildings (Upper Merrion Street and Kildare Street)—New

 

 

 

 

 

 

 

 

 

 

 

 

 

Electricity Distribution System

...

...

...

...

...

5,500

5,300

—

97

1

7

97

1

7

In planning.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

 

 

7

Dublin Castle—Rebuilding of Cross Block

...

...

...

115,000

60,000

21,246

4

11

16,886

7

9

38,132

12

8

In progress.

8

Stamping Branch—New Premises

...

...

...

...

525,000

2,000

—

2,270

16

11

2,270

16

11

In planning.

9

Carrickcarnan Customs Frontier Post—Office and Residence

15,000

10,000

10,376

0

0

1,599

0

2

11,975

0

2

Virtually completed.

10

Dundalk, New Customs Road Station

...

...

...

...

17,500

250

—

—

—

In planning.

11

Lifford Customs Post—Erection

...

...

...

...

...

9,500

5,000

—

—

—

Tenders under consideration.

12

Wexford, New Government Office and Telephone Exchange

...

33,000

12,000

4,100

0

1

3

3

0

4,103

3

1

In progress.

13

Government Publications Sale Office—Additional Accommodation

...

3,000

2,000

—

—

—

In planning.

14

Phoenix Park—Improvement of Water Supply

...

...

...

25,000

14,000

758

14

9

270

8

0

1,029

2

9

Planning completed.

 

Rotunda Gardens:

 

 

 

 

 

 

 

 

 

 

 

 

15

Garden of Remembrance—Architectural Works

...

...

144,000

75,000

57,332

0

0

40,708

15

0

98,040

15

0

In progress.

16

Memorial Sculpture

...

...

...

...

...

...

—

1,000

—

—

—

Under consideration.

 

Dún Laoghaire Harbour:

 

 

 

 

 

 

 

 

 

 

 

 

17

Mail Boat Pier Improvements

...

...

...

...

...

208,300

60,000

59,127

3

7

116,554

8

9

175,681

12

4

In progress.

18

Car Ferry Terminal

...

...

...

...

...

...

300,000

90,000

2,307

3

4

—

2,307

3

4

Trial-boring completed.

18A*

River Shannon—Bailey Bridge Offaly

...

...

...

...

...

—

—

2,144

0

0

—

2,144

0

0

Completed.

 

Total:

 

 

362,550

157,693

18

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

 

 

19

Garda Síochána Depot—Extension of Garage and Workshop

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

54,000

1,000

—

—

—

In planning.

20

New Garda Training Centre—Templemore—Adaptation, etc., works

435,000

200,000

207,708

5

9

93,506

5

3

301,214

11

0

In progress.

21

Erection of new Garda Síochána Stations and improvement of

 

 

 

 

 

 

 

 

 

 

 

 

 

existing specified Stations

...

...

...

...

...

...

375,000

140,000

93,313

7

9

 

 

 

 

 

 

 

 

 

 

 

 

(as under)

(detailed as follows)

 

 

 

 

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

 

 

 

 

 

 

Cabra—New Station

...

...

...

...

...

...

38,000

22,000

22,870

0

0

815

12

4

23,685

12

4

In progress.

 

Crumlin—New Divisional Headquarters

...

...

...

...

41,000

10,000

3,366

12

11

—

3,366

12

11

In progress.

 

Division of Dublin-Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

 

Clondalkin—New Station

...

...

...

...

...

...

12,000

2,000

—

—

—

In planning.

 

Divisional and District Headquarters Outside Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

 

Roscommon—New Divisional Headquarters

...

...

...

25,000

3,000

4,420

12

0

18,644

12

8

23,065

4

8

Completed.

 

Bantry—New District Headquarters

...

...

...

...

10,000

5,000

4,905

0

0

3,760

10

3

8,665

10

3

Virtually completed.

 

Ballyconnell—New District Headquarters

...

...

...

13,000

5,000

342

17

8

—

342

17

8

In progress.

 

Other New Stations as under:

200,000

80,000

47,458

8

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Co. Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

 

Cootehill

...

...

...

...

...

...

...

...

 

 

450

0

0

—

450

0

0

In progress.

 

Killeshandra

...

...

...

...

...

...

...

 

 

2,520

0

0

—

2,520

0

0

In progress.

 

Kingscourt

...

...

...

...

...

...

...

...

 

 

3,600

0

0

—

3,600

0

0

In progress.

 

Co. Clare:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ardnacrusha

...

...

...

...

...

...

...

 

 

—

—

—

In planning.

 

Labasheeda

...

...

...

...

...

...

...

...

 

 

273

17

6

—

273

17

6

In planning (work completed on well).

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

 

Castletownroche

...

...

...

...

...

...

...

 

 

—

—

—

Tenders invited.

 

Donoughmore

...

...

...

...

...

...

...

 

 

—

—

—

Contract placed.

 

Kinsale

...

...

...

...

...

...

...

...

 

 

—

—

—

Tenders invited.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

 

 

 

Burtonport

...

...

...

...

...

...

...

...

 

 

—

—

—

Tenders under consideration.

 

Carndonagh

...

...

...

...

...

...

...

...

 

 

—

—

—

Contract placed.

 

Castlefin

...

...

...

...

...

...

...

...

 

 

3,420

0

0

—

3,420

0

0

In progress.

 

Co. Galway:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ahascragh

...

...

...

...

...

...

...

...

 

 

2,250

0

0

—

2,250

0

0

In progress.

 

Portumna

...

...

...

...

...

...

...

...

 

 

5,478

0

0

—

5,478

0

0

In progress.

 

Co. Kerry:

 

 

 

 

 

 

 

 

 

 

 

 

 

Kilgarvan

...

...

...

...

...

...

...

...

 

 

153

0

0

—

153

0

0

Planning completed (work completed on well).

 

Co. Leitrim:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballinamore

...

...

...

...

...

...

...

 

 

—

—

—

Contract about to be placed.

 

Cloone

...

...

...

...

...

...

...

...

 

 

3,060

0

0

257

1

6

3,317

1

6

In progress.

 

Co. Louth:

 

 

 

 

 

 

 

 

 

 

 

 

 

Castlebellingham

...

...

...

...

...

...

...

 

 

1,890

0

0

—

1,890

0

0

In progress.

 

Co. Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Killala

...

...

...

...

...

...

...

...

 

 

2,880

0

0

—

2,880

0

0

In progress.

 

Co. Meath:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballivor

...

...

...

...

...

...

...

...

 

 

1,170

0

0

—

1,170

0

0

In progress.

 

Enfield

...

...

...

...

...

...

...

...

 

 

2,385

0

0

1,300

0

0

3,685

0

0

Completed.

 

Slane

...

...

...

...

...

...

...

...

...

 

 

450

0

0

—

450

0

0

In planning.

 

Co. Monaghan:

 

 

 

 

 

 

 

 

 

 

 

 

 

Clontibret

...

...

...

...

...

...

...

...

 

 

3,060

0

0

146

10

9

3,206

10

9

In progress.

 

Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

 

Banagher

...

...

...

...

...

...

...

...

 

 

2,250

0

0

—

2,250

0

0

In progress.

 

Co. Roscommon:

 

 

 

 

 

 

 

 

 

 

 

 

 

Kilmore

...

