Committee Reports::Report - Appropriation Accounts 1950 - 1951::26 February, 1953::Appendix

APPENDIX IV.

STATEMENT OF EXPENDITURE ON NEW WORKS, ALTERATIONS AND ADDITIONS, 1950-51 (VOTE 9, SUBHEAD B.)

Work

 

Total

Vote

Expenditure

 

No.

Service and Description

Estimate

1950-51

 

 

 

 

 

 

 

 

 

Observations

 

 

 

 

1950-51

to 31/3/50

to 31/3/51

 

 

 

£

£

£

s.

d.

£

s.

d.

£

s.

d.

 

 

President’s Establishment:

 

 

 

 

 

 

 

 

 

 

 

 

1

Arus an Uachtaráin—Improvements

 

 

 

 

 

 

 

 

 

 

 

 

 

and Furnishing

...

...

...

92,000

3,680

2,777

0

7

50,884

16

1

53,661

16

8

In progress.

 

 

 

3,680

2,777

0

7

 

 

 

 

 

 

 

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

 

 

2

Improvement of Entrance

...

...

8,000

820

1,226

1

0

6,333

17

11

7,559

18

11

Completed.

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

 

 

3

Dublin, Iveagh House—Office accommodation and Staff Restaurant

81,500

30,000

33,087

7

4

28,433

2

11

61,520

10

3

In progress.

4

Dublin Castle—Renovations

...

...

550

3

13

6

3

13

6

Preliminary work.

5

Dublin Custom House—Improvement

 

 

 

 

 

 

 

 

 

 

 

 

 

of lay out of Grounds

...

...

8,500

1,500

2,825

5

6

5,415

1

11

8,240

7

5

Virtually completed.

6

Dublin Custom House—West

 

 

 

 

 

 

 

 

 

 

 

 

 

Courtyard Approach—Alterations

...

450

450

477

4

9

477

4

9

In progress.

7

Dublin Inland Revenue, 14/15 Upper O’Connell Street—Additional Sanitary

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

500

500

485

5

0

485

5

0

In progress.

8

Lifford Customs and Excise—Official

 

 

 

 

 

 

 

 

 

 

 

 

 

Garage and Married Quarters

...

9,200

3,000

1,767

5

8

6,834

0

5

8,601

6

1

In progress.

9

Waterford Government Offices—

 

 

 

 

 

 

 

 

 

 

 

 

 

Erection

...

...

...

...

182,100

5,000

2,331

11

1

6,157

2

9

2,331


6,157

11


2

1


9

This work is now combined with Waterford Post Office, previously a separate work. In progress.

10

Office of Public Works—Central Engineering Workshop and Stores—

 

 

 

 

 

 

 

 

 

 

 

 

 

New premises

...

...

...

...

252,500

20,000

10,585

7

1

11,288

18

5

21,874

5

6

In progress.

11

Cenotaph

...

...

...

...

13,000

12,000

15,971

17

9

6,666

1

5

22,637

19

2

In progress.

 

Harbours:

 

 

 

 

 

 

 

 

 

 

 

 

12

Buncrana—Improvements

...

...

1,050

1,050

Postponed.

13

Dun Laoghaire—Provision of Crane

...

8,600

8,600

Postponed.

14

Dun Laoghaire—Public Lighting

...

2,300

2,300

Postponed.

 

 

 

£84,950

£67,534

17

8

 

 

 

 

 

 

 

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

 

 

15

Fisheries Branch—2 Kildare Place—

 

 

 

 

 

 

 

 

 

 

 

 

 

Installation of Laboratory

...

450

450

790

7

6

56

11

4

846

18

10

In progress.

16

Land Rehabilitation Section—

 

 

 

 

 

 

 

 

 

 

 

 

 

Additional accommodation

...

...

...

1,000

1,000

848

19

1

848

19

1

In progress.

17

Botanic Gardens—Erection of New

 

 

 

 

 

 

 

 

 

 

 

 

 

Fern House

...

...

...

...

6,000

5,000

20

9

8

20

9

8

Preliminary work.

18

Athenry Agricultural School—Poultry

 

 

 

 

 

 

 

 

 

 

 

 

 

Hatchery

...

...

...

...

3,550

3,500

Postponed.

19

Athenry Agricultural School—

 

 

 

 

 

 

 

 

 

 

 

 

 

Provision of Electric Power

...

...

480

350

52

16

6

130

13

3

183

9

9

In progress.

20

Ballyhaise Agricultural School—New

 

 

 

 

 

 

 

 

 

 

 

 

 

Piggeries

...

...

...

...

7,500

5,000

3,151

6

3

1,962

3

5

5,113

9

8

In progress.

21

Clonakilty Agricultural School—

 

 

 

 

 

 

 

 

 

 

 

 

 

Poultry Hatchery

...

...

...

3,125

3,000

3

2

9

3

2

9

Preliminary work.

22

Grange Stud and Dairy Farm—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations

...

...

...

...

21,000

5,000

1,910

17

8

1,910

17

8

In progress.

23

Johnstown Castle—Adaptations and

 

 

 

 

 

 

 

 

 

 

 

 

 

Renovations

...

...

...

...

85,000

36,000

22,050

15

6

53,188

12

11

75,239

8

5

In progress.

24

Munster Institute—Introduction of

 

 

 

 

 

 

 

 

 

 

 

 

 

Shannon Electric Power

...

...

2,500

350

338

2

6

1,115

4

7

1,453

7

1

In progress.

25

Munster Institute—Poultry Hatchery

4,500

4,500

Postponed.

26

Veterinary College—Improvements

...

123,000

1,650

3,863

17

10

72,237

9

10

76,101

7

8

In progress.

27

Veterinary Research Institute—New

 

 

 

 

 

 

 

 

 

 

 

 

 

Premises

...

...

...

...

4,000

1,032

17

7

1,032

17

7

Not proceeded with.

27(a)

Athenry Agricultural Station—

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation for Course for Adults

...

3,300

1,120

18

4

1,120

18

4

In progress.

27(c)

Grange Farm—Cow Byres

...

...

2,100

1,125

0

0

1,125

0

0

In progress.

 

Fishery, Etc., Harbours:

 

 

 

 

 

 

 

 

 

 

 

 

28

Dredging Operations—Arklow Harbour

9,400

7,000

2,068

6

1

2,068

6

1

In progress.

29

Works of Economic Development—

 

 

 

 

 

 

 

 

 

 

 

 

 

Greencastle Harbour

...

