Committee Reports::Report - Appropriation Accounts 1952 - 1953::30 March, 1955::Appendix

APPENDIX XII.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1952-53 (VOTE 9, SUBHEAD B.)

Work No.

Service and Description

Total Estimate

Vote 1952-53

Expenditure

Observations

1952-53

to 31/3/52

to 31/3/53

 

 

£

£

£

s.

d.

£

s.

d.

£

s.

d.

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

 

 

1

Áras an Uachtaráin—Improvements and furnishing

...

108,000

28,000

528

10

8

55,295

5

2

55,823

15

10

In Progress.

 

 

 

£28,000

£528

10

8

 

 

 

 

 

 

 

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

 

 

2

Electric Indicator System

...

...

...

...

3,000

3,000

—

—

—

Deferred.

3

Restaurant—Alteration and Improvement

...

...

1,500

1,500

£2,443

13

4

—

£2,443

13

4

In Progress.

 

 

 

£4,500

£2,443

13

4

—

—

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

 

4

2/3 Merrion Square—Central Heating

...

...

...

1,740

1,500

461

7

6

258

6

7

719

14

1

In Progress.

5

Ballyshannon Customs and Excise—Office accommodation

 

 

 

 

 

 

 

 

 

 

 

 

 

and Official Garage

...

...

...

...

...

2,500

2,500

—

—

—

Deferred.

6

Sligo Custom House—Thermal Storage Heating

...

600

600

—

—

—

In Progress.

7

Waterford Government Offices—Erection*

...

...

183,160

5,400

3,050

6

9

14,766

10

10

17,816

17

7

Project partly completed.

8

Office of Public Works—New Central Engineering

 

 

 

 

 

 

 

 

 

 

 

 

 

Workshop and Stores

...

...

...

...

...

30,500

3,500

861

1

3

1,784

13

6

2,645

14

9

In Progress.

9

Stationery Office—Storage

...

...

...

...

65,800

300

—

—

—

Deferred.

10

Valuation Office—Thermal Storage and Electric Water

 

 

 

 

 

 

 

 

 

 

 

 

 

Heaters

...

...

...

...

...

...

4,825

4,580

—

—

—

Postponed pending completion of legal formalities.

11

Ordnance Survey Office—Improved Ablution Facilities

950

950

461

7

6

—

461

7

6

Completed.

12

Ordnance Survey Office—Married Quarters—

 

 

 

 

 

 

 

 

 

 

 

 

 

Improvements

...

...

...

...

...

...

5,250

750

—

—

—

Deferred.

 

Parks:

 

 

 

 

 

 

 

 

 

 

 

 

13

Phoenix Park—Shelters for Relief Gatekeepers

...

2,100

175

994

7

10

1,430

19

9

2,425

7

7

Main work completed.

14

Rotunda Gardens—Garden of Remembrance

...

...

30,000

1,000

—

600

1

8

600

1

8

Postponed.

 

Harbours:

 

 

 

 

 

 

 

 

 

 

 

 

15

Buncrana Harbour—Improvements

...

...

...

1,050

750

175

0

0

300

0

0

475

0

0

In progress.

16

Dun Laoghaire Harbour—Additional Customs

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

35,000

20,000

28,153

12

1

7,955

5

1

36,108

17

2

Main work completed.

17

Dun Laoghaire Harbour—Public Lighting

...

...

2,300

1,000

—

—

—

Not commenced in 1952-53.

 

 

 

£43,005

£34,157

2

11

 

 

 

 

 

 

 

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

 

 

18

Botanic Gardens—Additional Glasshouse

...

...

7,000

3,000

4,035

13

2

4,003

1

10

8,038

15

0

Completed.

19

Botanic Gardens—New Fern House

...

...

...

Not yet made

500

—

—

—

Postponed.

20

Botanic Gardens—Improvement of Water Supply

...

 

1,000

—

395

3

11

395

3

11

Preliminary work completed; planning of main work in progress.

21

Athenry Agricultural School—Hard surfacing to Yards

 

 

 

 

 

 

 

 

 

 

 

 

 

and Avenues

...

...

...

...

...

...

2,800

2,800

1,268

16

3

—

1,268

16

3

In progress.

21A

Athenry Agricultural School—Reconstruction of “Laings

 

 

 

 

 

 

 

 

 

 

 

 

 

House”

...

...

...

...

...

...

—

—

480

0

0

—

480

0

0

Completed.

22

Athenry Agricultural School—New Grain, etc., Stores

...

4,500

4,250

 

4

8

—

 

4

8

Preliminary work.

23

Athenry Agricultural School—New Machinery Store

...

2,500

2,000

—

—

—

Tenders invited.

24

Athenry Agricultural School—Provision of Electric Power

1,750

500

1,075

0

0

387

9

9

1,462

9

9

In progress.

25

Ballyhaise Agricultural School—E.S.B. Supply

...

...

4,100

600

1,769

0

9

2,995

0

8

4,764

1

5

Completed.

25A

Ballyhaise Agricultural School—Artificial Insemination

 

 

 

 

 

 

 

 

 

 

 

 

 

Centre

...

...

...

...

...

...

—

—

23

0

0

—

23

0

0

In progress.

26

Clonakilty Agricultural School—New Buildings

...

75,000

500

439

6

4

286

11

9

725

18

1

Preliminary work completed. Main work not commenced in

26A

Clonakilty Agricultural School—Expenditure on

 

 

 

 

 

 

 

 

 

 

 

1952-53.

 

Insemination Centre

...

...

...

...

...

—

—

307

1

7

142

11

9

449

13

4

Completed.

27

Grange Stud and Dairy Farm—Adaptations

...

...

59,000

13,200

9,710

3

11

10,605

5

1

20,315

9

0

In progress.

28

Johnstown Castle—Adaptations and Renovations

...

142,000

15,400

17,886

3

8

106,176

9

8

124,062

13

4

Main adaptation works completed.

29

Munster Institute—Improved Accommodation

...

...

72,000

1,450

468

6

0

236

2

11

704

8

11

In progress.

30

Veterinary College—Improvements

...

...

...

127,000

10,000

200

1

6

76,831

6

5

77,031

7

11

Commencement of final section of work postponed pending settlement of legal dispute.

30A

Abbotstown Farm—Various overhaul and repair Works

..

—

—

634

9

3

—

634

9

3

In progress.