...

...

...

...

...

...

...

 

 

292

0

0

—

292

0

0

Well boring completed.

 

Strokestown

...

...

...

...

...

...

...

...

 

 

1,170

0

0

—

1,170

0

0

In progress.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballinafad

...

...

...

...

...

...

...

...

 

 

—

—

—

In planning.

 

Collooney

...

...

...

...

...

...

...

...

 

 

5,400

0

0

—

5,400

0

0

In progress.

 

Co. Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballingarry North

...

...

...

...

...

...

...

 

 

230

6

0

—

230

6

0

In progress.

 

Grangemockler

...

...

...

...

...

...

...

 

 

1,372

1

6

3,452

15

10

4,824

17

4

Completed.

 

Co. Westmeath:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballymore

...

...

...

...

...

...

...

...

 

 

10

0

0

—

10

0

0

In progress.

 

Rochfortbridge

...

...

...

...

...

...

...

 

 

810

0

0

—

810

0

0

In progress.

 

Co. Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Glynn

...

...

...

...

...

...

...

...

...

 

 

2,884

3

4

6,031

13

0

8,915

16

4

Completed.

 

Co. Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

 

Rathdrum

...

...

...

...

...

...

...

...

 

 

—

—

—

In planning.

 

Improvement Schemes as under:

36,000

13,000

9,949

16

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

Dublin Metropolitan Division:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bridewell

...

...

...

...

...

...

...

...

 

 

2,891

0

9

18,842

13

8

21,733

14

5

Completed.

 

Parkgate Hall, Conyngham Road

...

...

...

...

...

 

 

443

8

11

945

13

2

1,389

2

1

Completed.

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

 

Inchigeela

...

...

...

...

...

...

...

...

 

 

924

10

7

454

2

6

1,378

13

1

Completed.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

 

 

 

Buncrana

...

...

...

...

...

...

...

...

 

 

1,508

15

10

—

1,508

15

10

Completed.

 

Co. Galway:

 

 

 

 

 

 

 

 

 

 

 

 

 

Leenane

...

...

...

...

...

...

...

...

 

 

1,604

2

3

131

17

4

1,735

19

7

Completed.

 

Oranmore

...

...

...

...

...

...

...

...

 

 

1,033

7

6

64

0

4

1,097

7

10

Completed.

 

Co. Limerick:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bruff

...

...

...

...

...

...

...

...

 

 

—

—

—

In planning.

 

Pallas

...

...

...

...

...

...

...

...

 

 

—

917

18

6

917

18

6

Completed.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

 

Bunninadden

...

...

...

...

...

...

...

 

 

324

0

0

461

18

2

785

18

2

Completed.

 

Sligo

...

...

...

...

...

...

...

...

...

 

 

860

11

0

630

0

0

1,490

11

0

Completed.

 

Co. Waterford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Ballymacarbery

...

...

...

...

...

...

...

 

 

—

1,302

15

0

1,302

15

0

Completed.

 

Co. Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

 

Blackwater

...

...

...

...

...

...

...

...

 

 

360

0

0

—

360

0

0

In progress.

22

Improvement of other Garda Síochána Stations:

20,000

20,000

14,709

19

9

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Co. Carlow:

 

 

 

 

 

 

 

 

 

 

 

 

37/48 of 61/62

Muinebeag

...

...

...

...

...

...

...

...

 

 

788

0

0

1

5

0

789

5

0

In progress.

 

Co. Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

22/52

Stradone

...

...

...

...

...

...

...

...

 

 

200

0

0

—

200

0

0

In progress.

 

Co. Clare:

 

 

 

 

 

 

 

 

 

 

 

 

22/21

Lissyeasey

...

...

...

...

...

...

...

...

 

 

108

15

0

—

108

15

0

Completed.

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

22/35

Ballinspittle

...

...

...

...

...

...

...

...

 

 

327

11

2

—

327

11

2

Completed.

22/33

Coachford

...

...

...

...

...

...

...

...

 

 

616

10

4

—

616

10

4

Completed.

22/24

Fermoy

...

...

...

...

...

...

...

...

 

 

662

12

5

—

662

12

5

Completed.

22/61

Union Quay

...

...

...

...

...

...

...

...

 

 

135

13

0

—

135

13

0

Completed.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

 

 

27/21 of 61/62

Annagry

...

...

...

...

...

...

...

...

 

 

83

2

8

250

0

0

333

2

8

Completed.

22/40

Muff

...

...

...

...

...

...

...

...

...

 

 

900

0

0

—

900

0

0

In progress.

26 of 61/62

Rathmullen

...

...

...

...

...

...

...

...

 

 

218

17

2

650

0

0

868

17

2

In progress.

 

Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

 

Pearse Street (College):

 

 

 

 

 

 

 

 

 

 

 

 

22/60

New Mess Hall

...

...

...

...

...

...

...

 

 

293

15

6

—

293

15

6

In progress.

27/33 of 61/62

Canteen Improvements

...

...

...

...

...

...

 

 

27

8

9

156

11

7

184

0

4

Completed.

22/19

Accommodation for Ban Gárdaí

...

...

...

...

...

 

 

383

9

1

—

383

9

1

In progress.

22/25

Clontarf

...

...

...

...

...

...

...

...

 

 

343

3

5

—

343

3

5

Completed.

22/45

Cabinteely

...

...

...

...

...

...

...

...

 

 

112

7

3

—

112

7

3

In progress.

27/50 of 61/62

Kevin Street

...

...

...

...

...

...

...

 

 

21

1

9

427

8

4

448

10

1

Completed.

27/29 of 61/62

Kilmainham

...

...

...

...

...

...

...

...

 

 

24

0

6

140

1

11

164

2

5

Completed.

22/23

Store Street

...

...

...

...

...

...

...

...

 

 

528

17

10

—

528

17

10

In progress.

 

Co. Galway:

 

 

 

 

 

 

 

 

 

 

 

 

27/32 of 61/62

Clifden

...

...

...

...

...

...

...

...

 

 

254

7

0

 

16

0

255

3

0

Completed.

27/34 of 61/62

Headford

...

...

...

...

...

...

...

...

 

 

480

0

0

24

6

9

504

6

9

Completed.

22/3

Lettermore

...

...

...

...

...

...

...

...

 

 

140

10

3

—

140

10

3

Completed.

 

Co. Kildare:

 

 

 

 

 

 

 

 

 

 

 

 

22/20

Castledermot

...

...

...

...

...

...

...

...

 

 

636

11

0

—

636

11

0

Completed.

22/34

Kilcock

...

...

...

...

...

...

...

...

 

 

300

0

0

—

300

0

0

In progress.

 

Laois:

 

 

 

 

 

 

 

 

 

 

 

 

22/28

Ballylinan

...

...

...

...

...

...

...

 

 

600

0

0

—

600

0

0

Completed.

 

Co. Leitrim.

 

 

 

 

 

 

 

 

 

 

 

 

22/30

Carrick-on-Shannon

...

...

...

...

...

...

...

 

 

100

0

0

—

100

0

0

Completed.

 

Co. Limerick:

 

 

 

 

 

 

 

 

 

 

 

 

22/13

Askeaton

...