9,500

7,000

339

8

9

339

8

9

In progress.

 

 

 

83,800

37,684

8

5

 

 

 

 

 

 

 

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

 

 

30

Gárda Síochana Depot—New Electrical

 

 

 

 

 

 

 

 

 

 

 

 

 

Distribution System

...

...

1,000

1,000

53

12

0

53

12

0

Preliminary Work.

 

Garda Siochana Barracks:

 

 

 

 

 

 

 

 

 

 

 

 

31

Dublin Metropolitan Area Harcourt Terrace (Lad Lane)—New

 

 

 

 

 

 

 

 

 

 

 

 

 

Barracks

...

...

...

...

30,000

3,000

2,353

15

2

28,893

10

0

31,247

5

2

Completed.

32

Kilmainham—Adaptations

...

...

800

800

200

0

0

200

0

0

In progress.

33

Stillorgan—New Barrack

...

...

10,000

10

188

14

10

188

14

10

Postponed.

 

Co. Cavan:

 

 

 

 

 

 

 

 

 

 

 

 

34

Blacklion—New Barrack

...

...

5,000

10

1

13

9

1

13

9

Preliminary Work.

35

Swanlinbar—New Barrack

...

...

6,000

10

Postponed.

 

Co. Clare:

 

 

 

 

 

 

 

 

 

 

 

 

36

Ardnacrusha—New Barrack

...

...

800

700

Postponed.

37

Connolly—New Barrack

...

...

5,000

10

Postponed.

38

Doolin—New Barrack

...

...

...

4,000

10

8

5

10

8

5

10

Preliminary Work

39

Feakle—New Barrack

...

...

...

10

Postponed.

40

Labasheeda—New Barrack

...

...

10

Postponed.

41

Newmarket-on-Fergus—New Barrack

10,000

10

1

5

0

1

5

0

Postponed.

42

Tulla—New Barrack

...

...

5,000

10

 

4

0

 

4

0

Postponed.

 

Co. Cork:

 

 

 

 

 

 

 

 

 

 

 

 

43

Knocknagree—New Barrack

...

...

5,000

10

Postponed.

44

Liscarroll—New Barrack

...

...

5,000

10

Postponed.

45

Watergrasshill—New Barrack

...

5,000

10

Postponed.

 

Co. Donegal

 

 

 

 

 

 

 

 

 

 

 

 

46

Bundoran—New Barrack

5,500

2,500

Postponed.

47

Carrigans—Adaptations

10

 

4

2

2

1

6

2

5

8

Preliminary Work.

48

Carrigart—New Barrack

...

...

6,000

10

Postponed.

49

Castlefin—New Barrack

...

...

6,000

10

2

9

9

8

4

4

10

14

1

Preliminary Work.

50

Churchill—New Barrack

...

...

5,500

2,200

2,260

3

9

2,916

9

8

5,176

13

5

In progress.

51

Clogher—Adaptations

...

...

600

10

 

17

4

 

17

4

Preliminary Work.

52

Dungloe—Adaptations

...

...

500

10

Postponed.

53

Glencolumbkille—Adaptations

...

600

10

Postponed.

54

Glenties—Adaptations

...

...

400

10

Postponed.

55

Kilmacrennan—New Barrack

...

5,500

10

18

7

2

18

7

2

Preliminary Work.

56

Milford—Adaptations

...

...

...

950

10

Postponed.

 

Co. Dublin:

 

 

 

 

 

 

 

 

 

 

 

 

57

Lucan—Improvements

...

...

1,250

1,250

997

17

6

997

17

6

In progress.

 

Co. Galway

 

 

 

 

 

 

 

 

 

 

 

 

58

Ardrahan—Adaptations

...

...

1,300

10

10

3

8

10

3

8

Preliminary Work.

59

Athenry—New Barrack

...

...

12,000

10

 

12

10

2

17

11

3

10

9

Preliminary Work.

60

Lettermore—Adaptations

...

...

10

1

8

7

1

8

7

Postponed.

61

Portumna—New Barrack

...

...

5,000

10

Postponed.

62

Roundstone—New Barrack

...

...

5,500

10

8

6

8

8

6

8

Preliminary Work.

 

Co. Kerry:

 

 

 

 

 

 

 

 

 

 

 

 

63

Kilgarvan—New Barrack

...

...

5,000

10

Postponed.

64

Knocknagoshel—New Barrack

...

5,000

10

Postponed.

 

Co. Kilkenny:

 

 

 

 

 

 

 

 

 

 

 

 

65

Freshford—New Barrack

...

...

6,000

10

15

10

0

15

10

0

Postponed.

 

Laoighis:

 

 

 

 

 

 

 

 

 

 

 

 

66

Mountrath—New Barrack

...

...

5,250

2,770

 

2

11

 

2

11

Preliminary Work.

 

Co. Leitrim:

 

 

 

 

 

 

 

 

 

 

 

 

67

Ballinamore—New Barrack

...

...

6,000

10

Postponed.

68

Cloone—New Barrack

...

...

...

5,500

10

 

9

10

 

9

10

Postponed.

69

Drumsna—New Barrack

...

...

6,400

10

Postponed.

 

Co. Longford:

 

 

 

 

 

 

 

 

 

 

 

 

70

Lanesboro’—New Barrack

...

...

5,500

10

Postponed.

 

Co. Louth:

 

 

 

 

 

 

 

 

 

 

 

 

71

Ballymascanlon—New Barrack

...

10

Postponed.

72

Castlebellingham—New Barrack

...

5,000

10

Postponed.

 

Co. Mayo:

 

 

 

 

 

 

 

 

 

 

 

 

73

Achill Sound—New Barrack

...

...

4,050

250

51

15

0

3,796

19

7

3,848

14

7

Completed.

74

Kilkelly—New Barrack

...

...

10

3

13

10

3

13

10

Postponed.

75

Kilmaine—New Barrack

...

...

5,000

3,400

3,740

0

0

500

17

5

4,240

17

5

In progress.

 

Co. Monaghan:

 

 

 

 

 

 

 

 

 

 

 

 

76

Ballybay—New Barrack

...

...

5,500

10

3

5

0

3

5

0

Postponed.

77

Newbliss—New Barrack

...

...

4,500

10

Postponed.

 

Offaly:

 

 

 

 

 

 

 

 

 

 

 

 

78

Cloghan—New Barrack

...

...

5,500

10

2

0

0

2

0

0

Postponed.

79

Mountbolus—New Barrack

...