31

Fishery, etc. Harbours—Works of Economic Development

6,500

6,500

 

 

 

 

 

 

 

 

 

 

 

Ballymacw

...

...

...

...

—

—

9

7

0

—

—

In progress.

 

Bloodyforeland

...

...

...

—

—

77

8

8

—

—

Completed.

 

Carne

...

...

...

...

...

—

—

619

1

0

—

—

Completed.

 

Dingle

...

...

...

...

...

—

—

22

13

1

—

—

In progress.

 

Dooneen

...

...

...

...

—

—

1,869

12

1

—

—

Completed.

 

Greencastle

...

...

...

...

—

—

6,750

11

9

5,228

8

6

11,979

0

3

In progress.

 

Portaleen

...

...

...

...

—

—

89

16

7

—

—

In progress.

 

Sherkin Island

...

...

...

—

—

1,340

9

11

—

—

Completed.

 

Whiddy Island

...

...

...

—

—

566

11

2

—

—

Completed.

 

Tory Island

...

...

...

...

—

—

6

16

10

—

—

—

 

Malinmore

...

...

...

...

—

—

1

2

6

—

—

—

 

 

 

 

£11,353

10

7

 

 

 

 

 

 

 

 

 

 

£61,700

£49,650

17

8

 

 

 

 

 

 

 

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

 

 

32

Courts of Justice, Law Library—Improvement of

 

 

 

 

 

 

 

 

 

 

 

 

 

Ventilation

...

...

...

...

...

...

...

...

2,000

2,000

292

15

9

—

292

15

9

In progress.

32A

Government Buildings, North Block—Additional

 

 

 

 

 

 

 

 

 

 

 

 

 

Shelving

...

...

...

...

...

...

...

—

—

544

4

6

—

544

4

6

Completed.

32B

Land Registry—Improved Accommodation

...

...

—

—

1,508

2

10

—

1,508

2

10

In progress.

33

Garda Depot—Additional Accommodation

...

...

Not yet made

500

2,836

2

10

4,955

13

0

7,791

15

10

In progress.

34

Garda Depot—Additional Garage and Workshop

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

42,000

800

—

—

—

Postponed.

35

Garda Depot—Additional Storage

...

...

...

1,200

1,200

—

—

—

Planning virtually completed.

36

Garda Depot—Extension of Hospital

...

...

...

4,300

220

1,379

3

8

3,320

14

8

4,699

18

4

Completed.

37

Garda Depot—New Electrical Distribution System

...

1,250

1,250

—

53

12

0

53

12

0

In progress.

38

Garda Síochána Barracks (to be specified)—New Works,

 

 

 

 

 

 

 

 

 

 

 

 

 

Alterations and Additions

...

...

...

...

87,000

87,000

15,989

11

11

—

—

See details at back.

39

New Works, Alterations and Additions at other Garda

 

 

 

 

 

 

 

 

 

 

 

 

 

Síochána Barracks

...

...

...

...

...

5,000

5,000

60

19

7

—

—

See details at back.

40

Minor New Works at Garda Síochána Barracks

...

...

4,000

4,000

2,379

12

4

—

—

See details at back.

 

 

 

£101,970

£24,990

13

5

 

 

 

 

 

 

 

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

 

41

Tyrone House—Improvement of Lighting

...

...

1,000

1,000

—

—

—

Postponed.

42

Talbot House—Central Heating

...

...

...

3,500

3,300

—

—

—

In progress.

42A

National Education Office—Publications Branch

—

—

631

13

5

—

631

13

5

In progress.

43

Central Model Schools—Central Heating and Electric

 

 

 

 

 

 

 

 

 

 

 

 

 

Lighting

...

...

...

...

...

...

...

4,650

4,650

—

—

—

Postponed.

44

Central Model Schools—Erection of Italian Presentation

 

 

 

 

 

 

 

 

 

 

 

 

 

Statuary

...

...

...

...

...

...

...

1,300

1,300

—

—

—

Completed but not paid for.

45

Dunmanway Model School—Improvements

...

...

1,950

1,950

—

—

—

Commencement of work delayed pending settlement of way-leaves, etc.

46

National Schools—Grants for Building, Enlarging,

 

 

 

 

 

 

 

 

 

 

 

 

 

Enclosing, etc.

...

...

...

...

...

...

600,000

600,000

684,355

19

3

—

684,355

19

3

 

 

Preparatory Colleges:

 

 

 

 

 

 

 

 

 

 

 

 

47

Coláiste Móibhí—Adaptations

...

...

...

...

55,000

15,000

—

15,561

7

3

15,561

7

3

Next stage postponed.

 

Institutions of Science and Art:

 

 

 

 

 

 

 

 

 

 

 

 

48

National Library and National Museum—Renewal of

 

 

 

 

 

 

 

 

 

 

 

 

 

Defective Stonework

...

...

...

...

...

70,000

5,000

—

—

—

Postponed.

48A

National Library—Provision of Shelving

...

...

—

—

26

12

2

—

26

12

2

Tenders about to be invited.

49

National Museum—Internal Passage between Divisions

...

700

700

1,078

10

0

—

1,078

10

0

Virtually completed

 

Reformatory and Industrial Schools:

 

 

 

 

 

 

 

 

 

 

 

 

50

Reformatory School, Daingean—Adaptations

...

...

53,500

7,500

3,208

18

11

44,500

11

10

47,709

10

9

Four (of five) stages of work completed.

 

 

 

£640,400

£689,301

13

9

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

 

50A

Department of Lands—Luncheon Club Alterations

..

—

—

888

18

10

—

888

18

10

Completed.

 

Forestry Branch:

 

 

 

 

 

 

 

 

 

 

 

 

51

Forestry School, Shelton Abbey—Adaptations

37,000

10,000

536

4

7

—

536

4

7

In progress.

 

Gaeltacht Services Branch:

 

 

 

 

 

 

 

 

 

 

 

 

52

Ardara Tweed Mart—Improvements

...

...

...

3,000

2,000

171

18

1

—

171

18

1

In progress.

53

Cliffoney Lace Centre—New Premises

...

...

...

5,500

1,500

—

—

—

Project abandoned.

54

Crolly Toy Factory—Improvement of Heating

...

950

500

414

8

0

443

5

2

857

13

2

In progress.

55

Crolly Toy Factory—Water Supply, Cycle Shed, etc.

2,000

1,800

—

—

—

Tenders under consideration.