...

...

...

...

...

...

...

 

 

193

14

9

—

193

14

9

Completed.

27/57 of 61/62

Athea

...

...

...

...

...

...

...

...

 

 

517

12

6

1

5

0

518

17

6

Completed.

22/39

Limerick (Edward Street)

...

...

...

...

...

 

 

443

11

1

—

443

11

1

Completed.

27/37 of 61/62

Pallasgreen (New Pallas)

...

...

...

...

...

...

 

 

304

0

0

87

5

4

391

5

4

In progress.

 

Co. Louth:

 

 

 

 

 

 

 

 

 

 

 

 

22/26

Hackballscross

...

...

...

...

...

...

...

 

 

1,018

4

6

—

1,018

4

6

In progress.

 

Co. Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

22/15

Balla

...

...

...

...

...

...

...

...

 

 

381

10

9

—

381

10

9

Completed.

22/59

Bangor Erris

...

...

...

...

...

...

...

...

 

 

400

0

0

—

400

0

0

In progress.

27/8 of 61/62

Blacksod

...

...

...

...

...

...

...

...

 

 

64

5

0

338

6

7

402

11

7

Completed.

22/17

Cong

...

...

...

...

...

...

...

...

...

 

 

405

12

8

—

405

12

8

Completed.

22/7

Kiltimagh

...

...

...

...

...

...

...

...

 

 

214

14

6

—

214

14

6

In progress.

 

Co. Meath:

...

 

 

 

 

 

 

 

 

 

 

 

 

22/48

Oldcastle

...

...

...

...

...

...

...

...

 

 

180

0

0

—

180

0

0

In progress.

 

Co. Monaghan:

 

 

 

 

 

 

 

 

 

 

 

 

22/76

Corrinshigagh

...

...

...

...

...

...

...

...

 

 

350

0

0

—

350

0

0

In progress.

 

Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

22/27

Kilcormac

...

...

...

...

...

...

...

...

 

 

185

12

6

—

185

12

6

Completed.

 

Co. Roscommon:

 

 

 

 

 

 

 

 

 

 

 

 

27/30 of 61/62

Cootchall

...

...

...

...

...

...

...

...

 

 

198

12

6

600

0

0

798

12

6

Completed.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

22/10

Dromore West

...

...

...

...

...

...

...

 

 

270

15

0

—

270

15

0

Completed.

 

Co. Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

22/55

Thurles

...

...

...

...

...

...

...

...

 

 

233

13

0

—

233

13

0

In progress.

 

Co. Westmeath:

 

 

 

 

 

 

 

 

 

 

 

 

42/19 of 60/61

Kilbeggan

...

...

...

...

...

...

...

...

 

 

71

6

11

602

13

4

674

0

3

Completed.

 

Co. Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

22/31

Greystones

...

...

...

...

...

...

...

...

 

 

990

0

0

—

990

0

0

In progress.

23

Houses for married members of the Garda Síochána

...

...

25,000

25,000

101,254

0

0

—

101,254

0

0

In progress.

24

Courts of Justice—Renewal of Defective Stonework

...

...

...

50,000

10,000

1,460

13

7

3,485

0

10

4,945

14

5

Stage 1 completed.

 

Land Registry:

 

 

 

 

 

 

 

 

 

 

 

 

25

Improvements

...

...

...

...

...

...

...

7,500

450

370

5

4

7,002

7

8

7,372

13

0

Virtually completed.

26

Fire Precaution Works

...

...

...

...

...

...

5,200

2,600

3,460

17

11

330

14

7

3,791

12

6

In progress.

 

Total:

 

 

399,050

422,277

10

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

 

27

National Schools—Grants for Building, Enlarging, Enclosing, etc.

...

1,900,000

1,900,000

1,824,429

19

0

—

1,824,429

19

0

 

 

National Library:

 

 

 

 

 

 

 

 

 

 

 

 

28

Improvement of goods lift

...

...

...

...

...

...

1,375

500

525

0

0

900

15

10

1,425

15

10

Completed.

29

National Library and National Museum. Renewal of defective

 

 

 

 

 

 

 

 

 

 

 

 

 

stonework—Stage II

...

...

...

...

...

...

30,000

7,300

5,357

12

1

39,779

18

9

45,137

10

10

Nearing completion.

30

Dublin (Preventive Centre)—Erection

...

...

...

...

...

150,000

500

—

—

—

In planning.

31

National Gallery—Extension

...

...

...

...

...

...

277,000

250

2,411

5

4

—

2,411

5

4

In planning.

 

Total:

 

 

1,908,550

1,832,723

16

5

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

 

32

21-24 Upper Merrion Street Improvement of electrical installations

...

7,600

2,000

—

—

—

In planning.

 

Forestry Division:

 

 

 

 

 

 

 

 

 

 

 

 

33

Avondale House—Adaptation as Forestry Training and

 

 

 

 

 

 

 

 

 

 

 

 

 

Conference Centre

...

...

...

...

...

...

...

32,000

500

—

—

—

In planning.

34

Kinnitty Castle Forestry Training Centre—Additional

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation for Trainees and Fire Precaution Works

...

...

7,900

1,000

2,035

9

4

270 6,252

0 6

5 1

8,557

15

10

Completed.

 

Fisheries Division:

 

 

 

 

 

 

 

 

 

 

 

 

35

Galway, Fisheries Research Station—Erection

...

...

...

140,000

500

—

—

—

In planning.

36

Major Fishery Harbours (Stage 1)

...

...

...

...

1,260,000

140,000

57,058

7

0

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Castletownbere

...

...

...

...

...

...

...

 

 

7,181

3

4

1,038

14

7

8,219

17

11

Trial-borings completed.

 

Dunmore East

...

...

...

...

...

...

...

 

 

11,522

4

5

—

11,522

4

5

In planning.

 

Galway

...

...

...

...

...

...

...

...

 

 

21,316

17

7

2,420

2

7

23,737

0

2

Trial-borings completed.

 

Howth

...

...

...

...

...

...

...

...

...

 

 

2,406

9

11

1,512

6

6

3,918

16

5

Trial-borings in progress.

 

Killybegs

...

...

...

...

...

...

...

...

 

 

3,443

17

3

908 3,272

2 4

7 8

7,624

4

6

In planning.

 

Other expenditure

...

...

...

...

...

...

...

 

 

11,187

14

6

2,961

0

10

14,148

15

4

 

37

Works of Economic Development at other Fishery Harbours

...

70,210

50,000

24,157

17

5

 

 

 

 

 

 

 

 

 

 

 

(as under)

 

 

 

 

 

 

 

 

Aileen Reef

...

...

...

...

...

...

...

...

 

 

164

4

2

131

8

3

295

12

5

Completed.

 

Burtonport

...

...

...

...

...

...

...

...

 

 

1,493

12

1

3,074

15

4

4,568

7

5

Virtually completed.

 

Cahore

...

...

...

...

...

...

...

...

...

 

 

492

14

4

—

492

14

4

Completed.

 

Clogherhead

...

...

...

...

...

...

...

...

 

 

2,162

0

7

—

2,162

0

7

Nearing completion.

 

Dingle

...

...

...

...

...

...

...