...

5,000

10

Postponed.

80

Shannonbridge—New Barrack

...

6,000

10

Postponed.

 

Co. Roscommon:

 

 

 

 

 

 

 

 

 

 

 

 

81

Kilmore—New Barrack

...

...

5,000

10

Postponed.

82

Roscommon—New Barrack

...

...

35,000

10,000

2,580

15

2

2,580

15

2

Demolition work

83

Strokestown—New Barrack

...

...

17,000

10

Postponed.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

 

 

84

Ballinafad—New Barrack

...

...

6,000

10

Postponed.

85

Collooney—New Barrack

...

...

6,100

10

Postponed.

86

Enniscrone—New Barrack

...

...

11,150

600

717

19

6

11,992

1

8

12,710

1

2

Completed.

87

Strandhill—New Barrack

...

...

5,500

10

Postponed.

 

Co. Tipperary:

 

 

 

 

 

 

 

 

 

 

 

 

88

Mullinahone—New Barrack

...

5,000

10

2

11

6

2

11

6

Preliminary Work.

89

Thurles—New Barrack

...

...

32,500

4,000

5

13

10

5

13

10

Preliminary Work.

 

Co. Waterford

 

 

 

 

 

 

 

 

 

 

 

 

90

Aglish—New Barrack

...

...

10

Postponed.

91

Waterford—New Barrack

...

...

99,000

10

279

3

6

664

7

11

943

11

5

In progress.

 

Co. Westmeath:

 

 

 

 

 

 

 

 

 

 

 

 

92

Rochfortbridge—New Barrack

...

10

 

6

7

 

6

7

Preliminary Work.

 

Co. Wexford:

 

 

 

 

 

 

 

 

 

 

 

 

93

Coolgreany—Adaptations

...

...

10

6

5

9

6

5

9

Preliminary Work.

94

New Ross—New Barrack

...

...

16,000

12,000

1,160

4

4

20

0

0

1,180

4

4

In progress.

 

Co. Wicklow:

 

 

 

 

 

 

 

 

 

 

 

 

95

Ashford—New Barrack

...

...

10

Postponed.

96

Baltinglass—New Barrack

...

...

17,000

6,000

 

5

6

 

5

6

Postponed.

97

Roundwood—New Barrack

...

...

5,000

10

Postponed.

98

New Works, Alterations and Additions at other Garda Síochána Barracks

5,000

3,479

10

8

33,810

2

8

37,289

13

4

 

99

Minor New Works at Garda Síochána

 

 

 

 

 

 

 

 

 

 

 

 

 

Barracks

...

...

...

...

4,000

1,198

13

11

709

19

9

1,908

13

8

 

 

 

 

£60,000

£16,504

10

4

 

 

 

 

 

 

 

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

 

100

St. Joseph’s (West Dublin Model)

 

 

 

 

 

 

 

 

 

 

 

 

 

School—Electric Lighting

...

...

500

500

239

0

0

239

0

0

In progress.

101

National Schools—Grants for

 

 

 

 

 

 

 

 

 

 

 

 

 

Building, Enlarging, Enclosing, etc.

...

750,000

700,000

530,312

15

8

530,312

15

8

Expenditure represents grants which matured for payment.

102

Coláiste Moibhi, Shanganagh Castle,

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations and Renovations

...

59,000

15,000

284

17

1

14,921

2

4

15,205

19

5

In progress.

103

National Gallery—Electric Installation

6,000

180

441

17

4

5,821

19

3

6,263

16

7

In progress.

104

Reformatory School, Daingean—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptions

...

...

...

...

...

63,500

9,000

85

16

1

29,874

13

8

29,960

9

9

In progress.

104a

Council of Education

...

...

...

500

471

19

9

471

19

9

In progress.

 

 

 

£724,680

£531,836

5

11

 

 

 

 

 

 

 

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

 

 

105

Headquarters Buildings—Adaptations

11,100

1,450

1,948

1

10

8,231

12

1

10,179

13

11

In progress.

 

Gaeltacht Services:

 

 

 

 

 

 

 

 

 

 

 

 

106

Elly Bay Toy Factory—Rebuilding

4,600

3,000

2,777

8

8

1,782

15

0

4,560

3

8

In progress.

107

Geesala Knitting Centre—

 

 

 

 

 

 

 

 

 

 

 

 

 

Improvements

...

...

...

...

1,650

1,650

1,360

19

1

1,360

19

1

In progress.

108

New Spinning Factory, Kilcar, Co.

 

 

 

 

 

 

 

 

 

 

 

 

 

Donegal

...

...

...

...

60,250

7,700

2,775

9

3

38,572

3

0

41,347

12

3

In progress.

109

Spiddal Toy Factory—Adaptations

...

1,090

350

577

15

9

727

9

9

1,305

5

6

In progress.

110

Tourmakeady Knitting Centre—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations

...

...

...

...

6,250

2,000

28

2

9

235

19

4

264

2

1

Preliminary work.

 

 

 

£16,150

£9,467

17

4

 

 

 

 

 

 

 

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

 

 

111

New Headquarters, Kildare Street

...

256,000

500

571

8

5

255,054

17

2

255,626

5

7

In progress.

112

Industrial Development Authority—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations

...

...

...

...

2,700

350

238

11

4

2,268

1

9

2,506

13

1

In progress.

113

Valentia Observatory—Adaptations

 

 

 

 

 

 

 

 

 

 

 

 

 

and additions

...

...

...

50,000

1,100

790

4

4

395

6

4

1,185

10

8

In progress.

 

 

 

£1,950

£1,600

4

1

 

 

 

 

 

 

 

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

 

 

114

Dublin, New Post Office, St. Andrew

 

 

 

 

 

 

 

 

 

 

 

 

 

Street

...

...

...

...

...

33,000

16,000

9,577

3

5

5,575

3

6

15,152

6

11

In progress.

115

Dublin, Pearse Street Sorting Office—

 

 

 

 

 

 

 

 

 

 

 

 

 

Extension of Postmen’s Office

...

4,500

700

803

7

10

3,555

5

1

4,358

12

11

In progress.

116

Dublin P. O. Factory—Rebuilding, etc.

52,000

6,000

3,641

2

11

2,909

18

10

6,551

1

9

In progress.

117

Cork Head Post Office—Improvements

13,250

11,300

1,496

15

1

3,471

4

11

4,968

0

0

In progress.

118

Drogheda New Post Office and

 

 

 

 

 

 

 

 

 

 

 

 

 

Telephone Exchange

...