56

Elly Bay Toy Factory—Water Supply and Improved

 

 

 

 

 

 

 

 

 

 

 

 

 

Sanitary Accommodation, etc.

...

...

...

1,200

1,200

1,048

12

9

12

13

5

1,061

6

2

In progress.

57

Glencolumbkille—New Tweed Mart

...

...

...

6,000

1,000

—

—

—

Planning completed. Finance sanction awaited.

 

 

 

 

6

3

6

192

2

0

 

 

 

Hostel and main extension

58

Kilcar—New Spinning Factory

...

...

...

...

57,400

1,700

3,430

19

5

52,916

14

2

56,545

19

1

works completed. Supplementary works in progress.

59

Roundstone Knitting Centre—Extension

...

...

1,300

1,300

12

8

11

—

12

8

11

Tenders under consideration.

60

Tourmakeady Knitting Centre—Adaptations

...

...

3,200

2,900

3,092

3

11

272

19

2

3,365

3

1

Main works completed. Subsidiary works in progress.

61

Tourmakeady Knitting Centre—Residence for Technical

 

 

 

 

 

 

 

 

 

 

 

 

 

Staff

...

...

...

...

...

...

...

800

800

506

15

9

9

4

9

516

0

6

Completed.

62

Central Depot and Rural Centres—Improved

 

 

 

 

 

 

 

 

 

 

 

 

 

Fire-Fighting Facilities

...

...

...

...

...

10,425

6,000

—

—

—

Postponed.

 

 

 

£30,700

£10,108

13

9

 

 

 

 

 

 

 

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

 

 

63

Additional Telegraphic Weather Reporting Stations

...

16,100

5,000

—

1,829

4

4

1,829

4

4

Planning for one station in progress; sites for four others being acquired.

64

Rosslare, New Meteorological Observing Station and

 

 

 

 

 

 

 

 

 

 

 

 

 

Training Centre

...

...

...

...

...

...

15,500

3,000

 

9

3

—

 

9

3

Preliminary work.

65

Valentia Observatory—Adaptations and Additions

...

56,000

8,000

440

2

0

4,356

3

1

4,796

5

1

Preliminary works completed.

 

 

 

£16,000

£440

11

3

 

 

 

 

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

 

 

66

Dublin, General Post Office—Additional cycle

 

 

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

...

...

...

2,000

2,000

11

4

0

—

11

4

0

In progress.

67

Dublin, College Green Post Office—Alterations

...

1,000

1,000

—

—

—

Project being revised.

68

Dublin, New Post Office, St. Andrew Street*

...

...

34,000

8,000

6,801

2

0

26,896

16

3

33,697

18

3

Main works completed.

69

Dublin, Engineering Branch, Distillery Road—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations*

...

...

...

...

...

...

...

2,350

300

554

18

7

2,067

4

5

2,622

3

0

Main work completed. Supplementary works in progress.

70

Dublin, Post Office Factory—Improved Office

 

 

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

...

...

640

640

—

—

—

Planning completed.

71

Dublin, Post Office Factory—Rebuilding†

...

...

52,000

25,000

17,310

15

11

32,121

13

11

49,432

9

10

Main works completed.

72

Dublin, Post Office Stores, Infirmary Road—Thermal

 

 

 

 

 

 

 

 

 

 

 

 

 

Storage Heating

...

...

...

...

...

3,500

3,500

866

7

6

—

866

7

6

In progress.

73

Dublin, Post Office Stores—Resurfacing Yard

...

...

560

560

500

11

0

11

4

0

511

15

0

Work virtually completed.

74

Ballina Post Office—Additional Accommodation*

...

10,400

5,000

—

—

—

Bill of Quantities awaited.

75

Ballyhaunis Post Office—Improvements

...

...

700

100

360

7

6

380

10

4

740

17

10

Completed.

76

Birr Post Office—Adaptations

...

...

...

...

1,350

1,320

893

4

0

29

15

11

922

19

11

Completed.

77

Cahir Post Office—Adaptations*

...

...

...

490

490

9

1

7

3

2

4

12

3

11

Negotiations with Contractor for revision of original scheme.

78

Clonmel Post Office—Extension‡

...

...

...

1,350

1,350

260

10

0

2

11

8

263

1

8

In progress.

79

Cork Head Post Office—Improvements

...

...

15,200

750

8,378

16

2

12,240

0

0

20,618

16

2

Completed.

80

Drogheda, New Post Office and Telephone Exchange*

...

39,000

17,000

9,426

19

10

616

13

0

10,043

12

10

In progress.

81

Enniscorthy Post Office—Improvements*

...

...

420

420

—

—

—

In progress.

82

Kilrush, New Post Office and Telephone Exchange*

...

14,400

4,000

240

0

0

—

240

0

0

Quantity Surveyor’s fees.

83

Limerick, New Telephone Exchange*

...

...

...

2,000

600

1

0

6

—

1

0

6

Tenders about to be invited.

84

Portlaoighise Post Office—Improvements

...

...

1,050

1,050

650

13

9

—

650

13

9

In progress.

85

Rathluirc, New Post Office and Telephone Exchange*

...

14,000

4,000

—

—

—

Planning, etc., completed.

86

Tralee Post Office—Extension

...

...

...

...

6,000

2,000

—

—

—

Bills of Quantities awaited.

87

Improved Sorting Equipment at Post Offices

...

...

11,500

3,800

554

16

2

7,208

14

9

7,763

10

11

In progress.

87A

Droichead Nua Post Office—Adaptation of Premises

...

—

—

618

1

1

—

618

1

1

Completed.

 

Wireless Broadcasting:

 

 

 

 

 

 

 

 

 

 

 

 

88

Dublin G.P.O.—Studio and Office Accommodation

...

18,000

6,500

2,332

9

7

13,995

0

5

16,327

10

0

Furnishing in progress.

89

Dublin, Phoenix Hall—Adaptations

...

...

...

5,000

500

39

7

3

4,533

0

3

4,572

7

6

First series of adaptations completed.

90

Cork, New Studios

...

...

...

...

...

16,000

500

—

—

—

Delayed by negotiations with Cork V.E.C. regarding associated School of Music.

 

 

 

£90,380

£49,810

6

5

 

 

 

 

 

 

 

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

 

91

Dublin, Coláiste Caoimhín—Improvement of heating

...

2,500

2,250

1,712

0

5

—

1,712

0

5

In progress.

92

Dublin, St. Bricin’s Hospital—Lift

...

...

...