...

 

 

3

11

4

4,650

0

0

4,653

11

4

Completed.

 

Greencastle

...

...

...

...

...

...

...

...

 

 

19,354

18

2

12,240

12

6

31,595

10

8

In progress.

 

Giles Quay

...

...

...

...

...

...

...

...

 

 

452

12

0

—

452

12

0

Completed.

 

Kilmore Quay

...

...

...

...

...

...

...

 

 

34

4

9

—

34

4

9

In planning.

 

Total:

 

 

194,000

83,251

13

9

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

 

 

 

Veterinary College, Ballsbridge:

 

 

 

 

 

 

 

 

 

 

 

 

38 (1)

Improvements

...

...

...

...

...

...

...

20,000

5,000

5,703

2

5

9,578

0

3

15,281

2

8

Virtually completed.

38 (2)

Pathological Anatomy Unit

...

...

...

...

...

11,900

6,000

1,839

12

0

150

0

0

1,989

12

0

In progress.

39

Botanic Gardens—New Fern House

...

...

...

...

...

10,000

1,000

179

8

0

—

179

8

0

Contract about to be placed.

 

Abbotstown Farm:

 

 

 

 

 

 

 

 

 

 

 

 

40 (1)

Artifical Insemination Experimental Station

...

...

...

23,500

1,000

139

7

6

20,555

15

0

20,695

2

6

Completed.

40 (2)

Experimental Animals Farmyard

...

...

...

66,000

20,000

24,398

6

0

11,060

6

11

35,458

12

11

In progress.

40 (3)

Foundation Stock Farmyard

...

...

...

...

...

65,000

20,000

6,534

0

6

17,484

7

1

24,018

7

7

Stages II and III in progress.

40 (4)

Residence for Director

...

...

...

...

...

...

5,800

3,800

2,520

0

0

678

3

6

3,198

3

6

In progress.

40 (5)

Residence for Farm Manager

...

...

...

...

...

4,400

2,500

3,164

0

0

147

7

2

3,311

7

2

Virtually completed.

40 (6)

Veterinary Field Station

...

...

...

...

...

...

90,000

500

—

—

—

Contract placed.

 

Athenry Agricultural School:

 

 

 

 

 

 

 

 

 

 

 

 

41 (1)

Precaution Works

...

...

...

...

...

...

...

1,500

500

—

3

11

8

3

11

8

In planning.

41 (2)

Improvement of Water Supply

...

...

...

...

...

12,000

2,000

320

19

3

912

13

4

1,233

12

7

Pump installed.

41 (3)

New Building

...

...

...

...

...

...

...

...

110,000

45,000

34,271

5

0

19,287

11

9

53,558

16

9

In progress.

41 (4)

Provision of additional facilities at Turkey Hatchery

...

...

 

—

9,171

3

10

—

9,171

3

10

In progress.

 

Ballyhaise Agricultural School:

 

 

 

 

 

 

 

 

 

 

 

 

42 (1)

Employees’ Cottages

...

...

...

...

...

...

13,000

1,500

2,859

0

0

11,064

8

10

13,923

8

10

Completed.

42 (2)

Re-arrangement of Grinding Plant

...

...

...

...

2,100

500

—

433

12

6

433

12

6

Plant delivered.

 

Clonakilty Agricultural School:

 

 

 

 

 

 

 

 

 

 

 

 

43 (1)

Fire Precaution Works

...

...

...

...

...

...

2,250

500

—

633

9

11

633

9

11

In progress.

43 (2)

Improvement of Water Supply

...

...

...

...

...

12,250

8,000

753

12

11

552

8

0

1,306

0

11

In progress.

43 (3)

New Building

...

...

...

...

...

...

...

...

110,000

45,000

33,300

0

0

6,699

16

2

39,999

16

2

In progress.

 

Johnstown Castle:

 

 

 

 

 

 

 

 

 

 

 

 

44

Improvement of Water Supply

...

...

...

...

...

21,000

1,000

2,459

17

0

18,033

8

5

20,493

5

5

Completed.

 

Munster Institute:

 

 

 

 

 

 

 

 

 

 

 

 

45 (1)

Fire Precaution Works

...

...

...

...

...

...

2,500

1,500

27

10

11

209

0

3

236

11

2

Minor architectural works in progress.

45 (2)

Improved accommodation

...

...

...

...

...

...

20,000

3,000

1,960

0

0

15,291

3

2

17,251

3

2

Completed.

45 (3)

New Poultry Plant

...

...

...

...

...

...

...

98,500

200

—

17,093

2

7

17,093

2

7

Adaptations completed, further works in planning.

45 (4)

Reconstruction of Cattle Court and Calf Sheds

...

...

...

5,000

2,000

—

—

—

In planning.

46

Thorndale—Detention Station for Imported Livestock

...

...

12,000

3,000

280

0

0

—

280

0

0

Planning completed.

 

Total:

 

 

173,500

129,881

5

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

 

 

47

Valentia Observatory—Accommodation for Seismological Instruments

1,500

1,200

2,603

5

3

7

16

0

2,611

1

3

Completed.

 

Total:

 

 

1,200

2,603

5

3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

 

 

 

Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

48

New Central Sorting Office

...

...

...

...

...

...

600,000

175,000

84,954

12

8

1,490

2

4

86,444

15

0

In progress.

49

New District Sorting Office and Telephone Exchange Coolock,

 

 

 

 

 

 

 

 

 

 

 

 

 

Raheny

...

...

...

...

...

...

...

...

13,500

250

13

10

0

—

13

10

0

In planning.

50

New District Sorting Office and Telephone Exchange, Finglas

...

18,200

6,000

3,974

11

0

31

8

10

4,005

19

10

In progress.

51

G.P.O. Arcade—Conversion of Shop to Office Accommodation

6,000

3,500

5,449

3

0

—

5,449

3

0

Completed.

52

New Warehousing, etc., accommodation

...

...

...

190,000

2,000

—

—

—

In planning.

53

Arklow Post Office—Improvements and New Telephone Exchange

12,850

3,000

847

12

1

—

847

12

1

Tenders under consideration.

54

Ballinasloe—New Post Office and Telephone Exchange

...

...

24,500

7,500

512

13

3

—

512

13

3

In progress.

55

Carrick-on-Shannon Post Office—Improvements

...

...

...

19,000

8,000

7,479

13

8

10,176

6

1

17,655

19

9

Virtually completed.

56

Ennis Post Office—Improvements and New Telephone Exchange

...

9,600

6,400

3,638

11

2

2,050

3

9

5,688

14

11

In progress.

57

Killarney Post Office—Improvements

...

...

...

...

...

2,880

500

421

12

11

1,709

3

2

2,130

16

1

Completed.

 

Limerick:

 

 

 

 

 

 

 

 

 

 

 

 

58

New Engineering Stores and Garages

...

...

...

...

1,700

1,600

—

—

—

Planning completed.

59

Post Office Improvements

...

...

...

...

...

...

13,000

7,500

6,840

0

0

53

5

0

6,893

5

0

In progress.

60

Sligo Post Office—Improvements

...

...

...

...

...

6,000

4,000

1,620

0

0

3,611

5

4

5,231

5

4

Completed.