...

...

30,000

500

4

3

6

9

13

8

13

17

2

Preliminary Work.

119

Dundalk Post Office—Improvements

...

3,950

1,950

2,112

19

10

1,930

0

0

4,042

19

10

In progress.

120

Kilrush New Post Office

...

...

600

Postponed.

121

Loughrea Post Office—Adaptations

...

1,200

1,200

1,154

17

0

1,154

17

0

In progress.

122

Nenagh Post Office—Improvements

...

920

900

723

0

6

27

16

11

750

17

5

In progress.

123

Rathluirc Post Office—Adaptations

15,000

500

Postponed.

124

Improved Sorting Equipment at Post

 

 

 

 

 

 

 

 

 

 

 

 

 

Offices

...

...

...

...

15,500

10,250

5,052

5

3

5,052

5

3

In progress.

 

Wireless Broadcasting:

 

 

 

 

 

 

 

 

 

 

 

 

125

Dublin G.P.O. Studio and Office

 

 

 

 

 

 

 

 

 

 

 

 

 

Accommodation

...

...

...

13,450

7,200

2,710

7

0

6,106

5

9

8,816

12

9

In progress.

126

Dublin, Phoenix Hall, Exchequer Street

 

 

 

 

 

 

 

 

 

 

 

 

 

—Adaptations

...

...

...

6,950

500

30

11

5

4,034

11

6

4,065

2

11

In progress.

127

Athlone High Power Short Wave

 

 

 

 

 

 

 

 

 

 

 

 

 

Station

...

...

...

...

18,235

250

17,733

7

8

17,733

7

8

In progress.

 

 

 

£57,850

£27,306

13

9

 

 

 

 

 

 

 

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

 

 

128

Dublin G.H.Q. Parkgate Street—

 

 

 

 

 

 

 

 

 

 

 

 

 

Storage

...

...

...

...

500

500

350

0

0

350

0

0

In progress.

129

Clancy Barracks — Installation of

 

 

 

 

 

 

 

 

 

 

 

 

 

Heating in Lower Barrack

...

5,000

5,000

4,154

4

3

692

11

8

4,846

15

11

In progress.

130

Baldonnell Camp—Re-roofing Hangar

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 4

...

...

...

...

30,000

20,000

9,162

4

3

16,801

1

5

25,963

5

8

In progress.

131

Cork Collins Barrack—Junior Officers’

 

 

 

 

 

 

 

 

 

 

 

 

 

Married Quarters

...

...

...

25,845

20,000

18,331

18

3

4,247

1

2

22,578

19

5

In progress.

132

Haulbowline Dockyard—New Jetty

...

70,000

50,000

10,251

1

9

15,570

2

1

25,821

3

10

In progress.

132a

Curragh Camp—Extension of Magazines

76,860

6,359

2

4

759

19

3

7,119

1

7

In progress.

 

 

 

£95,500

£48,608

10

10

 

 

 

 

 

 

 

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

 

 

133

Ballina Employment Exchange—

 

 

 

 

 

 

 

 

 

 

 

 

 

Erection

...

...

...

...

25,000

2,000

Postponed.

134

Kilkenny Employment Exchange—

 

 

 

 

 

 

 

 

 

 

 

 

 

Adaptations

...

...

...

...

1,500

1,750

678

0

0

678

0

0

In progress.

135

Waterford Employment Exchange—

 

 

 

 

 

 

 

 

 

 

 

 

 

Erection

...

...

...

...

51,800

10,000

649

18

0

337

2

9

987

0

9

Preliminary Work.

 

 

 

£13,750

£1,327

18

0

 

 

 

 

 

 

 

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

 

 

136

Dundrum Asylum—Adaptations to

 

 

 

 

 

 

 

 

 

 

 

 

 

provide Infirmary Unit

...

...

1,900

1,900

Postponed.

137

Dundrum Asylum—Improved Cooking

 

 

 

 

 

 

 

 

 

 

 

 

 

Facilities

...

...

...

...

1,300

1,300

8

12

6

8

12

6

Preliminary

138

Dundrum Asylum—Improvements to

 

 

 

 

 

 

 

 

 

 

 

Work.

 

Governor’s Residence

...

...

1,100

900

1,079

11

0

168

10

0

1,248

1

0

In progress.

 

 

 

£4,100

£1,088

3

6

 

 

 

 

 

 

 

139

Minor New Works:

...

...

...

12,000

7,587

12

6

1,561

0

7

9,148

13

1

 

140

Urgent and Unforeseen Works:

...

20,000

10,319

11

3

10,319

11

3

 

141

Minor Balance of Expenditure on

 

 

 

 

 

 

 

 

 

 

 

 

 

Works of Prior Years:

...

...

7,500

15,915

8

4

69,938

0

7

85,853

8

11

 

 

 

 

£1,186,730

£780,785

3

6

 

 

 

 

 

 

 

 

Deduct for Works which may not be

 

 

 

 

 

 

 

 

 

 

 

 

 

carried out during the year

...

20,730

 

 

 

 

 

 

 

 

 

 

£1,166,000

£780,785

3

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 98—NEW WORKS, ALTERATIONS AND ADDITIONS AT OTHER GARDA SIOCHANA BARRACKS.

No.

Service and Description

Expenditure

Observations

1950-51

to 31/3/50

to 31/3/51

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Metropolitan Area:

 

 

 

 

 

 

 

 

 

 

1

Dublin Castle, Detective Branch—Adaptations, etc.

699

1

8

699

1

8

In progress.

44 of 1949/50

Garda Síochána Depot—Extension of Hospital

...

137

2

9

137

2

9

Preliminary Work.

 

Co. Cavan:

 

 

 

 

 

 

 

 

 

 

53 of 1949/50

Kilnaleck—New Barrack

...

...

...

...

463

0

0

3,867

4

9

4,330

4

9

Completed.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

70 of 1949/50

Convoy—New Barrack

...

...

...

...

849

16

11

5,257

12

4

6,107

9

3

Completed.

 

Co. Mayo:

 

 

 

 

 

 

 

 

 

 

95 of 1949/50

Ballycastle—New Barrack

...

...

...

...

69

5

6

4,118

7

11

4,187

13

5

Completed.

 

Co. Meath:

 

 

 

 

 

 

 

 

 

 

99 of 1949/50

Trim—New Barrack

...

...

...

...

...

920

3

10

17,011

10

1

17,931

13

11

Completed.