1,750

200

1,259

9

0

1,220

8

6

2,479

17

6

Completed.

93

Dublin, Portobello Barracks—Laundry and Bathhouse

—

150

—

—

—

Project abandoned.

94

Baldonnel Camp—Hangar Gates

...

...

...

17,250

500

12

13

0

—

12

13

0

In progress.

95

Baldonnel—Hard Surface Runways

...

...

...

—

20,000

2,904

8

10

—

2,904

8

10

Preliminary work.

96

Curragh Camp—Catholic Church

...

...

...

...

125,000

1,000

—

—

—

Planning in progress.

97

Curragh—Connolly Barracks—Dining Hall and

 

 

 

 

 

 

 

 

 

 

 

 

 

Cookhouse

...

...

...

...

...

...

...

—

1,000

—

—

—

Planning in progress.

98

Curragh, Plunkett Barracks—Dining Hall and Cookhouse

—

1,000

—

—

—

Planning in progress.

99

Curragh, Extension of Magazines

...

...

...

98,000

8,000

24,215

14

2

78,678

7

8

102,894

1

10

Completed.

100

Curragh, Renewal of Electrical Installation

...

...

40,000

20,000

—

—

—

Planning in progress.

101

Haulbowline Dockyard—New Jetty

...

...

...

85,000

30,000

25,241

13

7

46,685

5

8

71,926

19

3

Virtually completed.

102

Kilworth Camp—Officers’ Mess

...

...

...

...

17,000

5,000

2,260

10

1

—

2,260

10

1

In progress.

 

 

 

£89,100

£57,606

9

1

 

 

 

 

 

 

 

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

 

 

103

Berne Legation—Adaptations and Furnishing

...

6,310

4,350

5,041

16

0

18

9

4

5,060

5

4

Furnishing in progress.

104

Bonn Legation—Adaptations and Furnishing

...

...

12,000

11,000

9,767

17

9

804

7

9

10,572

5

6

In progress.

105

Canberra Embassy—New Building

...

...

...

95,000

800

151

3

2

2,728

12

10

2,879

16

0

Furnishings, etc.

106

London Embassy—Adaptations

...

...

...

...

95,000

12,000

18,244

4

10

83,267

6

2

101,511

11

0

Completed.

 

 

 

£28,150

£33,205

1

9

 

 

 

 

 

 

 

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

 

 

107

Dublin, Victoria Street Employment Exchange—Thermal

 

 

 

 

 

 

 

 

 

 

 

 

 

Storage heating and improved lighting

...

...

850

850

617

11

10

—

617

11

10

Completed.

108

Waterford, New Employment Exchange

...

...

51,800

11,500

10,005

6

7

23,944

9

11

33,949

16

6

Completed.

 

 

 

£12,350

£10,622

18

5

 

 

 

 

 

 

 

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

 

 

109

Dublin, Head Office, Custom House—Improved Typing

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

1,280

600

1,078

0

9

70

18

6

1,148

19

3

Completed save for furnishing.

110

Dundrum Asylum—Alterations and Additions

...

...

18,440

14,070

12,171

11

1

898

8

0

13,069

19

1

In progress.

 

 

 

£14,670

£13,249

11

10

 

 

 

 

 

 

 

 

General:

 

 

 

 

 

 

 

 

 

 

 

 

111

Minor New Works not exceeding £400 each

...

...

10,000

10,000

11,507

12

7

—

—

See details at back.

112

Urgent and Unforeseen Works

...

...

...

...

30,000

30,000

11,693

12

3

—

—

See details at back.

113

Minor Balances of Expenditure on Works of Prior Years

...

15,000

15,000

26,099

1

1

—

—

See details at back.

 

 

 

£1,215,925

£1,025,416

10

2

 

 

 

 

 

 

 

 

Deduct for Works which may not be carried out during the

 

 

 

 

 

 

 

 

 

 

 

 

 

year

...

...

...

...

...

...

...

 

65,925

—

 

 

 

 

 

 

 

 

 

 

£1,150,000

£1,025,416

10

2

 

 

 

 

 

 

 

 


Work No.

Service and Description

Expenditure

Observations

1952-53

to 31/3/52

to 31/3/53

 

No. 38—GARDA SIOCHANA BARRACKS.

 

 

 

 

 

 

 

 

 

 

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Newmarket-on-Fergus, Co. Clare—New Barracks

...

...

11

16

1

—

11

16

1

Fresh tenders about to be invited.

 

Bundoran, Co. Donegal

...

...

...

...

...

...

5,912

14

10

—

5,912

14

10

In progress.

 

Harcourt Terrace, Dublin—Boundary wall and cycle shed

...

732

1

6

—

732

1

6

In progress.

 

Athenry, Co. Galway—New Barracks

...

...

...

...

 

4

8

3

19

7

4

4

3

Postponed.

 

Achill Sound, Co. Mayo

...

...

...

...

...

197

10

0

3,893

14

4

4,091

4

4

Completed.

 

Thurles, Co. Tipperary—New Barracks

...

...

...

 

5

11

—

 

5

11

Bills of Quantities awaited.

 

New Ross, Co. Wexford—New Barracks

...

...

...

9,134

18

11

8,199

11

10

17,334

10

9

Completed.

 

 

£15,989

11

11

 

 

 

 

 

 

 

 

No. 39—NEW WORKS ALTERATIONS AND ADDITIONS, AT OTHER GARDA SIOCHANA BARRACKS.

 

32 of 1950/51

Kilmainham, Dublin—Adaptations

...

...

...

...

21

9

6

413

18

11

435

8

5

Completed.

37 of 1951/52

Churchill, Co. Donegal—New Barracks

...

...

...

...

27

17

0

5,876

13

5

5,904

10

5

Completed.

 

Sligo Garda Barracks—Improvements

...

...

...

...

11

13

1

—

11

13

1

Tenders under examination

 

 

£60

19

7

 

 

 

 

 

 

 

No. 40—MINOR NEW WORKS AT GARDA SIOCHANA BARRACKS.

 

 

 

 

 

 

 

 

 

 

 

Dublin Metropolitan Area:

 

 

 

 

 

 

 

 

 

 

1

Terenure—Improvements

...

...

...

...

...

96

2

5

—

96

2

5

Completed.

2

Rathmines—Improvements

...

...

...

...

...

25

4

8

—

25

4

8

In progress.

3

Kill-o-Grange

...

...

...

...

...

...