61

Waterford Post Office—Improvements

...

...

...

...

1,700

200

1,150

1

2

662

8

0

1,812

9

2

Completed.

 

Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

62

New Area Engineering Headquarters

...

...

...

...

1,500

1,500

1,710

0

0

375

0

0

2,085

0

0

Nearing completion.

63

Post Office—Improvements

...

...

...

...

...

...

6,000

1,200

1,709

4

4

3,500

19

3

5,210

3

7

Completed.

64

Wicklow—New Post Office and Telephone Exchange

...

...

29,800

13,700

15,778

0

0

3,252

15

6

19,030

15

6

In progress.

65

Youghal—New Post Office and Telephone Exchange

...

...

...

13,000

8,000

3,096

11

9

—

3,096

11

9

In progress.

 

Total:

 

 

249,850

139,195

17

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

 

66

School of Civil Defence—Improved Accommodation

...

...

23,500

14,000

3,803

1

3

414

18

6

4,217

19

9

In progress.

67

Dublin, Cathal Brugha Barracks—Dining Hall and Cookhouse

...

62,000

25,000

560

4

4

500

0

0

1,060

4

4

Planning completed.

68

Curragh Camp—New Catholic Church

...

...

...

...

...

124,000

5,000

—

118,529

17

7

118,529

17

7

Completed.

69

Arbour Hill Detention Prison—Memorial to 1916 Leaders

...

...

29,000

1,000

816

0

0

25,011

0

3

25,827

0

3

In progress.

 

Total:

 

 

45,000

5,179

5

7

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

 

 

70

Irish Embassy to the Federation of Nigeria—Residences for

 

 

 

 

 

 

 

 

 

 

 

 

 

Ambassador and Secretary

...

...

...

...

...

...

...

64,000

500

—

80

0

0

80

0

0

In planning.

 

Total:

 

 

500

—

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

 

 

71

Dublin—New Headquarters, Haddington Road

...

...

...

1,100,000

15,000

3,151

6

8

3

14

0

3,155

0

8

In planning.

72

Achill—New Employment Exchange

...

...

...

...

...

7,800

1,000

536

11

0

7,425

11

1

7,962

2

1

Completed.

73

Carrick-on-Shannon—New Employment Exchange

...

...

...

14,000

11,500

9,967

16

11

226

17

6

10,194

14

5

Virtually completed.

74

Mullingar—New Employment Exchange

...

...

...

...

20,500

14,000

12,099

14

6

313

7

11

12,413

2

5

In progress.

75

Tralee—New Employment Exchange

...

...

...

...

42,500

1,000

3,148

18

3

37,707

19

9

40,856

18

0

Completed.

 

Total:

 

 

42,500

28,904

7

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

 

 

 

Central Mental Hospital, Dundrum:

 

 

 

 

 

 

 

 

 

 

 

 

76 (1)

Fire Prevention and Control

...

...

...

...

...

5,500

1,400

837

6

2

4,131

7

6

4,968

13

8

Nearing completion.

76 (2)

New Residence for Governor

...

...

...

...

...

5,600

4,500

6,120

0

0

111

7

0

6,231

7

0

Completed.

 

Total:

 

 

5,900

6,957

6

2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

General:

 

 

 

 

 

 

 

 

 

 

 

 

77

Minor New Works not exceeding £2,000 each

...

...

...

...

20,000

20,000

31,989

7

1

—

—

Details appended.

78

Urgent and Unforeseen Works

...

...

...

...

...

...

5,000

5,000

38,040

14

0

—

—

Details appended.

79

Minor Balances of Expenditure (not provided for above) on works of

 

 

 

 

 

 

 

 

 

 

 

 

 

prior years which may not be completed on 1st April, 1962

...

15,000

15,000

16,394

0

1

—

—

Details appended.

 

Total:

 

 

3,518,600

2,947,154

16

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Deduct:

 

 

 

 

 

 

 

 

 

 

 

 

 

(1) for works which might not have been carried out during the year (£173,600) and (2) for adjustment for expenditure previously

 

 

 

 

 

 

 

 

 

 

 

 

 

borne on Vote 9 (£25,000)

...

...

...

...

...

...

 

198,600

 

 

 

 

 

 

 

 

 

 

 

Net Totals:

 

 

3,320,000

2,947,154

16

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF 77—MINOR NEW WORKS NOT EXCEEDING £2,000

Minor Work No.

Service and Description

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

Central Statistics Office:

 

 

 

 

 

 

 

 

 

 

82/1/ of 1961/62

Partitioning

...

...

...

...

...

...

...

...

...

...

...

...

29

17

4

180

12

2

210

9

6

Completed.

82/57 of 1961/62

Ladies’ Rest Room

...

...

...

...

...

...

...

...

...

...

...

 

5

2

194

9

1

194

14

3

Completed.

46

Heating Improvement

...

...

...

...

...

...

...

...

...

...

...

622

19

1

—

622

19

1

Completed.

78

Improvements

...

...

...

...

...

...

...

...

...

...

...

...

263

8

1

—

263

8

1

Completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

37

Headquarters—Improvements

...

...

...

...

...

...

...

...

...

...

181

2

2

—

181

2

2

Completed.

49

O.   M. Section—Adaptations, etc.

...

...

...

...

...

...

...

...

...

...

1,304

5

4

—

1,304

5

4

Completed.

90/52 of 1960/61

Finance Section—Electrical Installation

...

...

...

...

...

...

...

...

...

 

1

11

236

11

5

236

13

4

Completed.

 

Office of Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

100

Custom House, Dublin—Partitioning

...

...

...

...

...

...

...

...

...

139

19

8

—

139

19

8

Completed.

82/70 of 1961/62

Dublin Castle—Improved Ventilation

...

...

...

...

...

...

...

...

...

41

13

3

11

18

11

53

12

2

Completed.

82/98 of 1961/62

9-10 Upper O’ConnellStreet, Dublin—Adaptations

...

...

...

...

...

...

...

878

15

1

271

3

7

1,149

18

8

Completed.

52

51 Lr. Baggot Street, Dublin—Elecrrical Installation

...

...

...

...

...

...

...

621

9

4

—

621

9

4

Completed.

30

Clondergole Customs Huts—Electrical Installation

...

...

...

...

...

...

...

160

11

8

—

160

11

8

Completed.

82/19 of 1961/62

Donegal St. Johnstown Customs Hut—Sanitary Facilities, etc.

...

...

...

...

...

15

10

0

196

1

6

211

11

6

Completed.

70

Limerick Government Offices—Improvements etc.

...

...

...

...

...

...

...

242

8

3

—

242

8

3

In progress.

27

Moybridge Customs Station—Electrical Installation

...

...

...

...

...

...

...

116

9

11

—

116

9

11

Completed.

87

Tralee Customs House—Electrical Installation

...

...

...

...

...

...

...

...

280

8

6

—

280

8

6

Completed.

 

Valuation Office:

 

 

 

 

 

 

 

 

 

 

4

5-6 Ely Place—Improved Heating, etc.

...

...

...

...

...

...

...

...

...

561

6

2

—

561

6

2

Completed.

82/39 of 1961/62

5-6 Ely Place—Adaptations

...

...

...