 

Co. Monaghan

 

 

 

 

 

 

 

 

 

 

2

Monaghan—Adaptations

...

...

...

...

330

0

0

330

0

0

Completed.

 

Co. Roscommon:

 

 

 

 

 

 

 

 

 

 

105 of 1949/50

Athleague—New Barrack

...

...

...

...

11

0

0

3,555

7

7

3,566

7

7

Completed.

 

 

£3,479

10

8

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 99—MINOR NEW WORKS AT GARDA SIOCHANA BARRACKS.

No.

Service and Description

Expenditure

Observations

1950-51

to 31/3/50

to 31/3/51

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Metropolitan Area:

 

 

 

 

 

 

 

 

 

 

120/12 of 1948/49

Dublin Castle and other Garda Barracks—Installation of Teleprinters and incidental structural works, etc.

7

10

0

224

11

9

232

1

9

In progress.

124/5 of 1949/50

Dublin Castle—Adaptation of former Riding School

 

 

 

 

 

 

 

 

 

 

 

as a Garage

...

...

...

...

...

1

6

4

161

16

4

163

2

8

In progress.

124/4 of 1949/50

College Street—Improvements to Electric Lighting, provision of additional sanitary accommodation

 

 

 

 

 

 

 

 

 

 

 

and of shelving

...

...

...

...

...

22

16

0

243

16

2

266

12

2

Completed.

7

Store Street—Improvements

...

...

...

...

45

8

5

45

8

5

Completed.

 

Co. Carlow:

 

 

 

 

 

 

 

 

 

 

2

Borris—New Sanitary fittings, painting, etc.

...

293

18

2

293

18

2

Completed.

 

Co. Donegal:

 

 

 

 

 

 

 

 

 

 

6

Pettigo—Catch Drain

...

...

...

...

...

150

0

0

150

0

0

Completed.

 

Co. Dublin:

 

 

 

 

 

 

 

 

 

 

9

Dun Laoghaire—Provision of independent boiler and

 

 

 

 

 

 

 

 

 

 

 

drying room

...

...

...

...

...

11

18

10

11

18

10

Completed.

 

Co. Kildare:

 

 

 

 

 

 

 

 

 

 

4

Kildare—Provision of screen and internal sanitary

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

137

13

11

137

13

11

Completed.

 

Co. Kilkenny:

 

 

 

 

 

 

 

 

 

 

8

Castlecomer—New concrete path

...

...

...

146

6

0

146

6

0

Completed.

 

Co. Sligo:

 

 

 

 

 

 

 

 

 

 

3

Sligo—Alterations to provide office accommodation

 

 

 

 

 

 

 

 

 

 

 

for Garda Superintendent and his staff

...

...

180

0

0

180

0

0

Completed.

 

Co. Waterford:

 

 

 

 

 

 

 

 

 

 

1

Tramore—Provision of baths, hot water system, etc.

201

16

3

201

16

3

Completed.

 

 

£1,198

13

11

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 139—MINOR NEW WORKS.

No.

Service and Description

Expenditure

Observations

1950-51

to 31/3/50

to 31/3/51

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

232/14 of 1949/50

Central Heating Station—Provision of carbon

 

 

 

 

 

 

 

 

 

 

 

di-oxide indicators and recorders

...

...

...

35

5

7

200

0

0

235

5

7

Completed.

 

Office of Public Works:

 

 

 

 

 

 

 

 

 

 

5

(a) Provision of cubicle for Superintending Clerk

103

0

2

103

0

2

Completed.

6

(b) Provision of lift from Registry

...

...

134

19

7

134

19

7

Completed.

14

(c) Phoenix Park—Provision of gas supply at Fort

 

 

 

 

 

 

 

 

 

 

 

Lodge and Deerkeeper’s Lodge

...

...

...

215

0

4

215

0

4

Completed.

38

(d) Phoenix Park—Electrical Installation in Lodges

310

11

9

310

11

9

Completed.

21

(e) District Office, Portlaoighise—Provision of

 

 

 

 

 

 

 

 

 

 

 

extra room, furniture, etc.

...

...

...

304

19

5

304

19

5

Completed.

30

Valuation Office—Provision of new outside staircase

309

0

0

309

0

0

Completed.

34

Stationery Office—Provision of Shelving

...

...

132

4

4

132

4

4

Completed.

 

Revenue Department:

 

 

 

 

 

 

 

 

 

 

48

(a) Custom House, Dublin—Filing accommodation

65

16

4

65

16

4

Completed.

 

(b) 11-13 Upper O’Connell Street, Dublin—

 

 

 

 

 

 

 

 

 

 

 

Installation of Hot Water System

...

...

102

19

9

102

19

9

Completed.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

23

Government Buildings, West Block—Provision of

 

 

 

 

 

 

 

 

 

 

 

Porch in Room 13

...

...

...

...

...

98

0

4

98

0

4

Completed.

28

Government Buildings, South Block—Provision of

 

 

 

 

 

 

 

 

 

 

 

Enquiry Office

...

...

...

...

...

261

18

9

261

18

9

Completed.

59

Fisheries Branch—2.3 Kildare Place—Provision of

 

 

 

 

 

 

 

 

 

 

 

Messenger’s box

...

...

...

...

...

14

15

3

14

15

3

In progress.

232/19 of 1949/50

Ballyhaise Agricultural Station—Provision of

 

 

 

 

 

 

 

 

 

 

 

Laboratory Bench

...

...

...

...

...

37

3

6

175

0

0

212

3

6

Completed.

10

Botanic Gardens—Erection of additional shelving

 

 

 

 

 

 

 

 

 

 

 

and provision of store

...

...

...

...

128

19

10

128

19

10

Completed.

13

Clonakilty Agricultural School—Provision of lunch

 

 

 

 

 

 

 

 

 

 

 

room for farm workers

...

...

...

...

229

17

11

229

17

11

Completed.

27

Munster Institute—Erection of ctesiphon house for

 

 

 

 

 

 

 

 

 

 

 

poultry

...

...

...

...

...

...

...

1

3

7

1

3

7

Preliminary Work.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

43

Four Courts—County Registrar, improved

 

 

 

 

 

 

 

 

 

 

 

accommodation

...

...

...

...

...

...

487

1

4

487

1

4

Completed.

44

Courts of Justice—Central Scrivenery Office— alterations in connection with installation of photostat

 

 

 

 

 

 

 

 

 

 

 

machine

...

...

...

...

...

...