...

58 59

12 15

11 0

—

118

7

11

Completed.

5(39/12 of 51/52)

Newmarket—Formation of Reserve Room

...

...

...

145

5

3

156

10

9

301

16

0

Completed.

6

Kilmainham—Alterations

...

...

...

...

...

183

16

5

—

183

16

5

Completed.

7

Dalkey—Electrical Installation

...

...

...

...

82

13

0

—

82

13

0

Completed.

14

Irishtown—Improvements

...

...

...

...

57

14

6

—

57

14

6

In progress.

17

Dublin Castle Detective Branch—Improvements

...

...

233

15

1

—

233

15

1

Nearing completion.

22

Bridewell—Improvements

...

...

...

...

...

147

16

8

—

147

16

8

Virtually completed.

Provincial Barracks:

 

 

 

 

 

 

 

 

 

 

39/2 of 1951/52

Arva, Co. Cavan—Provision of Baths, etc.

...

...

...

42

15

10

100

0

0

142

15

10

Completed.

39/14 of 1951/52

Stradone, Co. Cavan—Alterations

...

...

...

...

37

11

0

60

0

0

97

11

0

Completed.

19

Castledermot, Co. Kildare—Installation of Electricity

...

97

5

0

—

97

5

0

In progress.

4

Mullinavat, Co. Kilkenny—Electrical Installation

...

...

98

7

3

—

98

7

3

Completed.

15

Kinlough, Co. Leitrim—Sanitary works, etc.

...

...

235

0

0

—

235

0

0

In progress.

11

Pallasgreen, Co. Limerick—Electrical Installations

...

...

226

0

0

—

226

0

0

Completed.

39/6 of 1951/52

Patrickswell, Co. Limerick—New Sanitary Appliances, etc.

...

10

0

0

167

8

0

177

8

0

Completed.

23

Keel, Co. Mayo—Electrical Installation

...

...

...

172

16

8

—

172

16

8

Completed.

16

Tullamore, Co. Offaly—Improvement of Drainage system

...

181

9

6

—

181

9

6

Completed.

9

Ballymote, Co. Sligo—Concreting yard, etc.

...

...

156

0

0

—

156

0

0

Completed.

12

Barnderrig, Co. Wicklow—Sinking of well and erection of

 

 

 

 

 

 

 

 

 

 

 

pump

...

...

...

...

...

...

...

...

1

10

0

—

1

10

0

Tender under consideration.

29

Rochfortbridge, Co. Westmeath—Electrical Installation

...

30

1

2

—

30

1

2

Completed.

 

 

£2,379

12

4

 

 

 

 

 

 

 

 

No. 111—MINOR NEW WORKS.

 

 

 

 

 

 

 

 

 

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

52

Áras an Uachtaráin—Improvements at Butler’s House

...

218

2

2

—

218

2

2

Virtually complete.

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

45

Library—Improvement of lighting

...

...

...

...

2

2

5

—

2

2

5

Tender accepted.

48

Entrance—Provision of seats

...

...

...

...

...

30

15

0

—

30

15

0

In progress.

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

92/2 of 1951/52

Statistics Office, 3 Cathal Brugha Street, Dublin—

26

6

9

42

6

8

311

5

5

Completed.

5

Improvement of heating

...

...

...

...

...

...

242

12

0

 

 

 

 

 

 

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Civil Service Commission:

 

 

 

 

 

 

 

 

 

 

91/51 of 1951/52

45 Upper O’Connell Street, Dublin—Improvement of

 

 

 

 

 

 

 

 

 

 

 

heating

...

...

...

...

...

...

...

127

13

0

2

0

5

129

13

5

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

91/43 of 1951/52

Headquarters: Finance Solicitor’s Office—Sub-division of

 

 

 

 

 

 

 

 

 

 

 

room

...

...

...

...

...

...

...

56

8

0

147

11

11

203

19

11

Completed.

91/67 of 1951/52

Headquarters: Secretariat—Improved lighting

...

...

245

10

7

10

17

0

256

7

7

Completed.

32

Headquarters: Provision of plugs for Dictating Machines

66

14

0

—

66

14

0

In progress.

59

Headquarters: Sub-division of room

...

...

...

63

0

10

—

63

0

10

In progress.

91/61 of 1951/52

Dún Laoghaire, Harbour Master’s Office—Improvements

...

209

14

3

121

0

11

330

15

2

In progress.

 

Pay-Master General’s Office:

 

 

 

 

 

 

 

 

 

 

91/44 of 1951/52

3 Lr. Ormond Quay—Improvement of lighting

...

...

93

0

0

92

16

4

185

16

4

Completed.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

91/31 of 1951/52

Dublin Castle, Clock Tower Building—Improved Heating

...

106

0

0

13

9

5

119

9

5

Completed.

91/76 of 1951/52

Dublin Castle, Legislation Section—Provision of Stoves

...

285

10

7

68

8

8

353

19

3

Completed.

18

Dublin Castle, Companies Branch—Improvements

...

142

17

6

—

142

17

6

Completed.

28

Dublin Castle, Adjudication Branch—Erection of Partitions

113

2

2

—

113

2

2

Virtually complete.

38

Dublin Castle, Block 10—Provision of shelving

...

...

149

7

8

—

149

7

8

Completed.

50

Dublin Castle, Public Departments Branch—Extension of

 

 

 

 

 

 

 

 

 

 

 

H.W. System

...

...

...

...

...

...

125

10

0

—

125

10

0

Completed.

91/56 of 1951/52

Bridgend Frontier Post—Improvements

...

...

...

24

7

0

150

0

0

174

7

0

Completed.

20

Dundalk Taxes Office—Provision of shelving, etc.

...

...

214

10

0

—

214

10

0

Completed.

14

Estate Duty Office, 21 St. Stephen’s Green—Supply of

 

 

 

 

 

 

 

 

 

 

 

Filing Units

...

...

...

...

...

...

135

15

3

—

135

15

3

Completed.

51

Tralee Custom House—Provision of Thermal Storage

 

 

 

 

 

 

 

 

 

 

 

Heaters

...

...

...

...

...

...

...

143

12

0

—

143

12

0

Completed.

 

Valuation Office:

 

 

 

 

 

 

 

 

 

 

91/47 of 1951/52

Headquarters—Improvements to Drawing Office

...

...

404

6

7

8

2

8

412

9

3

Completed.