...

...

...

...

...

...

...

501

9

7

31

17

0

533

6

7

Completed.

90/90 of 1960/61

Ordance Survey Office—Alterations

...

...

...

...

...

...

...

...

...

18

0

0

655

7

6

673

7

6

Completed.

82/58 of 1961/62

Ordance Survey Office—Sanitary Facilities

...

...

...

...

...

...

...

...

138

3

11

34

19

8

173

3

7

Completed.

96

Ordnance Survey Office—Electrical Installation

...

...

...

...

...

...

...

244

12

2

—

244

12

2

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

82/44 of 1961/62

51 St. Stephen’s Green, Dublin—Adaptations

...

...

...

...

...

...

...

...

21

0

10

685

4

7

706

5

5

Completed.

8

51 St. Stephen’s Green—Lunch Club Equipment

...

...

...

...

...

...

...

305

16

5

—

305

16

5

Completed.

80

Engineer’s Branch—Heating and Equipment

...

...

...

...

...

...

...

...

 

15

2

—

 

15

2

Deferred to 1963 64

77

District Office, Castlebar—Improved Heating

...

...

...

...

...

...

...

...

110

17

2

—

110

17

2

Completed.

113

District Office, Waterford—Adaptations

...

...

...

...

...

...

...

...

145

11

0

—

145

11

0

Completed.

95

Central Engineering Workshop—Partitioning

...

...

...

...

...

...

...

...

175

3

0

—

175

3

0

In progress.

 

Phoenix Park:

 

 

 

 

 

 

 

 

 

 

6

Extension at Chapelizod Gate-Lodge

...

...

...

...

...

...

...

...

...

931

16

11

—

931

16

11

Completed.

73

Improvement of Spa Lodge, East

...

...

...

...

...

...

...

...

...

...

552

7

9

—

552

7

9

Completed.

82/79 of 1961/62

Improvements at Ashview House

...

...

...

...

...

...

...

...

...

340

0

0

360

0

0

700

0

0

Completed.

105

Heating for Glasshouses

...

...

...

...

...

...

...

...

...

...

...

160

0

0

—

160

0

0

Completed.

18

Improvement of Knockmary Lodge

...

...

...

...

...

...

...

...

...

389

17

4

—

389

17

4

In progress.

68

Garinish Island—Improved Heating of House

...

...

...

...

...

...

...

...

269

14

6

—

269

14

6

Completed.

82/3/ of 1961/62

Garinish Island—Office, etc.

...

...

...

...

...

...

...

...

...

...

...

11

3

0

631

18

6

643

1

6

Completed.

75

Dunmore East Harbour—New Structure

...

...

...

...

...

...

...

...

...

771

4

7

—

771

4

7

Completed.

57

Royal Hospital, Kilmainham—Improvement of West Avenue Cottage

...

...

...

...

...

396

1

6

—

396

1

6

Completed.

67

Dun Laoghaire, Former Coast Guard Station—Improvement of Cottages

...

...

...

...

597

9

4

—

597

9

4

Completed.

 

Chief State Solicitor’s Office:

 

 

 

 

 

 

 

 

 

 

82/40 of 1961/62

Renovation of Rooms over Children’s Court

...

...

...

...

...

...

...

...

197

1

9

865

8

0

1,062

9

9

Completed.

103

Basement Storage Improvements

...

...

...

...

...

...

...

...

...

98

3

9

—

98

3

9

In progress.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

106

Public Record Office—Provision of Book Lift

...

...

...

...

...

...

...

...

31

12

3

—

31

12

3

In progress.

39

Garda Depot—Storage

...

...

...

...

...

...

...

...

...

...

...

285

19

6

—

285

19

6

Completed.

82/60 of 1961/62

Police Huts

...

...

...

...

...

...

...

...

...

...

...

...

...

17

11

0

249

10

0

267

1

0

Completed.

82/103 of 1961/62

Land Registry—Adaptations

...

...

...

...

...

...

...

...

...

...

...

755

14

7

56

12

7

812

7

2

Completed.

72

Registry of Deeds—Improved Heating

...

...

...

...

...

...

...

...

...

441

16

4

—

441

16

4

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

76

Headquarters—Alterations

...

...

...

...

...

...

...

...

...

...

...

137

15

7

—

137

15

7

Completed.

122

Headquarters—Improvements (Room 18)

...

...

...

...

...

...

...

...

...

45

9

4

—

45

9

4

In progress.

 

Technical Instruction Branch:

 

 

 

 

 

 

 

 

 

 

32/34 of 1961/62

Adaptations

...

...

...

...

...

...

...

...

...

...

...

...

...

60

3

2

156

7

2

216

10

4

Completed.

43

Improvements

...

...

...

...

...

...

...

...

...

...

...

...

406

9

9

—

406

9

9

Completed.

58

Improved Storage

...

...

...

...

...

...

...

...

...

...

...

...

172

19

0

—

172

19

0

In progress.

82/74 of 1961/62

National Museum—Improved Lighting

...

...

...

...

...

...

...

...

...

17

11

0

107

10

4

125

1

4

Completed.

115

National Museum—Improved Lighting (Central Court)

...

...

...

...

...

...

...

11

4

3

—

11

4

3

In progress.

82/87 of 1961/62

National Gallery—Fire Precaution Work, etc.

...

...

...

...

...

...

...

...

336

14

2

54

9

4

391

3

6

Completed.

90

National College of Art—Adaptation, etc. (Room 9)

...

...

...

...

...

...

...

479

15

0

—

479

15

0

In progress.

104

Model School, St. Joseph’s—Partitioning, etc.

...

...

...

...

...

...

...

...

452

8

4

—

452

8

4

In progress.

69

Model School, Sligo—Electrical Installation

...

...

...

...

...

...

...

...

242

8

4

—

242

8

4

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

56

Land Commission—Sanitary Facilities

...

...

...

...

...

...

...

...

...

262

14

3

—

262

14

3

Completed.

3

Land Commission—Incinerators

...

...

...

...

...

...

...

...

...

...

148

10

0

—

148

10

0

Completed.

94

Forestry Branch, Headquarters—Shelving

...

...

...

...

...

...

...

...

...

73

15

6

—

73

15

6

In progress.

82/26 of 1961/62

Forestry Branch, Kilkenny—Partitioning, etc.

...

...

...

...

...

...

...

...

299

12

0

21

9

6

321

1

6

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

85

Government Buildings (South Block)—Shelving

...

...

...

...

...

...

...

...

105

6

4

—

105

6

4

Completed.

 

Botanic Gardens:

 

 

 

 

 

 

 

 

 

 

82/83 of 1961/62

Garage

...

...

...

...

...

...

...

...

...

...

...

...

...

3

6

7

170

6

11

173

13

6

Completed.

53

Oil Storage

...

...

...

...

...

...

...

...

...

...

...

...

...

178

0

5

—

178

0

5

Completed.

63

Improved Water Supply

...

...

...

...

...

...

...

...

...

...

...

10

0

3

—

10

0

3

In progress.

82/59 of 1961/62

Abbotstown Farm—Fire Precautions

...

...

...

...

...

...

...

...

...

341

4

5

191

3

5

532

7

10

Completed.