150

4

10

150

4

10

In progress.

232/25 of 1949/50

38 Mountjoy Square, Dublin—Preparation of rooms

 

 

 

 

 

 

 

 

 

 

 

and supply of furniture for Probation Officers

...

22

13

3

134

17

11

157

11

2

Completed.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

 

National Museum—

 

 

 

 

 

 

 

 

 

 

185/36 of 1947/48

(a) Installation of Italian Statuary.

...

...

28

0

0

416

4

3

444

4

3

Completed.

15

(b) Alterations to Costume Exhibition case

...

172

11

4

172

11

4

Completed.

37

(c) Improved lighting in Loom Room and Folk

 

 

 

 

 

 

 

 

 

 

 

Room

...

...

...

...

...

...

233

7

4

233

7

4

Completed.

 

National College of Art—

 

 

 

 

 

 

 

 

 

 

2

(a) Structural alterations and improvements in

 

 

 

 

 

 

 

 

 

 

 

heating and lighting

...

...

...

...

130

14

1

130

14

1

In progress.

29

(b) Provision of Enquiry Office in Hall

...

...

111

10

1

111

10

1

In progress.

51

(c) Adaptation of two rooms to accommodate new

 

 

 

 

 

 

 

 

 

 

 

class

...

...

...

...

...

...

89

1

0

89

1

0

Completed.

17

National Gallery—Improvements to Caretaker’s

 

 

 

 

 

 

 

 

 

 

 

quarters

...

...

...

...

...

...

342

9

2

342

9

2

Completed.

 

National Library—

 

 

 

 

 

 

 

 

 

 

8

(a) Erection of partition and shelving in Map Room

150

4

8

150

4

8

Completed.

35

(b) Provision of Shelving and Lighting in Exhibition

 

 

 

 

 

 

 

 

 

 

 

Room

...

...

...

...

...

...

308

11

5

308

11

5

Completed.

16

Coláiste Einne—Installation of New Boiler

...

...

238

13

4

238

13

4

Completed.

46

Genealogical Office—Electrical installation and

 

 

 

 

 

 

 

 

 

 

 

building up door opes

...

...

...

...

...

90

7

2

90

7

2

Completed.

55

National Education Office—General repairs,

 

 

 

 

 

 

 

 

 

 

 

redecoration, etc., at Gatekeeper’s Lodge

...

...

...

62

2

10

62

2

10

In progress.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

24

24 Upper Merrion Street—Erection of partition, etc.,

 

 

 

 

 

 

 

 

 

 

 

in Enquiry Office

...

...

...

...

...

93

13

3

93

13

3

Completed.

 

Gaeltacht Services:

 

 

 

 

 

 

 

 

 

 

18

(a) Dunlop House—Erection of steel angle iron

...

232

16

0

232

16

0

Completed.

32

(b) Elly Bay Toy Factory—Provision of tank and

 

 

 

 

 

 

 

 

 

 

 

Petrol Pump

...

...

...

...

...

124

11

0

124

11

0

Completed.

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

32/232 of 1949/50

Griffith Barracks—Preparation of rooms for rationing

 

 

 

 

 

 

 

 

 

 

 

section

...

...

...

...

...

...

...

26

4

4

153

6

1

179

10

5

Completed.

20

44-45 Merrion Square—Additions and alterations

...

98

1

6

98

1

6

Completed.

39

Kildare Street—Sound proofing of copying rooms and

 

 

 

 

 

 

 

 

 

 

 

erection of indoor porch

...

...

...

...

157

7

4

157

7

4

In progress.

42

27 Eden Quay—Alterations

...

...

...

...

28

11

9

28

11

9

In progress.

47

Kildare Street—Provision of protective bars to ground

 

 

 

 

 

 

 

 

 

 

 

floor windows at West Side

...

...

...

...

111

0

0

111

0

0

Completed.

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

23/232 of 1949/50

10 Parnell Square, Dublin—Structural work in

 

 

 

 

 

 

 

 

 

 

 

connection with installation of lift

...

...

...

26

3

7

100

0

0

126

3

7

Completed.

33

Ballsbridge Post Office—Improvements to sorting

 

 

 

 

 

 

 

 

 

 

 

office, retiring rooms, public office, etc.

...

...

357

19

11

357

19

11

Completed.

45

Carrick-on-Shannon Post Office—Erection of glazed

 

 

 

 

 

 

 

 

 

 

 

enclosure in sorting office

...

...

...

...

146

12

6

146

12

6

Completed.

53

Pearse Street, Dublin—Provision of additional

 

 

 

 

 

 

 

 

 

 

 

accommodation for bicycles

...

...

...

...

11

6

0

11

6

0

Preliminary work.

58

133-136 Capel Street, Dublin—Preparation of floors

 

 

 

 

 

 

 

 

 

 

 

to take machines, alterations to doors, etc.

...

8

19

7

8

19

7

In progress.

69

Aldborough House—Provision of new entrance gate

 

 

 

 

 

 

 

 

 

 

 

and sloping footpath

...

...

...

...

99

12

10

99

12

10

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

9/232 of 1949/50

G.H.Q., Parkgate Street—Fitting doors to shelving in

 

 

 

 

 

 

 

 

 

 

 

Archives Section

...

...

...

...

...

73

16

2

42

2

9

115

18

11

Completed.

22

G.H.Q. Annexe—Provision of wash-hand basin, etc.

122

14

7

122

14

7

Completed.

49

G.H.Q.—Fitting plugs for electric dictating and

 

 

 

 

 

 

 

 

 

 

 

transcribing machines

...

...

...

...

...

114

19

3

114

19

3

Completed.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

21/232 of 1949/50

Werburgh Street Employment Exchange—

 

 

 

 

 

 

 

 

 

 

 

Improvement of Heating System

...

...

...

...

 

18

6

226

5

5

227

3

11

Completed.

31

Limerick Employment Exchange—Improvement of

 

 

 

 

 

 

 

 

 

 

 

electric installation

...

...

...

...

...

284

17

3

284

17

3

In progress.

54

Belmullet Employment Exchange—Provision of

 

 

 

 

 

 

 

 

 

 

 

additional lighting points, shelving, furniture, etc.

...

 

4

6

 

4

6

Preliminary work.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

29/232 of 1949/50

Custom House, Dublin—Provision of electric plugs

 

 

 

 

 

 

 

 

 

 

 

for wire recorders and supply of cabinets

...

...

197

16

2

113

4

2

311

0

4

In progress.