 

General:

 

 

 

 

 

 

 

 

 

 

26

State Apartments, Dublin Castle—Provision of Presidential

 

 

 

 

 

 

 

 

 

 

 

Arms, etc.

...

...

...

...

...

...

...

187

1

11

—

187

1

11

Completed.

65

State Apartments, Dublin Castle—Inauguration of the

 

 

 

 

 

 

 

 

 

 

 

third President

...

...

...

...

...

...

370

5

9

—

370

5

9

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

139/28 of 1950/51

Headquarters—Provision of Enquiry Office

...

...

...

6

5

0

385

10

8

391

15

8

Completed.

91/50 of 1951/52

Headquarters—Facilities for serving morning tea

...

...

71

10

0

137

15

11

209

5

11

Completed.

42

Athenry Agricultural College—Improvement of Entrance

...

207

0

0

—

207

0

0

Completed.

6

Ballyhaise Agricultural College—Improvements to Dairy

...

236

17

0

—

236

17

0

Completed.

23

Ballyhaise Agricultural College—Tarmacadam surfacing

...

173

7

0

—

173

7

0

Completed.

22

Botanic Gardens—Alterations to Hayshed

...

...

...

298

19

6

—

298

19

6

Completed.

12

Munster Institute—Improvements at Gardener’s Cottage

...

352

5

6

—

352

5

6

Completed.

9

Fisheries Branch—Provision of Shelving

...

...

...

102

14

0

—

102

14

0

Completed.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

24

Juvenile Court, Dublin Castle—Improvement of Heating

...

170

15

8

—

170

15

8

Completed.

55

District Courts—Adaptation of room for Court Clerk

...

161

8

4

—

161

8

4

Completed.

39/7 of 1951/52

Garda Depot—Alterations to heating in Sergeants’ Mess

...

74

1

10

60

6

4

134

8

2

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

21

National Library—Provision of Shelving

...

...

...

233

0

0

—

233

0

0

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

Land Commission:

 

 

 

 

 

 

 

 

 

 

11

7/8 Hume Street—Partitioning, Improvement of Lighting,

 

 

 

 

 

 

 

 

 

 

 

etc.

...

...

...

...

...

...

...

...

419

4

7

—

419

4

7

Completed.

25

Merrion Street—Provision of Additional Sanitary

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

210

7

10

—

210

7

10

Completed.

33

61 Merrion Square—Partitioning, etc., of store at rere

...

223

13

9

—

223

13

9

Completed.

43

61 Merrion Square—Alterations etc., to rooms on 1st and

 

 

 

 

 

 

 

 

 

 

 

3rd floors

...

...

...

...

...

...

...

209

16

5

—

209

16

5

In progress.

 

Gaeltacht Services Branch:

 

 

 

 

 

 

 

 

 

 

91/46 of 1951/52

Carraroe Knitting Centre—Adaptations, etc.

...

...

25

14

0

365

14

7

391

8

7

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

139/39 of 1950/51

Kildare Street—Sound-proofing “copy room” and erection

 

 

 

 

 

 

 

 

 

 

 

of porch

...

...

...

...

...

...

1

14

6

162

7

7

164

2

1

Completed.

91/32 of 1951/52

Kildare Street—Sound proofing four rooms

...

...

...

 

15

0

212

16

10

213

11

10

Completed.

91/65 of 1951/52

Kildare Street—Alterations in room No. 12

...

...

...

260

4

3

20

13

7

280

17

10

Completed.

40

Kildare Street—Improvement of heating of Registry

...

112

5

7

—

112

5

7

Completed.

58

Kildare Street—Provision of Shelving

...

...

...

4

11

10

—

4

11

10

In progress.

62

Gas, Weights and Measures Office—Dublin Castle—Electrical

 

 

 

 

 

 

 

 

 

 

 

Installation

...

...

...

...

...

...

...

356

4

5

—

356

4

5

Completed.

53

Industrial and Commercial Property Registration Office, 44

 

 

 

 

 

 

 

 

 

 

 

Merrion Square—Provision of Shelving

...

...

...

99

12

3

 

 

 

99

12

3

In progress.

139/42 of 1950/51

Mercantile Marine Office—Alterations

...

...

...

51

17

0

155

13

0

207

10

0

Completed.

 

Department of Posts and Telegraphs:*

 

 

 

 

 

 

 

 

 

 

91/41 of 1951/52

Aldboro House—Structural work in connection with heating

17

0

2

495

12

6

512

12

8

Completed.

13

Four Courts, Dublin—Provision of Storage Accommodation

238

0

3

—

238

0

3

Completed.

91/54 of 1951/52

St. Mary’s Abbey Stores—Adaptations, etc.

...

...

147

19

6

59

18

10

207

18

4

In progress.

30

Pearse Street Sorting Office—Provision of Cycle

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

...

...

...

...

...

201

2

2

—

201

2

2

Completed.

39

Pearse Street Sorting Office—Provision of Enclosure Porch

 

 

 

 

 

 

 

 

 

 

 

and Strong-room

...

...

...

...

...

...

192

3

4

—

192

3

4

In progress.

31

Clifden Post Office—Improvements

...

...

...

...

120

0

0

—

120

0

0

In progress.

10

Cork Sorting Office—Adaptation of room

...

...

...

105

18

3

—

105

18

3

Completed.

2

Galway Post Office—Adaptations

...

...

...

...

58

4

2

—

58

4

2

Completed.

8

Valentia Island Wireless Station—Provision of Fuel Storage

 

 

 

 

 

 

 

 

 

 

 

Accommodation, etc.

...

...

...

...

...

285

17

6

—

285

17

6

Completed.

91/78 of 1951/52

Post Office Savings Bank—Sound-proofing machine room

...

152

3

0

134

19

2

287

2

2

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

91/42 of 1951/52

Parkgate Street—Provision of Extract Fans

...

...

33

6

6

74

7

1

107

13

7

Completed.

36

Parkgate Street—Partitioning of room, etc.

...

...

...

183

5

4

—

183

5

4

Completed.

35

Marlboro’ Hall—Alterations at Luncheon Club

...

...

116

4

0

—

116

4

0

Completed.

47

Army Pensions Board—St. Bricin’s Hospital—Provision of

 

 

 

 

 

 

 

 

 

 

 

doors and curtains for pigeon holes

...

...

...

349

1

0

—

349

1

0

Completed.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

91/33 of 1951/52

Iveagh House—Improved Lighting in Library, etc.

...