84

Thorndale Veterinary Laboratory—Fencing, etc.

...

...

...

...

...

...

...

...

540

13

9

—

540

13

9

Completed.

82/47 of 1961/62

Munster Institute, Pig Progeny Testing Station—Partitioning

...

...

...

...

...

...

12

17

11

312

18

5

325

16

4

Completed.

 

Bovine Tuberculosis Eradication Scheme Offices:

 

 

 

 

 

 

 

 

 

 

55

Cork—Improvements

...

...

...

...

...

...

...

...

...

...

...

573

1

7

—

573

1

7

Completed.

19

Ennis—Improvements

...

...

...

...

...

...

...

...

...

...

...

252

2

4

—

252

2

4

Completed.

82/56 of 1961/62

Galway—Improved Heating, etc.

...

...

...

...

...

...

...

...

...

146

7

2

405

0

0

551

7

2

Completed.

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

101

Kildare Street—Partitioning

...

...

...

...

...

...

...

...

...

...

...

107

16

10

—

107

16

10

In progress.

 

Meteorological Office:

 

 

 

 

 

 

 

 

 

 

90/55 of 1960/61

Adaptations

...

...

...

...

...

...

...

...

...

...

...

...

...

30

18

6

1,607

4

6

1,638

3

0

Completed.

1

Formation of Laboratory

...

...

...

...

...

...

...

...

...

...

...

938

3

9

—

938

3

9

Completed.

33

Fire Precautions

...

...

...

...

...

...

...

...

...

...

...

...

671

14

6

—

671

14

6

Completed.

24

Mullingar—Electrical Installation

...

...

...

...

...

...

...

...

...

...

223

0

0

—

223

0

0

Completed.

7

Mercantile Marine Office—Improvement of Heating

...

...

...

...

...

...

...

373

1

4

—

373

1

4

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

82/80 of 1961/62

Headquarters (Kildare Street)—Partitioning

...

...

...

...

...

...

...

...

62

7

0

155

2

5

217

9

5

Completed.

60

Patents Office—Improvements

...

...

...

...

...

...

...

...

...

...

14

2

0

—

14

2

0

In progress.

82/97 of 1961/62

Industrial Development Authority—Renovations

...

...

...

...

...

...

...

545

2

7

17

5

0

562

7

7

Completed.

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

35

Central Telegraph Office—Conversion of Telex

...

...

...

...

...

...

...

...

982

10

0

—

982

10

0

Completed.

71

Central Telegraph Office—Adaptations

...

...

...

...

...

...

...

...

...

230

6

10

—

230

6

10

Completed.

83

Telephone Exchange, Crown Alley—Improvements

...

...

...

...

...

...

...

287

11

5

—

287

11

5

Completed.

50

Dublin Post Office Factory—Installation of Petrol Pump

...

...

...

...

...

...

...

142

0

0

—

142

0

0

Completed.

32

Athy Post Office—Partitioning

...

...

...

...

...

...

...

...

...

...

139

15

4

—

139

15

4

Completed.

82/92 of 1961/62

Cork Sorting Office—Partitioning, etc.

...

...

...

...

...

...

...

...

...

382

9

7

182

16

1

565

5

8

Completed.

40

Cork Sorting Office—Improvements

...

...

...

...

...

...

...

...

...

...

152

9

9

—

152

9

9

Completed.

45

Kinsale Post Office—Adaptations

...

...

...

...

...

...

...

...

...

...

157

10

0

—

157

10

0

Completed.

9

Longford Post Office—Improvements

...

...

...

...

...

...

...

...

...

822

7

3

—

822

7

3

Completed.

17

Tipperary Post Office—Fire Precautions

...

...

...

...

...

...

...

...

...

50

0

0

—

50

0

0

In progress.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

General Headquarters:

 

 

 

 

 

 

 

 

 

 

82/9 of 1961/62

Ladies’ Cloakroom

...

...

...

...

...

...

...

...

...

...

28

16

0

218

19

2

247

15

2

Completed.

82/68 of 1961/62

Arrangement of accommodation

...

...

...

...

...

...

...

...

...

...

145

14

9

280

13

7

426

8

4

Completed.

21

Improvement of Heating

...

...

...

...

...

...

...

...

...

...

...

528

10

0

—

528

10

0

Completed.

28

Adaptations (Strongroom)

...

...

...

...

...

...

...

...

...

...

...

224

7

8

—

224

7

8

Completed.

59

Government Buildings (Main Guard Room)—Erection of Partitions

...

...

...

...

...

258

16

11

—

258

16

11

Completed.

82/66 of 1961/62

Civil Defence Store, Newbridge—Surfacing Approaches

...

...

...

...

...

...

...

147

4

2

59

0

0

206

4

2

In progress.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

 

Headquarters:

 

 

 

 

 

 

 

 

 

 

82/95 of 1961/62

Shelving

...

...

...

...

...

...

...

...

...

...

...

...

...

48

3

7

53

8

7

101

12

2

Completed.

91

Improvement of Lighting

...

...

...

...

...

...

...

...

...

...

...

8

11

8

—

8

11

8

In progress.

 

Embassies Abroad:

 

 

 

 

 

 

 

 

 

 

62

Bonn—Improvement of Heating

...

...

...

...

...

...

...

...

...

489

17

5

—

489

17

5

Completed.

82/102 of 1961/62

Brussels—Partitioning

...

...

...

...

...

...

...

...

...

...

...

581

6

9

387

16

0

969

2

9

Completed.

51

Canberra—Partitioning

...

...

...

...

...

...

...

...

...

...

...

798

15

1

—

798

15

1

Completed.

2

Lagos—Partitioning

...

...

...

...

...

...

...

...

...

...

...

1,952

7

1

—

1,952

7

1

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

29

Áras Mhic Dhiarmada—Equipment for Lunch Club

...

...

...

...

...

...

...

158

13

6

—

158

13

6

Completed.

 

Employment Exchanges:

 

 

 

 

 

 

 

 

 

 

90/70 of 1960/61

Beresford Place (Northumberland House)—Improved electric lighting

...

...

...

...

98

13

7

170

7

5

269

1

0

Completed.

81

Gardiner Street—Partitioning, etc.

...

...

...

...

...

...

...

...

...

122

13

10

—

122

13

10

Completed.

36

Gardiner Street—Shelving, etc.

...

...

...

...

...

...

...

...

...

...

959

15

0

—

959

15

0

Completed.

114

Dundalk—Improved lighting

...

...

...

...

...

...

...

...

...

...

245

19

10

—

245

19

10

Completed.

41

Limerick—Improved lighting

...

...

...

...

...

...

...

...

...

...

80

9

5

—

80

9

5

Part Completed.

20

Mallow Social Welfare Office—Improved Heating

...

...

...

...

...

...

...

116

19

6

—

116

19

6

Completed.

 

Total:

 

...

£31,989

7

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF No. 78—URGENT AND UNFORESEEN WORKS.

Work No.

Service and Description

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Oireachtas:

 

 

 

 

 

 

 

 

 

 

7

Dáil Chamber—Improved acoustics

...

...

...

...

...

...

...

...

...