9

Custom House—Extension of Dictograph Facilities

...

163

4

10

163

4

10

Completed.

66

Dundrum Asylum—Improvements to clinical offices

 

 

 

 

 

 

 

 

 

 

 

and sleeping quarters of female attendants

...

2

13

5

2

13

5

Preliminary work.

 

 

£7,587

12

6

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 140—URGENT AND UNFORESEEN WORKS.

No.

Service and Description

Expenditure

Observations

1950-51

to 31/3/50

to 31/3/51

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

15

Revenue Department—Custom House, Dublin—

 

 

 

 

 

 

 

 

 

 

 

Provision of Staff restaurant

...

...

...

...

434

6

8

434

6

8

In progress.

18

Stationery Office—Installation of rotaprint machines,

 

 

 

 

 

 

 

 

 

 

 

etc.

...

...

...

...

...

...

45

1

5

45

1

5

In progress.

5

Office of Public Works—Phoenix Park, provision of

 

 

 

 

 

 

 

 

 

 

 

shelters for relief Gate keepers

...

...

...

4

5

11

4

5

11

Preliminary work.

 

Comptroller and Auditor General

 

 

 

 

 

 

 

 

 

 

3

32 Upper Merrion Street—Adaptations

...

...

1,174

13

3

1,174

13

3

In progress.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

4

Government Buildings—Provision of improved accommodation for typing staff, supply of furniture, and

 

 

 

 

 

 

 

 

 

 

 

provision of additional sanitary accommodation

...

997

0

3

997

0

3

In progress.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

7

23 Upper Merrion Street—Provision of additional sanitary accommodation on top floor of concrete

 

 

 

 

 

 

 

 

 

 

 

building

...

...

...

...

...

...

479

4

4

479

4

4

In progress.

11

Gaeltacht Services—Kilcar, Co. Donegal—

 

 

 

 

 

 

 

 

 

 

 

Adaptations

...

...

...

...

...

...

...

120

13

11

120

13

11

In progress. (Sanction of £1,750 includes cost of house).

 

Department of Industry and Commerce:

 

 

 

 

 

 

 

 

 

 

1

Kildare Street—Provision of new water storage tank

1,030

19

6

1,030

19

6

In progress.

12

Griffith Barracks—Adaptations and Redecoration,

 

 

 

 

 

 

 

 

 

 

 

etc.

...

...

...

...

...

...

...

2,848

2

4

2,848

2

4

In progress.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

10

Saint Bricin’s Hospital—Provision of new Lift and

 

 

 

 

 

 

 

 

 

 

 

Motor Room

...

...

...

...

...

...

8

2

6

8

2

6

Preliminary expenditure.

16

Ratra, Phoenix Park—Adaptations and provision of

 

 

 

 

 

 

 

 

 

 

 

furniture

...

...

...

...

...

...

378

3

9

378

3

9

In progress.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

6

London Embassy—Adaptation of 17 Grosvenor Place,

 

 

 

 

 

 

 

 

 

 

 

supply of furniture

...

...

...

...

2,591

0

9

2,591

0

9

In progress.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

2

Dundrum Asylum—Provision of two airing

 

 

 

 

 

 

 

 

 

 

 

courts

...

...

...

...

...

...

...

207

16

8

207

16

8

In progress.

 

 

£10,319

11

3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

No. 141—MINOR BALANCES OF EXPENDITURE.

No.

Service and Description

Expenditure

Observations

1950-51

to 31/3/50

to 31/3/51

 

 

£

s.

d.

£

s.

d.

£

s.

d.

 

 

Houses of the Oireachtas:

 

 

 

 

 

 

 

 

 

 

3 of 1949/50

(a) Preparation of busts of Pádraig Pearse and

 

 

 

 

 

 

 

 

 

 

 

and other National Leaders

...

...

...

180

4

4

1,286

9

9

1,466

14

1

In progress.

4 of 1948/49

(b) Extension of Electric Clock System

...

...

53

7

3

520

6

4

573

13

7

Completed.

234 of 1949/50

 

 

 

 

 

 

 

 

 

 

 

 

Department of Finance:

 

 

 

 

 

 

 

 

 

 

21 of 1948/49

Central Heating of Government Establishments—

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

Conversion to oil burning

...

...

...

...

517

10

0

15,004

15

4

15,522

5

4

In progress

239/12 of 1948/49

2-3 Merrion Square Adaptations

...

...

...

35

4

9

2,198

9

3

2,233

14

0

Completed.

234 of 1949/50

 

 

 

 

 

 

 

 

 

 

 

229/15 of 1948/49

Revenue Department—11-15 Upper O’Connell St.,

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

Dublin, 14/15 St. Andrew St. and Dublin Castle

 

 

 

 

 

 

 

 

 

 

 

—Adaptations and furniture

...

...

...

...

1,145

2

3

2,819

13

1

3,964

15

4

In progress.

 

Department of Agriculture:

 

 

 

 

 

 

 

 

 

 

233/40 of 1949/50

Government Buildings, Dublin—Alterations and adaptations to provide additional accommodation

115

15

5

1,102

5

9

1,218

1

2

In progress.

25 of 1949/50

Kildare Place—Central Heating

...

...

...

58

2

0

645

17

6

703

19

6

Completed.

28 of 1949/50

Athenry Agricultural Station—Improvement of Water

 

 

 

 

 

 

 

 

 

 

 

Supply

...

...

...

...

...

...

339

10

8

72

1

3

411

11

11

Consulting

 

 

 

 

 

 

 

 

 

 

 

Engineers’ Fees.

31 of 1949/50

Clonakilty Agricultural Station—New Buildings

...

22

5

0

241

16

9

264

1

9

In progress (water supply.)

38 of 1949/50

Veterinary Research Laboratory—Additional Cold

 

 

 

 

 

 

 

 

 

 

 

Storage, etc.

...

...

...

...

...

543

17

3

72

12

7

616

9

10

In progress

39 of 1949/50

Glenties Fish Hatchery—improvements to Manager’s

 

 

 

 

 

 

 

 

 

 

 

House

...

...

...

...

...

...

170

0

0

129

17

2

299

17

2

In progress.

35 of 1949/50

Munster Institute—Improved accommodation

...

92

2

11

33

5

3

125

8

2

Completed.

 

Department of Justice:

 

 

 

 

 

 

 

 

 

 

233/1 of 1949/50

Garda Síochána Headquarters—Alterations and

 

 

 

 

 

 

 

 

 

 

 

Improvements

...