29

19

5

119

7

3

149

6

8

Completed.

3

Iveagh House—Provision of additional kitchen equipment

164

15

6

—

164

15

6

Completed.

27

Iveagh House—Partitioning room

...

...

...

...

111

12

8

—

111

12

8

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

139/54 of 1950/51

Belmullet Employment Exchange—Provision of Shelving, etc.

3

1

2

9

14

3

12

15

5

In progress.

17

Cork Employment Exchange—Transfer of Staff

...

...

167

6

9

—

167

6

9

Completed.

56

Victoria Street, Dublin, Employment Exchange—

 

 

 

 

 

 

 

 

 

 

 

Improvements

...

...

...

...

...

...

...

...

97

6

5

—

97

6

5

In progress.

66

Ship Street Barracks—Alterations, etc., and Transfer of Staff

377

5

9

—

377

5

9

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

46

Dublin Custom House—Alterations to Annexe

...

184

16

8

—

184

16

8

Completed.

91/21 of 1951/52

Dundrum Asylum—Extension of Shed at Ball-Alley

...

89

0

0

295

18

8

384

18

8

Completed.

91/63 of 1951/52

Dundrum Asylum—New Washing Machine

...

...

...

233

7

5

27

13

10

261

1

3

Completed.

139/66 of 1950/51

Dundrum Asylum—Improvements to Sleeping Quarters

...

 

5

0

312

5

8

312

10

8

Completed.

 

 

£11,507

12

7

 

 

 

 

 

 

 

 

No. 112—URGENT AND UNFORESEEN WORKS.

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

12

Earlsfort Terrace Workshop—Adaptation of former stable

1,477

17

7

—

1,477

17

7

In progress.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

2

C. & E. Dublin Castle—Adaptations, etc.

...

...

572

6

7

—

572

6

7

In progress.

22

Accountant General’s Office—Structural and electrical work

184

7

2

—

184

7

2

In progress.

 

Stationery Office:

 

 

 

 

 

 

 

 

 

 

21

Beggars Bush Barracks—Provision of Canteen

...

...

49

13

1

—

49

13

1

In progress.

 

Valuation Office:

 

 

 

 

 

 

 

 

 

 

20

Ordnance Survey Office—Installation of Machines, etc.

...

192

19

2

—

192

19

2

In progress.

 

General:

 

 

 

 

 

 

 

 

 

 

1

Removal and re-erection of ceilings from Mespil House

...

2,743

6

8

—

2,743

6

8

Completed.

24

State Apartments—Provision of Catering Facilities

...

561

12

10

—

561

12

10

In progress.

25

An Tóstal—Floodlighting of Government Buildings

...

3

14

9

—

3

14

9

In progress.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

16

Ballyhaise Agricultural College—Electrical Installations, etc.

179

16

4

—

179

16

4

In progress.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

23

Adoption Board, 45 St. Stephen’s Green—Structural

 

 

 

 

 

 

 

 

 

 

 

Alterations, etc.

...

...

...

...

...

...

...

218

5

2

—

218

5

2

In progress.

 

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

15

Housing Section—Provision of Filing Cabinets, and structural

 

 

 

 

 

 

 

 

 

 

 

work, etc.

...

...

...

...

...

...

711

10

10

—

711

10

10

In progress.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

19

Kildare Street—Installation of Germicidal Apparatus

...

536

16

11

—

536

16

11

Completed.

6

Labour Court, Griffith Barracks—Installation of Storage

 

 

 

 

 

 

 

 

 

 

 

Heaters

...

...

...

...

...

...

...

1,119

16

7

—

1,119

16

7

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

8

Marlboro’ Hall—Improvement of lighting

...

...

...

1,135

9

5

—

1,135

 

 

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

11

Árus Brugha—Adaptations, etc.

...

...

...

...

465

1

8

—

465

1

8

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

10 (91/70 of 1951/2)

General Register Office—Improvements, etc.

...

...

767

11

11

44

16

0

812

7

11

Completed.

4

Dundrum Asylum—New Lavatories

...

...

...

...

773

5

7

—

773

5

7

Completed.

 

 

£11,693

12

3

 

 

 

 

 

 

 

 

No. 113—MINOR BALANCES OF EXPENDITURE.

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

2 of 1951/52

Improvement of Entrance

...

...

...

...

...

1

6

4

7,602

0

2

7,602

6

6

Completed.

 

Department of An Taoiseach:

 

 

 

 

 

 

 

 

 

 

92/6 of 1951/52

Central Statistics Office, Dublin Castle—Improvements

...

746

13

4

393

19

4

1,140

12

8

Completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

92/13 of 1951/52

10 Hume Street—Electric Storage Heating

...

...

167

8

4

515

11

7

682

19

11

Completed

92/15 of 1951/52

51 St. Stephen’s Green—Engineers Branch New Office

...

155

0

0

455

16

6

610

16

6

Completed.

 

Revenue Commissioners:

 

 

 

 

 

 

 

 

 

 

4 of 1951/52

Dublin Castle—Renovations

...

...

...

...

523

6

7

4,500

18

0

5,024

4

7

Completed.

 

General:

 

 

 

 

 

 

 

 

 

 

3 of 1950/51 3 of 1951/52

Iveagh House—Office Accommodation and Staff Restaurant

13,221

13

4

82,231

4

10

95,452

18

2

Completed.

5 of 1951/52

Dublin Custom House—Improvement of lay-out of Grounds

273

10

1

8,291

4

1

8,564

14

2

Completed.

91/73 of 1950/51 6/73 of 1951/52

Dublin Custom House—Staff Restaurant

...

...

...

1,436

0

1

7,279

18

7

8,715

18

8

In progress.

92/22 of 1951/52

Papal Nunciature—Extension of Accommodation

...

...

542

17

9

693

6

0

1,236

3

9

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

140/4 of 1950/51

Government Buildings—Provision of improved

 

 

 

 

 

 

 

 

 

 

93 of 1951/52

accommodation for typing staff, etc.

...

...

...

...

...

1,163

9

10

1,621

15

9

2,785

5

7

Completed.

92/8 of 1951/52

Botanic Gardens—Electriclighting sheds and boiler house

...

52

10

9

487

12

2

540

2

11

Completed.

23 of 1951/52

Ballyhaise Agricultural College—New Piggeries

...

...

55

15

0

7,635

17

7

7,691

12

7

Completed.