1,555

9

2

—

1,555

9

2

Stage I completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Office of the Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

6

21 Parliament Street, Dublin—Adaptation for Claims Branch

...

...

...

...

...

2,889

17

10

—

2,889

17

10

In progress.

13

9-10 Upper O’ConnellStreet, Dublin—Installation of computer

...

...

...

...

...

5,293

12

7

—

5,293

12

7

In progress.

10

55-56 Upper O’ConnellStreet, Dublin—Adaptations, etc.

...

...

...

...

...

...

3,139

0

11

—

3,139

0

11

In progress.

12

19-22 Dame Street, Dublin—Adaptations, etc.

...

...

...

...

...

...

...

...

1,163

10

0

—

1,163

10

0

Virtually completed.

 

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

1

121 Lower Baggot Street, Dublin—Adaptations, etc., for Road Traffic Section

...

...

...

4,709

14

6

—

4,709

14

6

In progress.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

8

9-10 Burlington Road, Dublin—Adaptations, etc. for Institute for Advanced Studies

...

...

...

5,601

16

1

—

5,601

16

1

In progress.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

9

69 Fitzwilliam Square, Dublin—Adaptations, etc.

...

...

...

...

...

...

...

...

800

10

0

—

800

10

0

In progress.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

3

1, 7   8 Mount Street Crescent—Adaptations etc. for An Foras Tionscail and the Industrial

 

 

 

 

 

 

 

 

 

 

 

Development Authority

...

...

...

...

...

...

...

...

...

...

...

...

6,033

6

2

—

6,033

6

2

In progress.

4

21 Fitzwilliam Square, Dublin—Adaptations etc. for An Cheard Chomhairle

...

...

...

5,301

6

8

—

5,301

6

8

In progress.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

11

Stockholm Legation—Adaptations, etc.

...

...

...

...

...

...

...

...

...

1,552

10

1

—

1,552

10

1

In progress.

 

Total:

...

38,040

14

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DETAILS OF B.79—MINOR BALANCES OF EXPENDITURE.

Work No.

Service and Description

Expenditure

Observamions

1962-63

To 31-3-62

To 31-3-63

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Oireachtas:

 

 

 

 

 

 

 

 

 

 

3 of 1960/61

Leinster House—Reconstruction of loggias

...

...

...

...

...

...

...

...

...

1,772

2

1

14,112

17

11

15,885

0

0

Completed.

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

 

Central Statistics Office:

 

 

 

 

 

 

 

 

 

 

4 of 1961/62

Accommodation for Census of Population Staff

...

...

...

...

...

...

...

2,166

5

9

23,953

17

9

26,120

3

6

In progress.

91/3 of 1960/61

Transfer of dining club, etc.

...

...

...

...

...

...

...

...

...

...

29

6

6

3,721

17

6

3,751

4

0

In progress.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

9 of 1961/62

Economic Research Institute (73 Lr. Baggot Street, Dublin)—Adaptations

...

...

...

...

1,827

9

2

6,226

5

7

8,053

14

9

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

9a of 1961/62

Adaptations at 8-9 Merrion Row, Dublin

...

...

...

...

...

...

...

...

2

0

1

2,023

5

6

2,025

5

7

In progress.

9b of 1961/62

Adaptations at 50-51 St. Stephen’s Green, Dublin

...

...

...

...

...

...

...

68

19

2

2,271

10

7

2,340

9

9

In progress.

11a of 1961/62

Cork Government Offices—Adaptations

...

...

...

...

...

...

...

...

185

0

0

969

18

0

1,154

18

0

In progress.

12a of 1961/62

Cloghore Customs Frontier Post—Improvements

...

...

...

...

...

...

...

205

8

5

1,092

8

4

1,297

116

9

In progress.

 

Ordnance Survey Office:

 

 

 

 

 

 

 

 

 

 

11 of 1960/61

Fundamental Bench Marks

...

...

...

...

...

...

...

...

...

208

11

4

3,251

17

2

3,460

8

6

In progress.

17 of 1961/62

Improvement of storage equipment

...

...

...

...

...

...

...

...

...

525

0

0

634

12

11

1,159

12

11

In progress.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

96/3 of 1957/58

Kilkenny Forestry Office—Adaptations

...

...

...

...

...

...

...

...

...

135

4

6

490

11

7

625

16

1

Completed.

34 of 1961/62

Shelton Abbey Forestry School—Accommodation for additional trainees

...

...

...

...

192

4

6

3,693

19

1

3,886

3

7

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

48 of 1961/62

Cork: Egg and Poultry Inspection—Accommodation

...

...

...

...

...

...

...

623

2

11

2,074

2

6

2,697

5

5

In progress.

49 of 1961/62

Waterford Bovine Tuberculosis and Portal Inspection Offices—Adaptations

...

...

...

...

558

5

9

4,637

4

0

5,195

9

9

Completed.

 

Department of Transport and Power:

 

 

 

 

 

 

 

 

 

 

50 of 1961/62

Valentia Observatory—Alterations and additions

...

...

...

...

...

...

...

...

2,531

16

7

63,210

15

5

65,742

12

0

Completed.

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

57a of 1960/61

General Post Office, Dublin—Partitions in Post Office Savings Bank

...

...

...

...

...

198

0

0

1,786

19

0

1,984

19

0

Completed.

35 of 1961/62

Bandon—New Telephone Exchange, Engineers Stores and Garages

...

...

...

...

...

395

12

10

1,030

4

10

1,425

17

8

In progress.

58 of 1960/61

Churchtown, Dublin—New District Sorting Office

...

...

...

...

...

...

...

54

13

6

17,309

6

9

17,364

0

3

Completed.

57 of 1961/62

Droichead Nua—New Post Office and Telephone Exchange

...

...

...

...

...

...

167

0

4

15,682

6

3

15,849

6

7

In progress.

59 of 1961/62

Galway—New Post Office and Telephone Exchange

...

...

...

...

...

...

...

358

17

8

55,542

14

0

55,901

11

8

In progress.

60 of 1961/62

Gorey Post Office—Improvements

...

...

...

...

...

...

...

...

...

...

217

11

10

2,573

0

2

2,790

12

0

In progress.

70 of 1961/62

Letterkenny—New Post Office and Telephone Exchange

...

...

...

...

...

...

...

30

1

4

31,310

8

10

31,340

10

2

Completed.

64 of 1961/62

Mallow Post Office—Improvements

...

...

...

...

...

...

...

...

...

...

810

11

5

1,654

4

7

2,464

16

0

In progress.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

73 of 1961/62

Curragh Camp, Plunkett Barracks—Dining Hall and Cookhouse

...

...

...

...

...

1,891

5

4

69,449

2

2

71,340

7

6

Completed.

74 of 1961/62

Haulbowline—New water main

...

...

...

...

...

...

...

...

...

...

1,210

15

6

9,383

4

5

10,593

19

11

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

88 of 1960/61

Central Mental Hospital—New water main

...

...

...

...

...

...

...

...

12

16

1

5,125

11

1

5,138

7

2

Completed.

88a of 1960/61

Customs House, Dublin—Demolition of annexe

...

...

...

...

...

...

...

...

15

17

6

3,409

3

3

3,425

0

9

Completed.

 

Total:

...

16,394

0

1