...

...

...

...

4,517

8

10

13,985

6

2

18,502

15

0

In progress.

233/10 of 1949/50

Four Courts—Adaptation of rooms in Circuit Court

 

 

 

 

 

 

 

 

 

 

 

Building

...

...

...

...

...

...

204

14

6

867

6

7

1,072

1

1

In progress.

47 of 1949/50

Public Record Office—Restoration of air raid shelter

 

 

 

 

 

 

 

 

 

 

 

as record repository

...

...

...

...

...

81

17

0

40

0

7

121

17

7

In progress.

 

Department of Education:

 

 

 

 

 

 

 

 

 

 

95 of 1946/47

Coláiste Einne—Improvements

...

...

...

480

13

6

553

4

8

1,033

18

2

Completed.

234 of 1949/50

 

 

 

 

 

 

 

 

 

 

 

 

Department of Local Government:

 

 

 

 

 

 

 

 

 

 

229/8 of 1948/49

Custom House, Dublin—Adaptations and provision

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

of Dictaphone machines

...

...

...

...

412

4

8

1,309

3

2

1,721

7

10

Completed.

 

Department of Lands:

 

 

 

 

 

 

 

 

 

 

229/9 of 1948/49

21 Upper Merrion Street—Provision of Luncheon

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

Club and equipment

...

...

...

...

...

765

1

4

1,769

9

7

2,534

10

11

In progress.

 

Gaeltacht Industries:

 

 

 

 

 

 

 

 

 

 

141 of 1949/50

(a) Bruckless Lace and Embroidery centre—

 

 

 

 

 

 

 

 

 

 

 

Renovation and Extension

...

...

...

...

215

2

0

953

0

11

1,168

2

11

In progress.

143 of 1949/50

(b) Crolly Toy Factory—Provision of Water Supply,

 

 

 

 

 

 

 

 

 

 

 

sanitary accommodation, etc.

...

...

...

 

15

4

100

17

10

101

13

2

Preliminary Work.

139 of 1949/50

(c) Annagry Factory—Renovation and adaptation

...

247

12

0

1,789

2

2

2,036

14

2

Completed.

138 of 1949/50

(d) Dublin Central Marketing Depot—Alterations

 

 

 

 

 

 

 

 

 

 

 

and improvements

...

...

...

...

33

3

11

719

0

8

752

4

7

Completed.

 

Department of Posts and Telegraphs:

 

 

 

 

 

 

 

 

 

 

233/16 of 1949/50

Provision of improved Sorting Fittings at Post Offices

7

11

0

516

15

7

524

6

7

In progress.

233/20 of 1949/50

Leitrim House, Dublin—Conversion of store and lofts

 

 

 

 

 

 

 

 

 

 

 

to drawing office

...

...

...

...

...

20

16

11

418

2

5

438

19

4

Completed.

162 of 1949/50

Birr Post Office—Adaptations

...

...

...

...

4

5

10

22

0

0

26

5

10

In progress.

186/10 of 1947/48 230 of 1948/49

Wireless Broadcasting—Adaptation of former Portobello Bridge Post Office premises for use as an

 

 

 

 

 

 

 

 

 

 

 

additional Broadcasting Studio

...

...

...

...

1

6

9

821

10

7

822

17

4

In progress.

155 of 1949/50

Dublin Engineering Branch, Distillery Road—

 

 

 

 

 

 

 

 

 

 

 

Adaptations

...

...

...

...

...

...

...

1

4

5

114

9

5

115

13

10

Preliminary Work.

165 of 1949/50

Claremorris Post Office—Extension

...

...

8

4

2

1,300

6

6

1,308

10

8

Completed.

 

Department of Defence:

 

 

 

 

 

 

 

 

 

 

206 of 1949/50

Curragh Camp—New Married Quarters

...

...

292

12

4

11,951

17

2

12,244

9

6

Completed.

160/28 of 1948/47

26 Westland Row, Dublin—Provision of

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

accommodation and furniture for Bureau of Military History

...

 

5

8

926

9

2

926

14

10

Completed.

233/13 of 1949/50

Coláiste Caoimhin—Preparation of room and provision of furniture for the Pensions Referee Advisory

 

 

 

 

 

 

 

 

 

 

 

Committee and staff

...

...

...

...

...

256

9

6

135

1

5

391

10

11

Completed.

 

Department of External Affairs:

 

 

 

 

 

 

 

 

 

 

233/21 of 1949/50

Iveagh House—Supply and installation of Chandeliers

318

5

0

150

0

11

468

5

11

Completed.

229/7 of 1948/49

Iveagh House—Adaptation and supply of furniture,

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

etc., to meet accommodation for extra staff

...

22

17

6

3,402

0

9

3,424

18

3

Completed.

233/18 of 1949/50

Lisbon Legation—Improvements to official residence

 

 

 

 

 

 

 

 

 

 

 

and supply of furniture

...

...

...

...

667

1

11

1,603

18

7

2,271

0

6

In progress.

229 of 1948/49

Ottawa Legation—Repairs, decoration and furnishing

363

14

6

9,072

13

8

9,436

8

2

Completed.

233 of 1949/50

Washington Legation—Adaptation and furnishing

2,545

12

0

7,824

8

3

10,370

0

3

In progress.

 

Department of Social Welfare:

 

 

 

 

 

 

 

 

 

 

220 of 1949/50

Dublin Employment Exchange, Werburgh Street—

 

 

 

 

 

 

 

 

 

 

 

Additional sanitary accommodation

...

...

389

7

4

550

2

11

939

10

3

Completed.

219 of 1949/50

Dublin Employment Exchange, Lower Gardiner

 

 

 

 

 

 

 

 

 

 

 

Street—Electrical Rewiring

...

...

...

...

290

17

0

543

7

6

834

4

6

In progress.

233/6 of 1949/50

Dunfanaghy Employment Exchange, Co. Donegal—

 

 

 

 

 

 

 

 

 

 

 

Alterations and improvements and provision of

 

 

 

 

 

 

 

 

 

 

 

furniture

...

...

...

...

...

...

243

8

2

144

16

2

388

4

4

In progress.

 

Department of Health:

 

 

 

 

 

 

 

 

 

 

229/18 of 1948/49

Custom House, Dublin—Re-arrangement of

 

 

 

 

 

 

 

 

 

 

234 of 1949/50

accommodation involving structural alterations

...

249

13

5

686

7

8

936

1

1

Completed.

 

 

£15,915

8

4