25 of 1951/52

Clonakilty Agricultural College—Poultry Hatchery

...

163

14

2

2,361

1

4

2,524

15

6

Completed.

92/14 of 1951/52

Fisheries Branch—Accommodation for Parliamentary

 

 

 

 

 

 

 

 

 

 

 

Secretary

...

...

...

...

...

...

...

...

56

6

6

562

4

10

618

11

4

Completed.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

47 of 1949/50

Public Record Office—Restoration of Air-raid shelter as Record

 

 

 

 

 

 

 

 

 

 

141 of 1950/51

Repository

...

...

...

...

...

...

...

209

19

10

121

17

7

331

17

5

Completed.

 


Work No.

Service and Description

Expenditure

Observations

1952-53

to 31/3/52

to 31/3/53

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Courts of Justice:

 

 

 

 

 

 

 

 

 

 

233/10 of 1949/50

Adaptation of rooms

...

...

...

...

...

37

10

0

1,083

11

2

1,121

1

2

Completed.

39a of 1951/52

Audibility Improvements at Metropolitan District Courts

...

511

8

7

21

7

3

532

15

10

In progress.

92/11 of 1951/52

Structural Alterations etc., at Restaurant

...

...

467

10

8

1,981

9

7

2,449

0

3

Completed.

 

Garda Síochána:

 

 

 

 

 

 

 

 

 

 

233/1 of 1949/50

Headquarters—Transfer to Depot

...

...

...

...

19

0

7

18,801

3

2

18,820

3

9

Completed.

36 of 1951/52

Dublin Castle—Garage Accommodation

...

...

...

697

6

2

268

2

5

965

8

7

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

40a of 1951/52

Headquarters Office—Adaptations

...

...

...

...

1,958

19

0

376

4

3

2,335

3

3

Completed.

44 of 1951/52

National Gallery—Electric Installation

...

...

...

212

10

10

6,263

16

7

6,476

7

5

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

105 of 1950/51

Headquarters Buildings—Adaptations

...

...

...

104

4

1

10,869

14

2

10,973

18

3

Completed.

 

Gaeltacht Services Branch:

 

 

 

 

 

 

 

 

 

 

141 of 1949/50

Bruckless Lace Centre—Renovation and extension

...

76

15

0

1,554

18

5

1,631

13

5

Completed.

107 of 1950/51

Geesala Knitting Centre—Improvements

...

...

...

 

14

10

1,570

5

5

1,571

0

3

Completed.

46 of 1951/52

Elly Bay Toy Factory—Rebuilding

...

...

...

75

14

10

5,602

14

10

5,678

9

8

Completed.

48 of 1951/52

Falcarragh Knitting Centre—Adaptations

...

...

...

150

4

11

1,331

15

9

1,482

0

8

Completed.

92/16 of 1951/52

Carratigue Knitting Centre—Improvements

...

...

108

16

3

250

0

0

358

16

3

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

111 of 1950/51

Kildare Street—New Headquarters

...

...

...

...

33

0

0

255,748

4

3

255,781

4

3

Completed.

140/1 of 1950/51

Kildare Street—Provision of water storage tank

...

...

152

3

7

1,593

4

3

1,745

7

10

Completed.

140/12 of 1950/51

Griffith Barracks—Adaptations, etc., for Prices Advisory Body

1

1

0

4,176

12

6

4,177

13

6

Completed.

234 of 1949/50

Meteorological Services—Fencing, etc., of Rainfall Gauges

...

8

0

0

689

18

8

697

18

8

Completed.

 

Department of Posts and Telegraphs:*

 

 

 

 

 

 

 

 

 

 

119 of 1950/51

Dundalk Post Office—Improvements

...

...

...

...

51

6

9

4,278

6

4

4,329

13

1

Completed.

121 of 1950/51

Loughrea Post Office—Adaptations

...

...

...

...

1

17

11

1,164

3

1

1,166

1

0

Completed.

122 of 1950/51

Nenagh Post Office—Improvements

...

...

...

...

80

0

0

1,132

11

11

1,212

11

11

Completed.

63 of 1951/52

Boyle Post Office—Adaptations

...

...

...

...

19

15

9

340

0

0

359

15

9

Completed.

71 of 1951/52

Wexford Post Office—Adaptations

...

...

...

...

115

18

0

354

3

3

470

1

3

Completed.

92/1 of 1951/52

Newbridge Military Barracks—Adaptations for Stores

...

55

9

5

841

14

7

897

4

0

Completed.

92/18 of 1951/52

Caherciveen Post Office—Adaptations

...

...

...

300

0

0

452

10

0

752

10

0

Completed.

92/19 of 1951/52

Glencree former Reformatory—Adaptations for Stores

...

276

6

0

450

0

0

726

6

0

In progress.

186/10 of 1947/48

Wireless Broadcasting—Adaptation of Portobello former Post

 

 

 

 

 

 

 

 

 

 

 

Office

...

...

...

...

...

...

...

24

6

3

870

5

0

894

11

3

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

140/16 of 1950/51

School of Defence—Adaptations, etc.

...

...

...

233

14

10

1,543

19

1

1,777

13

11

Completed.

77 of 1951/52

Collins Barracks, Cork—Married Quarters

...

...

...

7

10

0

26,710

12

10

26,718

2

10

Completed.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

233/180 of 1949/50

Lisbon Legation—Improvements, etc.

...

...

...

7

6

4

3,871

9

9

3,878

16

1

Completed.

92/24 of 1951/52

Stockholm Legation—Works and Furniture

...

...

465

9

0

817

4

5

1,282

13

5

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

134 of 1950/51 84 of 1951/52

Kilkenny Employment Exchange—Adaptations

...

...

378

16

8

712

10

0

1,091

6

8

Completed.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

89 of 1951/52

Dundrum Asylum—Improved Cooking Facilities

...

...

627

19

11

1,296

7

11

1,924

7

10

Completed.

92/25 of 1951/52

Dundrum Asylum—Recreation Room for Attendants

...

68

12

0

33

19

9

102

11

9

Completed.

 

 

£26,099

1

1

 

 

 

 

 

 

 

*Excluding amount chargeable to Telephone Capital.


†Excluding amount chargeable to Telephone Capital and Vote for Posts and Telegraphs.


‡Excluding amount chargeable to Vote for Posts and Telegraphs.


*Excluding amounts, if any, chargeable to Telephone Capital Account.


*Excluding amount chargeable to Telephone Capital Account.